Power Reactor Status Report for April 9, 2012
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Beaver Valley 1 | 0 | 04/08/2012 | REFUELING OUTAGE | * | |
Beaver Valley 2 | 100 | ||||
Calvert Cliffs 1 | 0 | 02/05/2012 | REACTOR IS CRITICAL. PLANT STARTUP IN PROGRESS. | * | |
Calvert Cliffs 2 | 100 | ||||
FitzPatrick | 100 | ||||
Ginna | 100 | ||||
Hope Creek 1 | 96 | COASTDOWN TO REFUELING OUTAGE 500 KV 5023 LINE OOS FOR PLANNED MAINTENANCE | * | ||
Indian Point 2 | 100 | * | |||
Indian Point 3 | 100 | 138 KV AUX TRANSFORMER OOS | |||
Limerick 1 | 100 | ||||
Limerick 2 | 100 | ||||
Millstone 2 | 100 | ||||
Millstone 3 | 100 | ||||
Nine Mile Point 1 | 100 | ||||
Nine Mile Point 2 | 0 | 04/08/2012 | REACTOR IS SUBCRITICAL IN MODE 2 COMMENCING REFUELING OUTAGE. | * | |
Oyster Creek | 100 | ||||
Peach Bottom 2 | 100 | SBO LINE OOS FOR PM | * | ||
Peach Bottom 3 | 100 | SBO LINE OOS FOR PM | * | ||
Pilgrim 1 | 100 | ||||
Salem 1 | 100 | ||||
Salem 2 | 100 | ||||
Seabrook 1 | 85 | HOLDING POWER BASED ON GENERATOR STATOR COOLING DELTA T LIMIT | |||
Susquehanna 1 | 0 | 03/31/2012 | REFUELING OUTAGE | ||
Susquehanna 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
Three Mile Island 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
Vermont Yankee | 100 |
Region 2
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Browns Ferry 1 | 100 | ||||
Browns Ferry 2 | 100 | ||||
Browns Ferry 3 | 0 | 04/07/2012 | REFUELING OUTAGE | * | |
Brunswick 1 | 0 | 02/23/2012 | REFUELING OUTAGE | ||
Brunswick 2 | 100 | ||||
Catawba 1 | 0 | 04/04/2012 | FORCED OUTAGE. SEE EN #47805 | * | |
Catawba 2 | 0 | 03/10/2012 | REFUELING OUTAGE | * | |
Crystal River 3 | 0 | 09/25/2009 | DEFUELED - CONTAINMENT TENSIONING ON HOLD | ||
Farley 1 | 0 | 04/01/2012 | DEFUELED | * | |
Farley 2 | 100 | ||||
Harris 1 | 97 | COASTDOWN TO REFUELING OUTAGE | |||
Hatch 1 | 100 | ||||
Hatch 2 | 100 | ||||
McGuire 1 | 100 | ||||
McGuire 2 | 100 | ||||
North Anna 1 | 0 | 03/10/2012 | REFUELING OUTAGE | * | |
North Anna 2 | 100 | * | |||
Oconee 1 | 100 | ||||
Oconee 2 | 100 | ||||
Oconee 3 | 82 | COASTDOWN TO REFUELING OUTAGE | * | ||
Robinson 2 | 100 | ||||
Saint Lucie 1 | 0 | 04/07/2012 | SHUTDOWN FOR WATERBOX REPAIR | ||
Saint Lucie 2 | 100 | ||||
Sequoyah 1 | 100 | ||||
Sequoyah 2 | 100 | ||||
Summer | 100 | ||||
Surry 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
Surry 2 | 98 | CALORIMETRIC NON-FUNCTIONAL WHEN ON EXCESS LETDOWN HIGH SYSTEM VOLTAGE ACTION | |||
Turkey Point 3 | 0 | 02/26/2012 | DEFUELED | ||
Turkey Point 4 | 100 | ||||
Vogtle 1 | 100 | ||||
Vogtle 2 | 100 | ||||
Watts Bar 1 | 100 |
Region 3
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Braidwood 1 | 100 | ||||
Braidwood 2 | 100 | ||||
Byron 1 | 100 | FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.6% | |||
Byron 2 | 100 | FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.9% | |||
Clinton | 97 | 100% ELECTRICAL CAPABILITY | |||
D.C. Cook 1 | 100 | HI VOLTAGE ACTION | |||
D.C. Cook 2 | 0 | 03/21/2012 | DEFUELED HI VOLTAGE ACTION | ||
Davis-Besse | 100 | ||||
Dresden 2 | 100 | ||||
Dresden 3 | 100 | ||||
Duane Arnold | 100 | ||||
Fermi 2 | 0 | 03/25/2012 | REFUELING OUTAGE | ||
Kewaunee | 0 | 04/05/2012 | REFUELING OUTAGE | * | |
La Salle 1 | 100 | ||||
La Salle 2 | 100 | ||||
Monticello | 100 | ||||
Palisades | 0 | 04/08/2012 | REFUELING OUTAGE | * | |
Perry 1 | 100 | ||||
Point Beach 1 | 100 | ||||
Point Beach 2 | 100 | ||||
Prairie Island 1 | 100 | ||||
Prairie Island 2 | 0 | 02/21/2012 | DEFUELED | ||
Quad Cities 1 | 100 | MONITORING TURBINE VIBRATION | |||
Quad Cities 2 | 0 | REFUELING OUTAGE |
Region 4
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Arkansas Nuclear 1 | 100 | ||||
Arkansas Nuclear 2 | 100 | ||||
Callaway | 98 | TURBINE CONTROL OSCILLATIONS | * | ||
Columbia Generating Station | 85 | DOWNPOWER FOR LOAD FOLLOWING | |||
Comanche Peak 1 | 100 | ||||
Comanche Peak 2 | 99 | 100% TURBINE LOAD | * | ||
Cooper | 100 | ||||
Diablo Canyon 1 | 100 | ||||
Diablo Canyon 2 | 100 | ||||
Fort Calhoun | 0 | 04/09/2011 | REFUELING OUTAGE | ||
Grand Gulf 1 | 0 | 02/19/2012 | REFUELING OUTAGE | ||
Palo Verde 1 | 100 | ||||
Palo Verde 2 | 100 | ||||
Palo Verde 3 | 0 | 03/16/2012 | REFUELING OUTAGE - CORE RELOAD COMPLETED | ||
River Bend 1 | 100 | ||||
San Onofre 2 | 0 | 01/09/2012 | REFUELING OUTAGE | ||
San Onofre 3 | 0 | 01/31/2012 | FORCED OUTAGE - S/G REPAIR | ||
South Texas 1 | 100 | ||||
South Texas 2 | 0 | 11/28/2011 | HEATUP IN PROGRESS | * | |
Waterford 3 | 76 | INCREASING POWER | * | ||
Wolf Creek 1 | 100 |