The objective of this task was to provide instrumentation to monitor plant variables and systems during and following an accident. Indications of plant variables and status of systems important to safety are required by the plant operator (licensee) …
1
TASK III.A.1: IMPROVE LICENSEE EMERGENCY PREPAREDNESS - SHORT-TERM The objectives of this task were to improve and upgrade licensee emergency preparedness by requiring improvements in facilities, plans, procedures, offsite support, technical assistance, …
1
The objective of this task was to upgrade the emergency preparedness of nuclear power plants. Specific criteria to meet this objective were delineated in NUREG-0654. [1] ITEM III.A.2.1: AMEND 10 CFR 50 AND 10 CFR 50, APPENDIX E The four parts of this item …
1
The objective of this task is to enable NRC, in the event of a nuclear accident at a licensed reactor facility, to: (1) monitor and evaluate the situation and potential hazards, (2) advise the licensee's operating staff as needed, and (3) in an extreme …
1
The objective of this task is to upgrade the state of emergency preparedness of State and local governments affected by nuclear facilities. The Federal Emergency Management Agency was given the lead on this effort by the President on December 7, 1979. …
1
The objectives of this task are: (1) to have information available for the news media and the public describing how nuclear plants operate, radiation and its health effects, and protective actions against radiation; and (2) to provide training for members …
1
DESCRIPTION By letter dated June 18, 1975, licensees of operating reactor facilities were sent a preliminary copy of a staff paper, "Guidance for Proposed License Amendments Relating to Refueling," and "Refueling Information Request Form." The purpose was …
1
DESCRIPTION Historical Background This NUREG-0371 [1] item involves the development of consistent and formalized acceptance criteria regarding the conversion to higher density storage racks (increased storage capacity) in existing spent fuel storage …
1
DESCRIPTION Historical Background Individual reactor fuel rods sometimes fail during normal operations and many fuel rods are expected to fail during severe accidents. To ensure that these fuel failures do not result in unacceptable releases to the …
1
DESCRIPTION This NUREG-0471 [1] task covers a spectrum of technical efforts related to the staff review of LMFBR fuel designs. The efforts include: (1) evaluating licensing requirements for the behavior of stainless steel cladding and hexcans in an LMFBR …
1
DESCRIPTION The fuel assembly is a highly nonlinear structure which can be subjected to substantial loadings during seismic excitations and LOCA transients. The integrity of this assembly is critical for plant safety. Extensive work has been completed by …
1
DESCRIPTION Present NRC actions taken in response to a serious incident are directed from an Incident Response Center (IRC). To implement an adequate response, it is necessary that the IRC be equipped with appropriate communications services, information …
1
DESCRIPTION BWRs are operated in such a manner as to attempt to produce an axial power distribution with as little peaking as possible. When the reactor moderator is not boiling (e.g., during startup and heatup), the axial flux distribution is much more …
1
DESCRIPTION Historical Background On April 7, 1980, Arkansas Nuclear One (ANO) Units 1 and 2 experienced a significant event resulting from a loss of offsite power. Although both units were safely shut down, the analysis and evaluation of the event …
1
DESCRIPTION Historical Background In response to a 1967 ACRS concern relative to the potential of melting and subsequent disintegration of a portion of a fuel assembly due to inlet orifice flow blockage, GE submitted NEDO-10174 [1] in May 1970. As a …
1
DESCRIPTION Historical Background This issue was initiated to address concerns raised by the Union of Concerned Scientists. (References [1] , [2] , and [3] .) The purposes for including this issue as a generic issue are to: (1) provide brief background …
1
DESCRIPTION Historical Background Experiments conducted at several test facilities prior to 1984 showed that irradiated fuel can fragment (crumble) into small pieces during a LOCA. Some evaluation of this effect was made for NRC by EG&G. [1] Although it …
1
DESCRIPTION Historical Background Following the TMI-2 accident, the NRC converted its fuel behavior research program into a severe accident research program and, consequently, no further confirmatory work on fuel damage criteria was pursued. However, some …
1
DESCRIPTION On August 24, 1992, Hurricane Andrew hit south Florida and caused extensive onsite and offsite damage at Turkey Point. Following this hurricane which was classified Category 4, an NRC/industry team was organized to: (1) review the damage …
1
DESCRIPTION Core design is a fundamental component of plant safety because maintaining fuel integrity is the first principal safety barrier (i.e., fuel cladding, reactor coolant system boundary, or the containment) against serious radioactive releases. …
1
DESCRIPTION The objective of this task was to respond to the Regulatory Review Group (RRG) Item #55. The RRG recommendations were to provide quicker review of core reload codes and to revise existing TS to permit changes, in accordance with approved core …
1
DESCRIPTION Historical Background This issue was identified [1] following an NRR request for reconsideration of the safety priority ranking (DROP) of GSI-22, "Inadvertent Boron Dilution Events," based on new information on high burn-up fuel and new …
1
This task, outlined in Chapter 1 of NUREG-1251, [1] called for the staff to review the administrative controls over plant operations in the U.S. to determine if adequate controls are in place to maintain plant conditions within the safe operating …
1
A number of facts about the Chernobyl accident have some bearing on emergency planning and preparedness around U.S. commercial nuclear power plants. This task, outlined in Chapter 4 of NUREG-1251, [1] called for the staff to examine the implications of …