Approved Power Uprate Application Information For Ginna

The following table refers to NRC-approved power uprate applications. The table shows the ADAMS accession number for (1) each plant's power uprate application, (2) any supplement to the application, and (3) the license amendment approving the application and allowing the licensee to increase power. These documents illustrate the information that the NRC staff requires in order to complete a power uprate review.

NRC encourages licensees to review the documents listed in the table before preparing a power uprate application. Addressing the information contained in these documents below may improve the quality of the application, thereby reducing the number of RAIs, and expedite the staff's review.

On this page:

Ginna Nuclear Power Station
License No. DPR-18 (Docket No. 50-244)

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Application Information

Date Description Adams
Accession No.
07/07/2005 License Amendment Request Regarding Extended Power Uprate ML051950123

To top of page

Supplement Information

Date Description Adams
Accession No.
08/15/2005 Supplemental Information Related to Small Break (SB) Loss of Coolant Accident (LOCA) Analysis and Post-LOCA Boric Acid Precipitation Analysis ML052310155
09/30/2005 Large Transient Tests Associated with License Amendment Request Regarding Extended Power Uprate ML052800223
12/06/2005 Response to Requests for Additional Information Regarding Topics Described by Letter Dated October 25, 2005 ML053480388
12/09/2005 Response to Requests for Additional Information Regarding Revised Loss-of-Coolant-Accident Analyses ML053480362
12/22/2005 Response to Requests for Additional Information Regarding Topics Described by Letter Dated November 10, 2005 ML053640080
01/11/2006 Supplemental Response to Requests for Additional Information Regarding Topics Described by Letters Dated August 24, 2005 and October 28, 2005 ML060180262
01/25/2006 Response to Requests for Additional Information Regarding Topics Described in Meeting Minutes ML060960416
02/16/2006 Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls ML060540349
03/03/2006 Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls ML060810218
03/24/2006 Response to BOP Systems Questions Discussed on March 2, 2006 Conference Call ML060940312
05/09/2006 Response to Requests for Additional Information Reqarding Topics Discussed on Conference Calls for Extended Power Uprate (EPU) ML061350375
05/19/2006 Final Response to Requests for Additional Information Regardinq Topics Discussed on Conference Calls for Extended Power Uprate (EPU) ML061450381

To top of page

Amendment Information

Date Description Adams
Accession No.
07/11/2006 Amendment No. 97 Re: 16.8 Percent Power Uprate (TAC No. MC7382) ML061380133

To top of page