Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Search Results

Displaying 1 - 10 of 13

EA-98-464 - Clinton (Illinois Power Company)

… EA-98-464 - Clinton (Illinois Power Company) … September 30, 1999 EA 98-464 Mr. John P. McElwain Chief Nuclear Officer Clinton Power Station Illinois Power Company Mail Code V-275 P. O. Box 678 …

EA-96-412 - Clinton (Illinois Power Company)

… EA-96-412 - Clinton (Illinois Power Company) … June 9, 1997 EAs 96-412, 97-001, 97-002, … 30, 1996, through January 23, 1997, at the Clinton Power Station (CPS). The inspections included evaluations and …

EA-97-132 - Clinton (Illinois Power Company)

… EA-97-132 - Clinton (Illinois Power Company) … August 1, 1997 EA 97-132 Mr. John G. Cook … 6, 1997, through March 7, 1997, at the Clinton Power Station (CPS). The inspection included aspects of …

EA-03-030 - Clinton (AmerGen Energy Co., LLC)

… EA-03-030 - Clinton (AmerGen Energy Co., LLC) … May 6, 2003 EA-03-030 … 4300 Winfield Road Warrenville, IL 60555 SUBJECT: CLINTON POWER STATION NOTICE OF VIOLATION - NRC INSPECTION REPORT …

NOEDs Issued to Power Reactor Licensees

… NOEDs Issued to Power Reactor Licensees … On this page: 2025 |  2024 | 2023 … NOTICE OF ENFORCEMENT DISCRETION FOR HOPE CREEK GENERATING STATION (EPID: L-2025-LLD-0002)  2024 Confirmation Date NOED … 01-1-001 Hope Creek (PSEG Nuclear, LLC) 01/18/2001 01-6-001 Clinton (AmerGen Energy Company, LLC) 2000 Confirmation Date …

Escalated Enforcement Actions Issued to Reactor Licensees - C

… information. Callaway Calvert Cliffs 1 & 2 Catawba 1 & 2 Clinton Columbia Generating Station Comanche Peak 1 & 2 Cooper Crystal River 3 Callaway … Date Issued Description EA-23-097 Calvert Cliffs Nuclear Power Plant     NOV (White) 10/26/2023 On October 26, 2023, …

EA-05-103 - LaSalle 1 and 2 (Exelon Nuclear)

… REPORT 05000373/2005010; 05000374/2005010), LASALLE COUNTY STATION, UNITS 1 AND 2 Dear Mr. Crane: The purpose of this … that could result in a loss of all onsite and offsite power sources to both 4160 Vac Division 1 and Division 2 … - Mid-West Regional   Operating Group Manager Licensing - Clinton and LaSalle Senior Counsel, Nuclear, Mid-West …