Fire Protection Functional Responsibilities (Davis-Besse Nuclear Power Station, Unit 1) (Generic Letter 77-02)
GL 77-02
UNITED STATES
NUCLEAR REGULATORY COMMISSION
WASHINGTON, D.C. 20555
August 29, 1977
The Toledo Edison Company
ATTN: Mr. Lowell E. Roe, Vice President
Power Facilities Development
Edison Plaza
300 Madison Avenue
Toledo, Ohio 43652
Gentlemen:
SUBJECT: FIRE PROTECTION FUNCTIONAL RESPONSIBILITIES (DAVIS-BESSE NUCLEAR
POWER STATION, UNIT 1): GENERIC LETTER 77-02
We are enclosing for your information and use a copy of "Nuclear Plant Fire
Protection Functional Responsibilities, Administrative Controls and Quality
Assurance." This document is presently being used by NRC as supplemental
guidance for the review of the organizational and administrative aspects of
fire protection evaluations.
Sincerely,
D. B. Vassallo, Assistant Director
for Light Water Reactors
Division of Project Management
Enclosure:
As stated
8001220884