The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for October 20, 2013

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 0 09/29/2013 REFUELING OUTAGE - CORE RELOAD IN PROGRESS *  
Beaver Valley 2 100        
Calvert Cliffs 1 100   HIGH SYSTEM VOLTAGE ALERT    
Calvert Cliffs 2 100   HIGH SYSTEM VOLTAGE ALERT    
FitzPatrick 92   INCREASING POWER AFTER MAIN CONDENSER TUBE LEAK REPAIR *  
Ginna 100        
Hope Creek 1 0 10/11/2013 REFUELING OUTAGE    
Indian Point 2 100   13.8 KV LINE 33332LM OOS    
Indian Point 3 100   13.8 KV LINE 33332LM OOS    
Limerick 1 100        
Limerick 2 100        
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 100        
Peach Bottom 2 100        
Peach Bottom 3 20   HOLDING POWER FOR MAINTENANCE *  
Pilgrim 1 0 10/14/2013 UNPLANNED MAINTENANCE OUTAGE *  
Salem 1 100        
Salem 2 100        
Seabrook 1 100   CONTINGENCY DUE TO 307 LINE OUTAGE: DROP TO 800 MWE    
Susquehanna 1 100   HIGH SYSTEM VOLTAGE ACTION    
Susquehanna 2 100   HIGH SYSTEM VOLTAGE ACTION    
Three Mile Island 1 100   HIGH SYSTEM VOLTAGE ACTION *  
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100        
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 100        
Catawba 1 100        
Catawba 2 15   HOLDING POWER FOR TESTING    
Farley 1 0 09/29/2013 REFUELING OUTAGE - CORE RELOADED    
Farley 2 100        
Harris 1 100        
Hatch 1 100        
Hatch 2 100        
McGuire 1 97   INCREASING POWER AFTER TURBINE VALVE TESTING *  
McGuire 2 100     *  
North Anna 1 100        
North Anna 2 100        
Oconee 1 100        
Oconee 2 0 10/11/2013 REFUELING OUTAGE    
Oconee 3 100        
Robinson 2 0 09/13/2013 REFUELING OUTAGE - CORE RELOAD IN PROGRESS *  
Saint Lucie 1 0 09/30/2013 REFUELING OUTAGE - CORE RELOAD IN PROGRESS    
Saint Lucie 2 100        
Sequoyah 1 0 10/14/2013 REFUELING OUTAGE    
Sequoyah 2 100        
Summer 100        
Surry 1 0 10/19/2013 REFUELING OUTAGE *  
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 100        
Vogtle 2 0 10/19/2013 AUTOMATIC REACTOR TRIP. SEE EN #49453 * 1
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100     *  
Byron 2 100        
Clinton 0 10/07/2013 REFUELING OUTAGE    
D.C. Cook 1 100   HIGH SYSTEM VOLTAGE ACTION    
D.C. Cook 2 0 10/01/2013 REFUELING OUTAGE HIGH SYSTEM VOLTAGE ACTION    
Davis-Besse 100        
Dresden 2 97   COASTDOWN TO REFUELING OUTAGE    
Dresden 3 0 10/19/2013 MAINTENANCE OUTAGE *  
Duane Arnold 97   INCREASING POWER *  
Fermi 2 100        
La Salle 1 100        
La Salle 2 100        
Monticello 100        
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 0 09/21/2013 DEFUELED    
Quad Cities 1 100        
Quad Cities 2 100     *  

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 100        
Diablo Canyon 1 100        
Diablo Canyon 2 100        
Fort Calhoun 0 04/09/2011 REFUELING OUTAGE - FUEL LOADING COMPLETE    
Grand Gulf 1 100     *  
Palo Verde 1 100        
Palo Verde 2 100        
Palo Verde 3 0 10/04/2013 REFUELING OUTAGE    
River Bend 1 100        
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 0 10/18/2013 TECH SPEC REQUIRED SHUTDOWN. SEE EN #49448.    

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Thursday, March 25, 2021