Power Reactor Status Report for April 27, 2011
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Beaver Valley 1 | 100 | ||||
Beaver Valley 2 | 94 | HEATER DRAIN LEVEL CONTROL VALVE ISSUES | * | ||
Calvert Cliffs 1 | 100 | ||||
Calvert Cliffs 2 | 100 | ||||
FitzPatrick | 100 | MAIN GENERATOR VOLTAGE REGULATOR IN MANUAL | |||
Ginna | 0 | 04/23/2011 | REFUELING OUTAGE | * | |
Hope Creek 1 | 100 | ||||
Indian Point 2 | 100 | ||||
Indian Point 3 | 100 | ||||
Limerick 1 | 100 | ||||
Limerick 2 | 97 | REDUCED POWER DUE TO HIGH RECIRC PUMP TEMPS | * | ||
Millstone 2 | 0 | 04/02/2011 | REFUELING OUTAGE | ||
Millstone 3 | 100 | ||||
Nine Mile Point 1 | 46 | #13 FEEDWATER PUMP OOS | * | ||
Nine Mile Point 2 | 100 | ||||
Oyster Creek | 100 | ||||
Peach Bottom 2 | 100 | ||||
Peach Bottom 3 | 100 | ||||
Pilgrim 1 | 0 | 04/17/2011 | REFUELING OUTAGE | ||
Salem 1 | 8 | WATERBOX CLEANING | |||
Salem 2 | 0 | 04/09/2011 | REFUELING OUTAGE | ||
Seabrook 1 | 0 | 03/31/2011 | EXITING REFUELING OUTAGE | ||
Susquehanna 1 | 100 | ||||
Susquehanna 2 | 0 | 04/04/2011 | REFUELING OUTAGE | ||
Three Mile Island 1 | 100 | ||||
Vermont Yankee | 100 | * |
Region 2
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Browns Ferry 1 | 100 | ||||
Browns Ferry 2 | 100 | ||||
Browns Ferry 3 | 100 | ||||
Brunswick 1 | 100 | ||||
Brunswick 2 | 100 | * | |||
Catawba 1 | 0 | 04/23/2011 | ENTERING REFUELING OUTAGE | ||
Catawba 2 | 100 | ||||
Crystal River 3 | 0 | 09/25/2009 | MAINTENANCE OUTAGE - CONTAINMENT TENSIONING ON HOLD | ||
Farley 1 | 100 | 500 KV OFFSITE LINE OOS FOR PLANNED MAINTENANCE UNTIL 5/6 | |||
Farley 2 | 100 | 500 KV OFFSITE LINE OOS FOR PLANNED MAINTENANCE UNTIL 5/6 | |||
Harris 1 | 100 | ||||
Hatch 1 | 100 | ||||
Hatch 2 | 0 | 03/28/2011 | REFUELING OUTAGE | ||
McGuire 1 | 100 | ||||
McGuire 2 | 100 | ||||
North Anna 1 | 100 | ||||
North Anna 2 | 100 | ||||
Oconee 1 | 0 | 04/01/2011 | DEFUELED | ||
Oconee 2 | 100 | ||||
Oconee 3 | 100 | ||||
Robinson 2 | 100 | ||||
Saint Lucie 1 | 100 | ||||
Saint Lucie 2 | 0 | 01/02/2011 | REFUELING OUTAGE | ||
Sequoyah 1 | 100 | ||||
Sequoyah 2 | 92 | COASTDOWN TO REFUELING OUTAGE | |||
Summer | 0 | 04/15/2011 | REFUELING OUTAGE | ||
Surry 1 | 100 | ||||
Surry 2 | 0 | 04/16/2011 | REFUELING OUTAGE | ||
Turkey Point 3 | 100 | ||||
Turkey Point 4 | 0 | 03/20/2011 | EXITING REFUELING OUTAGE | ||
Vogtle 1 | 100 | ||||
Vogtle 2 | 100 | ||||
Watts Bar 1 | 0 | 04/03/2011 | DEFUELED |
Region 3
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Braidwood 1 | 100 | ||||
Braidwood 2 | 0 | 04/17/2011 | DEFUELED | ||
Byron 1 | 80 | INCREASING POWER | * | ||
Byron 2 | 100 | ||||
Clinton | 97 | 100% ELECTRICAL CAPABILITY | |||
D.C. Cook 1 | 100 | ||||
D.C. Cook 2 | 100 | ||||
Davis-Besse | 99 | * | |||
Dresden 2 | 100 | ||||
Dresden 3 | 100 | ||||
Duane Arnold | 100 | ||||
Fermi 2 | 100 | N-1 CONTINGENCY FOR LOW VOLTAGE | |||
Kewaunee | 100 | ||||
La Salle 1 | 100 | ||||
La Salle 2 | 80 | LOW PRESSURE HEATER DRAIN LEVEL CONTROL ISSUES | * | ||
Monticello | 0 | 03/04/2011 | REFUELING OUTAGE | ||
Palisades | 100 | ||||
Perry 1 | 0 | 04/17/2011 | REFUELING OUTAGE | ||
Point Beach 1 | 100 | ||||
Point Beach 2 | 0 | 02/28/2011 | EXITING REFUELING OUTAGE | ||
Prairie Island 1 | 90 | DECREASING POWER FOR TREVI-TESTING OF MSSVS | * | ||
Prairie Island 2 | 100 | ||||
Quad Cities 1 | 100 | ||||
Quad Cities 2 | 100 |
Region 4
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Arkansas Nuclear 1 | 43 | STORMS/DISPATCH REQUEST | * | ||
Arkansas Nuclear 2 | 43 | STORMS/DISPATCH REQUEST | * | ||
Callaway | 100 | ||||
Columbia Generating Station | 0 | 04/02/2011 | REFUELING OUTAGE | ||
Comanche Peak 1 | 100 | ||||
Comanche Peak 2 | 46 | INCREASING POWER | * | ||
Cooper | 0 | 03/12/2011 | EXITING REFUELING OUTAGE | ||
Diablo Canyon 1 | 100 | ||||
Diablo Canyon 2 | 100 | ||||
Fort Calhoun | 0 | 04/09/2011 | REFUELING OUTAGE | ||
Grand Gulf 1 | 96 | POWER LIMITED 2ND STAGE MSR OUT OF SERVICE FOR THE ENTIRE CYCLE | |||
Palo Verde 1 | 100 | ||||
Palo Verde 2 | 0 | 04/01/2011 | REFUELING OUTAGE | ||
Palo Verde 3 | 100 | ||||
River Bend 1 | 100 | ||||
San Onofre 2 | 100 | ||||
San Onofre 3 | 100 | ||||
South Texas 1 | 0 | 04/02/2011 | REFUELING OUTAGE | ||
South Texas 2 | 100 | ||||
Waterford 3 | 0 | 04/05/2011 | REFUELING OUTAGE | ||
Wolf Creek 1 | 0 | 03/18/2011 | DEFUELED |