Skip to main content

NOEDs Issued to Power Reactor Licensees

On this page:

| 2026 | 20252024 | 202320222021 | 2020 |
| 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 |
| 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2003 | 2002 | 2001 | 2000 |

2026

Confirmation DateNOED NumberFacility (Licensee)
06/24/2026EAF-RIV-2026-0060NOTICE OF ENFORCEMENT DISCRETION FOR WATERFORD STEAM ELECTRIC STATION (EPID L-2026-LLD-0004)
02/05/2026EAF-RIV-2026-0013NOTICE OF ENFORCEMENT DISCRETION FOR COOPER NUCLEAR STATION (EPID L-2026-LLD-0001)

2025

Confirmation DateNOED NumberFacility (Licensee)
11/19/2025EAF-RII-2025-0197NOTICE OF ENFORCEMENT DISCRETION (NOED) FOR VIRGIL C. SUMMER NUCLEAR PLANT, UNIT 1 (EPID: L-2025-LLD-0007)
02/05/2025EAF-RI-2025-0048NOTICE OF ENFORCEMENT DISCRETION FOR HOPE CREEK GENERATING STATION (EPID: L-2025-LLD-0002) 

2024

Confirmation DateNOED NumberFacility (Licensee)
09/26/2024EA-24-113Notice of Enforcement Discretion for James A. Fitzpatrick Nuclear Power Plant (EPID: L-2024-lLD-0005)
08/29/2024EA-24-091Notice Of Enforcement Discretion For Wolf Creek Generating Station
04/02/2024EA-24-036Cooper Nuclear Station (EPID L-2024-LLD-0003)
03/25/2024EA-24-033Diablo Canyon Power Plant, Unit 2 (EPID L-2024-LLD-0002)
03/05/2024EA-24-027Seabrook Station, Unit 1 (EPID L-2024-033)

2023

Confirmation DateNOED NumberFacility (Licensee)
07/26/2023EA-23-091Fermi Power Plant, Unit 2 (EPID L-2023-LLD-0002)
06/08/2023EA-23-067Fermi Power Plant, Unit Two (EPID L-2023-LLD-0000)

To top of page

2022

Confirmation DateNOED NumberFacility (Licensee)
12/30/2022EA-22-137Davis-Besse Nuclear Power Station, Unit 1 (EPID L-2022-LLD-0008)
07/27/2022EA-22-073Surry Power Station, Units 1 and 2 (EPID I 2022 003 0023 AND EPID L 2022 LLD 0006)
07/26/2022EA-22-072Sequoyah Nuclear Plant, Unit 1 (EPID I-2022-003-0027 and EPID L-2022-LLD-0005)
01/31/2022EA-22-008Millstone Power Station, Unit 3 (EPID: L-2022-LLD-0000)

To top of page

2021

Confirmation DateNOED NumberFacility (Licensee)
09/28/2021EA-21-138
Enclosure
Seabrook Station, UNIT NO. 1:  Notice Of Enforcement Discretion (NOED) (EPID: L-2021-LLA-0168)
03/04/2021EA-21-024Donald C. Cook Nuclear Plant, Units 1 and 2 (EPID: L-2021-LLD-0000)

To top of page

2020

Confirmation DateNOED NumberFacility (Licensee)
07/01/2020EA-20-089Wolf Creek Generating Station (Wolf Creek Nuclear Operating Corporation)

To top of page

2018

Confirmation DateNOED NumberFacility (Licensee)
06/18/201818-2-001Catawba Nuclear Station, Unit 2 (Duke Energy Corporation)
08/15/201818-1-01Beaver Valley Power Station, Unit No. 2 (FirstEnergy Nuclear Operating Company)

To top of page

2017

Confirmation DateNOED NumberFacility (Licensee)
09/10/201717-2-01Browns Ferry Nuclear Plant, Units 1, 2 and 3 (Tennessee Valley Authority)
09/12/201717-3-001Dresden Nuclear Power Station, Unit 3 (Exelon Generation Company)

To top of page

2016

Confirmation DateNOED NumberFacility (Licensee)
03/09/201616-2-001Brunswick Steam Electric Plant, Unit 2 (Duke Energy Progress, Inc.)
10/20/201616-2-01Watts Bar Nuclear Plant, Units 1 and 2 (Tennessee Valley Authority)

To top of page

2015

Confirmation DateNOED NumberFacility (Licensee)
07/17/201515-4-02Comanche Peak Nuclear Power Plant (Luminant Generation Company)
06/04/201515-4-01Palo Verde Nuclear Generating Station, Unit 3 (Arizona Public Service Company)

To top of page

2014

Confirmation DateNOED NumberFacility (Licensee)
10/16/201414-4-002Wolf Creek Generating Station (Wolf Creek Nuclear Operating Corporation)
08/28/201414-1-04Peach Bottom Atomic Power Station Units 2 and 3 (Exelon)
08/27/201414-2-03Vogtle Electric Generating Plant Unit 2 (Southern Nuclear Operating Company, Inc.)
08/27/201414-2-002McGuire Nuclear Station Unit 1 (Duke Energy Carolinas, LLC)
08/21/201414-4-001Diablo Canyon Power Plant Unit 2 (Pacific Gas and Electric Company)
07/31/201414-2-001 (Extension)Turkey Point Nuclear Generating Station Units 3 and 4 (Florida Power and Light Company)
07/23/201414-2-001Turkey Point Nuclear Generating Station Units 3 and 4 (Florida Power and Light Company)
07/17/201414-1-03Three Mile Island Unit 1 (Exelon Generation Company LLC.)
03/12/201414-2-001Catawba Nuclear Station Unit 1 (Duke Energy Corporation)
02/19/201414-1-02Salem Unit 2 (PSEG Nuclear)
01/30/201414-1-01Millstone Power Station Unit 3 (Dominion Resources)

To top of page

2013

Confirmation DateNOED NumberFacility (Licensee)
12/11/201313-4-004Comanche Peak Nuclear Power Plant (Luminant Generation Company LLC)
10/24/201313-4-003NOED DENIED – Wolf Creek (Wolf Creek Nuclear Operating Corporation)
06/21/201313-4-002Wolf Creek (Wolf Creek Nuclear Operating Corporation)
04/17/201313-2-001Brunswick 1 (Carolina Power and Light Company)
01/15/201313-4-001Wolf Creek (Wolf Creek Nuclear Operating Corporation)

To top of page

2012

Confirmation DateNOED NumberFacility (Licensee)
07/12/201212-3-001Braidwood (Exelon)
07/31/201212-2-002NOED DENIED – Joseph M. Farley Nuclear Plant Unit 1 (Southern Nuclear Company)
07/26/201212-2-001Shearon Harris Nuclear Power Plant Unit 1 (Carolina Power and Light Company)
07/25/201212-3-002Donald C Cook 1 (Indiana Michigan Power)
08/23/201212-4-002Callaway Plant Unit 1 (Union Electric Company)
08/15/201212-2-003Surry Power Station Units 1 and 2 (Virginia Electric and Power Company)

To top of page

2011

Confirmation DateNOED NumberFacility (Licensee)
12/22/201111-2-004Catawba Nuclear Station Unit 1 and 2 (Duke Energy Corporation)
10/12/201111-1-001Calvert Cliffs (Constellation Energy Nuclear Group, LLC)
10/05/201111-3-001Monticello Nuclear Generating Plant (Northern States Power Company)
08/18/201111-4-001Wolf Creek Generating Station (Wolf Creek Nuclear Operating Corporation)
06/06/201111-2-003Oconee Nuclear Station (Duke Energy Carolinas, LLC)
01/26/201111-2-001McGuire Nuclear Station Unit 1 (Duke Energy Carolinas, LLC)

To top of page

2010

Confirmation DateNOED NumberFacility (Licensee)
04/08/201010-4-001Callaway, Unit 1 (Union Electric Company)

To top of page

2009

Confirmation DateNOED NumberFacility (Licensee)
10/07/200909-3-002Palisades (Entergy Nuclear Operations, Inc.)
01/29/200909-3-01Kewaunee (Dominion Energy Kewaunee, Inc.)

To top of page

2008

Confirmation DateNOED NumberFacility (Licensee)
10/02/200808-2-001Sequoyah 1 and 2 (Tennessee Valley Authority)
08/21/200808-3-002Dresden 3 (Exelon Generation Company, LLC)
04/10/200808-3-01Palisades (Energy Nuclear Operations, Inc.)
02/20/200808-4-01Wolf Creek (Wolf Creek Nuclear Operating Corporation)

To top of page

2007

Confirmation DateNOED NumberFacility (Licensee)
07/12/200707-4-01Wolf Creek (Wolf Creek Nuclear Operating Corporation)
01/24/200707-3-01Dresden (Exelon Generation Company, LLC)

To top of page

2006

Confirmation DateNOED NumberFacility (Licensee)
12/20/200606-4-02South Texas Unit 1 (STP Nuclear)
12/06/200606-4-01South Texas Unit 2 (STP Nuclear)
10/18/200606-3-01Quad Cities (Exelon Generation Company)
04/20/200606-1-01Beaver Valley 2 (FirstEnergy Nuclear Operating Company)
02/22/200606-2-01St. Lucie 2 (Florida Power and Light Company)

To top of page

2005

Confirmation DateNOED NumberFacility (Licensee)
12/05/200505-01-01Seabrook (FPL Energy Seabrook, LLC)
10/14/200505-2-002McGuire 1 (Duke Power Company)
05/17/200505-2-001Brunswick (Carolina Power and Light Company)

To top of page

2004

Confirmation DateNOED NumberFacility (Licensee)
05/26/200403-4-002Callaway (Union Electric Company)
03/23/200404-6-001South Texas Project 1 and 2 (STP Nuclear Operating Company)

To top of page

2003

Confirmation DateNOED NumberFacility (Licensee)
11/25/200303-2-007St. Lucie 2 (Florida Power and Light Company)
11/07/200303-6-004Vogtle 2 (Southern Nuclear Operating Company)
10/16/200303-1-003Calvert Cliffs 2 (Constellation Generation Group, LLC)
10/14/200303-6-003Catawba 1 (Duke Energe Corporation)
09/10/200303-3-006Perry (FirstEnergy Nuclear Operating Co.)
08/20/200303-2-006Catawba 2 (Duke Energy Corporation)
08/20/200303-6-002Ginna (Rochester Gas and Electric Corporation)
08/18/200303-1-002Nine Point 2 (Nine Mile Point Nuclear Station, LLC)
07/10/200303-3-005Palisades (Nuclear Management Co., LLC)
05/13/200303-2-005Catawba 1 (Duke Energy Corporation)
04/14/200303-3-004LaSalle 1 (Exelon Generation Company)
03/13/200303-3-003D.C. Cook 2 (Indiana Michigan Power Company)
03/06/200303-2-004Sequoyah 2 (Tennessee Valley Authority)
02/26/200303-1-001Pilgrim 1 (Entergy Nuclear Operations, Inc.)
02/21/200303-4-001Columbia Generating Station (Energy Northwest)
02/11/200303-2-003McGuire 1 (Duke Energy Corporation)
02/11/200303-2-002Summer 1 (South Carolina Electric & Gas Company)
02/06/200303-3-002Braidwood (Exelon Generation Company, LLC)
01/30/200303-6-001Sequoyah 2 (Tennessee Valley Authority)
01/22/200303-3-001Palisades (Nuclear Management Company, LLC)

To top of page

2002

Confirmation DateNOED NumberFacility (Licensee)
12/20/200202-6-002Hope Creek (PSEG Nuclear, LLC)
12/23/200202-4-004Callaway (Union Electric Company)
11/15/200202-3-059Palisades (Nuclear Management Company, LLC)
11/08/200202-3-058D.C. Cook 2 (Indiana Michigan Power Company)
10/08/200202-1-003Susquehanna 1 (PP&L, Inc.)
08/23/200202-4-003Diablo Canyon 2 (Pacific Gas and Electric Company)
07/17/200202-3-009Dresden (Thomas S. Cisco)
07/17/200202-3-012Dresden (Daniel G. Daly)
07/17/200202-3-018Dresden (Gerard A. Gates)
07/17/200202-3-029Dresden (Christopher A. Keebaugh)
07/17/200202-3-033Dresden (Raymond D. Laboda)
07/17/200202-3-035Dresden (Steven E. Mattson)
07/17/200202-3-040Dresden (Daniel M. Potochnic)
07/10/200202-3-003Dresden (Michael B. Alfred)
07/10/200202-3-004Dresden (Leigh D. Anderson)
07/10/200202-3-005Dresden (Carol Y. Barajas)
07/10/200202-3-006Dresden (Gary D. Bierwirth)
07/10/200202-3-007Dresden (Scott J. Briley)
07/10/200202-3-008Dresden (David J. Carlson)
07/10/200202-3-010Dresden (Louis A. Ciuffini)
07/10/200202-3-011Dresden (Larry E. Cruse)
07/10/200202-3-013Dresden (Hal G. Dodd)
07/10/200202-3-014Dresden (John C. Doyle)
07/10/200202-3-015Dresden (Ronald B. Eltrevoog)
07/10/200202-3-016Dresden (Andrew R. Failor)
07/10/200202-3-017Dresden (Richard E. Gadbois)
07/10/200202-3-019Dresden (Robert A. Gato)
07/10/200202-3-020Dresden (Joseph T. Glanek)
07/10/200202-3-021Dresden (Brian E. Grant)
07/10/200202-3-022Dresden (David H. Gronek)
07/10/200202-3-023Dresden (James J. Gulas)
07/10/200202-3-024Dresden (David I. Hamilton)
07/10/200202-3-025Dresden (Gerald T. Hartman)
07/10/200202-3-026Dresden (Richard L. Hocraffer)
07/10/200202-3-027Dresden (Martin T. Kapchinske)
07/10/200202-3-028Dresden (Peter J. Karaba)
07/10/200202-3-030Dresden (Christopher P. Kent)
07/10/200202-3-031Dresden (David M. Klimek)
07/10/200202-3-032Dresden (Thomas D. Koppen)
07/10/200202-3-034Dresden (Gregory N. Leonatti)
07/10/200202-3-036Dresden (Michael J. McDonald)
07/10/200202-3-037Dresden (Glen K. Morrow)
07/10/200202-3-038Dresden (Thomas A. Mosey)
07/10/200202-3-039Dresden (Terence S. Palanyk)
07/10/200202-3-041Dresden (Thomas L. Pouk)
07/10/200202-3-042Dresden (Randy F. Pritzl)
07/10/200202-3-043Dresden (Donald F. Ragan)
07/10/200202-3-044Dresden (Mitchell D. Roether)
07/10/200202-3-045Dresden (William M. Runion)
07/10/200202-3-046Dresden (Paul A. Salgado)
07/10/200202-3-047Dresden (Brian W. Sampson)
07/10/200202-3-048Dresden (David P. Schupp)
07/10/200202-3-049Dresden (Robert P. Scott)
07/10/200202-3-050Dresden (David A. Slager)
07/10/200202-3-051Dresden (Roger W. Stobert)
07/10/200202-3-052Dresden (David B. Throne)
07/10/200202-3-053Dresden (Steven P. Vercelli)
07/10/200202-3-054Dresden (Joseph M. Welch)
07/10/200202-3-055Dresden (Kim R. Wynn)
07/10/200202-3-056Dresden (Alan H. Zlomie)
06/18/200202-3-002D.C. Cook 1 and 2 (Indiana Michigan Power Company)
06/13/200202-1-002Indian Point 3 (Entergy Nuclear)
04/10/200202-3-001D.C. Cook 2 (Indiana Michigan Power Company)
04/02/200202-4-001Grand Gulf 1 (Energy Operations, Inc.)
03/26/200202-6-001Columbia Generating Station (Energy Northwest)
01/31/200202-1-001Calvert Cliffs (Constellation Nuclear)

To top of page

2001

Confirmation DateNOED NumberFacility (Licensee)
10/03/200101-6-003Byron 1 (Exelon Generation Company, LLC)
01-6-004Byron 2 (Exelon Generation Company, LLC)
01-6-005Braidwood 2 (Exelon Generation Company, LLC)
09/25/200101-4-002South Texas Project 1 (STP Nuclear Operating Company)
04/24/200101-2-001McGuire 1 (Duke Energy Corporation)
04/18/200101-3-002Prairie Island (Nuclear Management Company, LLC)
03/29/200101-3-001Fermi 2 (Detroit Edison Company)
03/08/200101-2-001Watts Bar 1 (Tennessee Valley Authority)
02/23/200101-4-001Grand Gulf (Entergy Operations, Inc.)
02/05/200101-6-002Monticello (Nuclear Management Company, LLC)
01/19/200101-1-001Hope Creek (PSEG Nuclear, LLC)
01/18/200101-6-001Clinton (AmerGen Energy Company, LLC)

To top of page

2000

Confirmation DateNOED NumberFacility (Licensee)
11/28/200000-4-002Fort Calhoun (Omaha Public Power District)
11/03/200000-3-001Prairie Island (Nuclear Management Company, LLC)
10/12/200000-2-001Surry 1 (Virginia Electric and Power Company)
09/20/200000-6-011Clinton (AmerGen Energy Company)
09/11/200000-6-010Callaway (Union Electric Company)
09/08/200000-6-009Oconee 1, 2, and 3 (Duke Energy Corporation)
07/21/200000-6-007Oyster Creek (GPU Nuclear, Inc.)
09/05/200000-6-008FitzPatrick (Power Authority of the State of New York)
05/01/200000-6-006Waterford 3 (Entergy Operations, Inc.)
04/11/200000-6-005Susquehanna 2 (PP&L, Inc.)
02/25/200000-6-004Watts Bar 1 (Tennessee Valley Authority)
02/23/200000-6-003LaSalle (Commonwealth Edison Company)
02/18/200000-6-002Palisades (Consumer Power)
02/14/200000-6-001Vermont Yankee (Vermont Yankee Nuclear Power Corporation)
01/24/200000-4-001Comanche Peak 1 (TXU Electric)
01/08/200099-3-001Point Beach 1 (Wisconsin Electric)
01/04/200099-6-010Cooper (Nebraska Public Power District)

To top of page