The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Discussion Of Lessons Learned Short Term Requirements (Generic Letter 79-60)



GL79060 

                                 UNITED STATES 
                         NUCLEAR REGULATORY COMMISSION 
                            WASHINGTON, D. C. 20555 

                               November 9, 1979 

                  TO ALL PENDING OPERATING LICENSE APPLICANTS 

Gentlemen: 

SUBJECT:  DISCUSSION OF LESSONS LEARNED SHORT TERM REQUIREMENTS 

On September 27, 1979, you received a letter which defined a set of "short 
term" requirements resulting from the NRC staff investigations of the TMI 
accident. Since the letter was issued, the staff has further defined these 
requirements. 

Enclosure 1 provides the additional clarifications of the NRC staff 
requirements as provided to licensees of operating reactors. Enclosure 2 
provides a list of modifications to these clarifications to make them 
applicable to applicants for operating licenses, applicants for construction 
permits and licensees of plants under construction. It should be noted that 
the intent of these requirements and the purpose of our letter of September 
27, 1979 have not changed. 

If you have any questions regarding these actions, please contact the NRC 
Project Manager for your facility. 

                                        Sincerely, 



                                   D. R. Vassallo, Acting Director Division 
                                   of  Project Management Office of Nuclear 
                                        Reactor Regulation 

Enclosure:
Discussion of TMI Lessons Learned
Short Term Requirements

ccs:
Service List 
.

                               UNDER OL REVIEW 


1.   Farely                             Alabama Power Company 

2.   Byron/Braidwood                    Commonwealth Edison 

3.   LaSalle                                 " 

4.   Zion                                    " 

5.   Midland                            Consumers Power 

6.   Greenwood                          Detroit Edison 

7.   Catawba                            Duke Power Company 

8.   McGuire                                 " 

9.   So. Texas                          Houston Lighting & Power 

10.  Shoreham                           Long Island Lighting 

11.  Waterford                          Louisiana Power & Light 

12.  Grand Gulf                         Mississippi Power & Light 

13.                                     Ohio Edison Company 

14.  Diablo Canyon                      Pacific Gas & Electric 

15.  Susquehana                         Pennsylvania Power & Light 

16.  Salem 2                            Public Service Gas & Electric 

17.  Summer                             So. Carolina Electric & Gas 

18.  San Onofre                         So. California Edison 
                                        San Diego Gas & Electric Co. 

19.  Bellefonte                         Tennessee Valley Authority 

20.  Watts Bar                               " 

21.  Sequoyah                                " 

22.  Comanche Peak                      Texas Utilities Generating 

23.                                     Toledo Edison 

24.  North Anna 2                       Virginia Electric & Power 

25.  WPPSS-2                            Washington P. O. S. S. 

26.  Fermi                              Detroit Edison 

27.  Zimmer                             Cincinnati Gas & Electric 
.

                             CONSTRUCTION PERMIT 
                            with Application for OL 

                    Pressurized Water Reactors    

                              50-275/323 

                              50-311 

                              50-327/328 

                              50-329/330 

                              50-361/362 

                              50-364 

                              50-369/370 

                              50-373/374 

                              50-382 

                              50-390/391 

                              50-395 

                              50-438/439 

                              50-445/446 

                              50-454/455 

                              50-456/457 

                              50-498/499 
.

                             CONSTRUCTION PERMIT 
                           with application for OL 

                         Boiling Water Reactors  

                              50-322 

                              50-341 

                              50-358 

                              50-387/388 

                              50-397 

                              50-416/417 

 