Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Power Reactor Status Report for July 9, 2016

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 82   WATER BOX LEAK *  
Calvert Cliffs 1 100     *  
Calvert Cliffs 2 100     *  
FitzPatrick 84   CONDENSATE BOOSTER PUMP MAINTENANCE *  
Ginna 100        
Hope Creek 1 100        
Indian Point 2 100        
Indian Point 3 100   13.8 kV and 138 kV FEEDER RESTRICTIONS    
Limerick 1 100     *  
Limerick 2 100     *  
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 100     *  
Peach Bottom 2 100   100 MVAR LIMIT FOR TURBINE BEARING VIBRATION    
Peach Bottom 3 100        
Pilgrim 1 100        
Salem 1 0 04/14/2016 REFUELING OUTAGE    
Salem 2 13   TURBINE OFFLINE FOR TROUBLE SHOOTING *  
Seabrook 1 100        
Susquehanna 1 100     *  
Susquehanna 2 100     *  
Three Mile Island 1 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 99   REDUCED POWER FOR ROD PATTERN ADJUSTMENT *  
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 100        
Catawba 1 100        
Catawba 2 100        
Farley 1 100        
Farley 2 100        
Harris 1 100        
Hatch 1 100        
Hatch 2 100        
McGuire 1 100        
McGuire 2 100        
North Anna 1 100     *  
North Anna 2 100     *  
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 100        
Saint Lucie 1 100        
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100     *  
Surry 2 100     *  
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 100        
Vogtle 2 100        
Watts Bar 1 95   BACK PRESSURE ISSUES *  
Watts Bar 2 47   POWER ASCENSION TESTING    

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 99   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100        
D.C. Cook 2 0 07/05/2016 FORCED OUTAGE - SEE EN #52065    
Davis-Besse 100        
Dresden 2 100        
Dresden 3 100        
Duane Arnold 97   INCREASING POWER - FOLLOWING LOAD LINE ADJUSTMENT *  
Fermi 2 100        
La Salle 1 100        
La Salle 2 100        
Monticello 100        
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 100        
Quad Cities 1 100        
Quad Cities 2 100        

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 100        
Diablo Canyon 1 100        
Diablo Canyon 2 100        
Fort Calhoun 100        
Grand Gulf 1 3   INCREASING POWER - FOLLOWING A FORCED OUTAGE *  
Palo Verde 1 100        
Palo Verde 2 100        
Palo Verde 3 100        
River Bend 1 100        
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 100        