ACTIVE Generic issue that involves actions under the GIP DROP Issue dropped from further pursuit as a generic issue EI Environmental issue
GSI Generic safety issue LI Licensing issue
MEDIUM Medium safety priority
NOTE 5 Issue that is not a generic safety issue but should be assigned resources for completion. As clarified by SECY-11-0101, Summary of Activities Related to Generic Issues Program, dated July 26, 2011, Generic Issues Program will not pursue any further actions toward resolution of Licensing and Regulatory impact issues.
RI Regulatory impact issue
ROI Regulatory office implementation: A formal GI for which RES actions of safety/risk assessment or regulatory assessment are complete and remaining actions reside with program offices (e.g., regulatory compliance, reactor oversight process, rulemaking, further research, coordination with industry initiatives)
RWRP Resolved with regulatory product RWORP Resolved without regulatory product USI Unresolved safety issue
Action Item / Issue Group | Legacy Program | Active | ROI | Action Completed | Total | ||||||
NOTE 5 | MEDIUM | RWRP | RWORP | DROP | NOTE 5 | NUREG- 0737 | Covered by Other Issues | ||||
TMI ACTION PLAN ITEMS (369) | |||||||||||
GSI | - | - | - | 66 | 69 | 21 | - | 84 | 46 | 286 | |
LI | - | - | - | - | 75 | - | 8 | - | - | 83 | |
TASK PLANNING ACTION ITEMS (142) | |||||||||||
USI | - | - | - | - | 27 | - | - | - | - | 27 | |
GSI | - | - | - | - | 36 | 14 | - | - | 20 | 70 | |
RI | - | - | - | - | 6 | - | 1 | - | - | 7 | |
LI | - | - | - | - | 11 | - | 12 | - | - | 23 | |
EI | 2 | - | - | - | 13 | - | - | - | - | 15 | |
NEW GENERIC ISSUES (284) |
Action Item / Issue Group | Legacy Program | Active | ROI | Action Completed | Total | ||||||
NOTE 5 | MEDIUM | RWRP | RWORP | DROP | NOTE 5 | NUREG- 0737 | Covered by Other Issues | ||||
GSI | - | 1 | 2 | 3 | 24 | 66 | 108 | - | - | 54 | 258 |
RI | - | - | - | - | 5 | 1 | 5 | - | 1 | 12 | |
LI | - | - | - | - | 8 | - | 4 | - | 1 | 13 | |
EI | 1 | - | - | - | - | - | - | - | - | 1 | |
HUMAN FACTORS ISSUES (27) | |||||||||||
GSI | - | - | - | - | 1 | 7 | - | - | - | 8 | 16 |
LI | - | - | - | - | 3 | - | 8 | - | - | 11 | |
CHERNOBYL ISSUES (32) | |||||||||||
LI | - | - | - | - | 7 | - | 23 | - | 2 | 32 | |
NUCLEAR MATERIAL SAFETY AND SAFEGUARDS ISSUES (22) | |||||||||||
22 | |||||||||||
TOTAL | 3 | 1 | 2 | 3 | 423 | 144 | 61 | 84 | 132 | 876 |
[1] SECY-81-513, "Plan for Early Resolution of Safety Issues," U.S. Nuclear Regulatory Commission, August 25, 1981. [8109140067]
Page Last Reviewed/Updated 06/24/2025