Power Reactor Status Report for January 17, 2012
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Beaver Valley 1 | 100 | ||||
Beaver Valley 2 | 100 | ||||
Calvert Cliffs 1 | 100 | ||||
Calvert Cliffs 2 | 100 | ||||
FitzPatrick | 99 | XENON TRANSIENT | * | ||
Ginna | 100 | ||||
Hope Creek 1 | 100 | ||||
Indian Point 2 | 0 | 01/10/2012 | FORCED OUTAGE TO REPAIR 21 RCP SEAL | ||
Indian Point 3 | 100 | 1 OF 3 13.8 KV LINES OOS | * | ||
Limerick 1 | 100 | ||||
Limerick 2 | 100 | ||||
Millstone 2 | 100 | ||||
Millstone 3 | 100 | ||||
Nine Mile Point 1 | 100 | ||||
Nine Mile Point 2 | 100 | ||||
Oyster Creek | 100 | ||||
Peach Bottom 2 | 100 | ||||
Peach Bottom 3 | 100 | ||||
Pilgrim 1 | 100 | ||||
Salem 1 | 100 | ||||
Salem 2 | 100 | ||||
Seabrook 1 | 75 | GENERATOR STATOR WATER COOLING SYSTEM CLEANING | * | ||
Susquehanna 1 | 98 | 100% ELECTRICAL CAPABILITY | * | ||
Susquehanna 2 | 100 | 100% ELECTRICAL CAPABILITY | * | ||
Three Mile Island 1 | 100 | ||||
Vermont Yankee | 100 |
Region 2
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Browns Ferry 1 | 100 | ||||
Browns Ferry 2 | 100 | ||||
Browns Ferry 3 | 100 | ||||
Brunswick 1 | 100 | ||||
Brunswick 2 | 100 | ||||
Catawba 1 | 100 | ||||
Catawba 2 | 100 | ||||
Crystal River 3 | 0 | 09/25/2009 | DEFUELED - CONTAINMENT TENSIONING ON HOLD | ||
Farley 1 | 0 | 01/16/2012 | MAINTENANCE OUTAGE - TURBINE BLADE INSPECTION | * | |
Farley 2 | 100 | ||||
Harris 1 | 100 | ||||
Hatch 1 | 95 | COASTDOWN TO REFUELING OUTAGE | * | ||
Hatch 2 | 100 | ||||
McGuire 1 | 100 | ||||
McGuire 2 | 100 | ||||
North Anna 1 | 100 | ||||
North Anna 2 | 100 | ||||
Oconee 1 | 100 | ||||
Oconee 2 | 100 | ||||
Oconee 3 | 100 | ||||
Robinson 2 | 86 | COASTDOWN TO REFUELING OUTAGE | * | ||
Saint Lucie 1 | 0 | 11/27/2011 | REFUELING OUTAGE - DEFUELED | ||
Saint Lucie 2 | 100 | * | |||
Sequoyah 1 | 100 | ||||
Sequoyah 2 | 100 | ||||
Summer | 100 | ||||
Surry 1 | 100 | ||||
Surry 2 | 100 | ||||
Turkey Point 3 | 100 | ||||
Turkey Point 4 | 100 | ||||
Vogtle 1 | 100 | ||||
Vogtle 2 | 100 | ||||
Watts Bar 1 | 100 |
Region 3
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Braidwood 1 | 100 | ||||
Braidwood 2 | 100 | ||||
Byron 1 | 100 | SLIGHTLY REDUCED TO 99.6% POWER FOR FEEDWATER FLOW INSTRUMENT INVESTIGATION | |||
Byron 2 | 100 | ||||
Clinton | 97 | 100% ELECTRICAL GENERATION | |||
D.C. Cook 1 | 100 | ||||
D.C. Cook 2 | 100 | ||||
Davis-Besse | 100 | ||||
Dresden 2 | 100 | ||||
Dresden 3 | 100 | ||||
Duane Arnold | 100 | ||||
Fermi 2 | 100 | ||||
Kewaunee | 100 | ||||
La Salle 1 | 100 | ||||
La Salle 2 | 100 | ||||
Monticello | 100 | ||||
Palisades | 100 | ||||
Perry 1 | 100 | ||||
Point Beach 1 | 100 | ||||
Point Beach 2 | 100 | ||||
Prairie Island 1 | 100 | ||||
Prairie Island 2 | 100 | ||||
Quad Cities 1 | 100 | ||||
Quad Cities 2 | 100 |
Region 4
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Arkansas Nuclear 1 | 100 | ||||
Arkansas Nuclear 2 | 100 | ||||
Callaway | 100 | ||||
Columbia Generating Station | 100 | ||||
Comanche Peak 1 | 100 | ||||
Comanche Peak 2 | 100 | ||||
Cooper | 100 | ||||
Diablo Canyon 1 | 100 | DIABLO- MESA 230 KV LINE OOS | * | ||
Diablo Canyon 2 | 100 | DIABLO- MESA 230 KV LINE OOS | * | ||
Fort Calhoun | 0 | 04/09/2011 | REFUELING OUTAGE | ||
Grand Gulf 1 | 96 | POWER LIMITED BASED ON SECOND STAGE MSR ISOLATED | |||
Palo Verde 1 | 100 | ||||
Palo Verde 2 | 100 | ||||
Palo Verde 3 | 100 | ||||
River Bend 1 | 100 | ||||
San Onofre 2 | 0 | 01/09/2012 | REFUELING OUTAGE | * | |
San Onofre 3 | 100 | ||||
South Texas 1 | 100 | ||||
South Texas 2 | 0 | 11/28/2011 | MAINTENANCE OUTAGE | ||
Waterford 3 | 100 | ||||
Wolf Creek 1 | 0 | 01/13/2012 | LOSS OF OFFSITE POWER - STARTUP TRANSFORMERS POWERED FROM OFFSITE - SEE EN #47590 |