DESCRIPTION The concern of this issue involves the requirement for verification that the balance-of-plant equipment satisfies the design intent. This issue was identified in NUREG-0705. [1] CONCLUSION Task I.F in NUREG-0660, [2] the TMI Action Plan, is a …
DESCRIPTION Historical Background Cracking has occurred in PWR piping systems as a result of stress corrosion, vibratory and thermal fatigue, and dynamic loading. However, as of February 1981, no cracking had been experienced in the primary system piping …
DESCRIPTION Historical Background Prior to 1981, the number of bolting-related incidents reported by licensees was on the increase. A large number of these were related to primary pressure boundary applications and major component support structures. As a …
DESCRIPTION Historical Background On April 7, 1980, Arkansas Nuclear One (ANO) Units 1 and 2 experienced a significant event resulting from a loss of offsite power. Although both units were safely shut down, the analysis and evaluation of the event …
DESCRIPTION Historical Background Cracks were found in the normal make-up high pressure injection (MU/HPI) nozzles of several B&W plants following an inspection of the 8 B&W plants licensed to operate. These cracks appeared to be directly related to loose …
DESCRIPTION Historical Background PORVs and block valves were originally designed as non-safety components in the reactor pressure control system for use only when plants are in operation. The block valves were installed because of expected leakage from …
DESCRIPTION Historical Background On two occasions (February 22 and 25, 1983), Salem Unit 1 failed to scram automatically due to failure of both reactor trip breakers to open on receipt of an actuation signal. In both cases, the unit was successfully …
DESCRIPTION Historical Background Over the past several years, the NRC staff has noted an unacceptably large number of overexposures and uncontrolled exposures associated with pressurized water reactor cavity entries while incore detectors were withdrawn. …
DESCRIPTION Historical Background This issue was raised [1] in March 1985 to address the staff's concern that there were no requirements for dynamic qualification testing or dynamic surveillance testing of large bore hydraulic snubbers (> 50 kips load …
DESCRIPTION Historical Background This issue was identified in the U.S. Nuclear Regulatory Commission (NRC) incident investigation team (IIT) report on the loss of integrated control system (ICS) power event at Rancho Seco Nuclear Generating Station …
DESCRIPTION The TMI-2 Safety Advisory Board was established to provide the licensee, General Public Utilities Nuclear Corporation, with a qualified, independent appraisal of the cleanup of TMI-2, with particular emphasis on the assurance of public and …
DESCRIPTION Historical Background This issue was identified [1] by NRR after reactor operating experience and research results on MOVs, SOVs, AOVs, and HOVs indicated that testing under static conditions did not always reveal how these valves would …
This issue has two parts that were evaluated separately. ISSUE 174.A: SONGS EMPLOYEES' CONCERN DESCRIPTION Historical Background A San Onofre Nuclear Generating Station (SONGS) employee filed a concern with the SONGS Employee Program concerning the …
DESCRIPTION Core design is a fundamental component of plant safety because maintaining fuel integrity is the first principal safety barrier (i.e., fuel cladding, reactor coolant system boundary, or the containment) against serious radioactive releases. …
DESCRIPTION NRC regulatory requirements include the estimation of individual offsite dose from the design basis LOCA. The fission product source term in TID-14844 [1] which is referenced by the regulations, has historically been used for this application. …
DESCRIPTION Historical Background This GI was proposed [1] in response to a concern raised by the ACRS in its May 21, 2004, report on the resolution of certain NUREG-1740 [2] items. The ACRS recommended that the staff develop a mechanistic understanding …