Application Review Schedule for Kendrick

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Strata Energy, Inc. submitted to obtain a license for its Kendrick In Situ Recovery expansion.

Key Milestones Completion Date
Actual – A
Target – T
Application Tendered 04/28/15 – A
Acceptance Review
Acceptance Review Start
09/30/15 – A
Docketing Decision Letter Issued/Acceptance Review Complete
01/14/16 – A
Safety Review *
Requests for Additional Information (RAIs) Issued to Applicant
09/14/16 – A
RAI Acceptance by NRC Staff
See Note Below
Final Safety Evaluation Report (SER) completed
See Note Below
Environmental Review
RAIs Issued to Applicant
05/27/16 – A
Draft Environmental Impact Statement (EIS) Issued
See Note Below
Final EIS Issued
See Note Below
License Amendment issued
See Note Below

* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.

NOTE: Review suspended as of December 21, 2016, at the request of the applicant.

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.