The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for September 11, 2010

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 85   MAIN TURBINE VALVE TESTING CONDENSER WATER BOX CLEANING *  
Calvert Cliffs 2 100     *  
FitzPatrick 89   COASTDOWN TO REFUELING OUTAGE *  
Ginna 100        
Hope Creek 1 100        
Indian Point 2 0 09/03/2010 SEE EN #46229    
Indian Point 3 0 09/09/2010 MANUAL REACTOR TRIP. SEE EN# 46241    
Limerick 1 100        
Limerick 2 65   PLANNED LOAD DROP FOR MAINTENANCE *  
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 100        
Peach Bottom 2 89   COASTDOWN TO REFUELING OUTAGE    
Peach Bottom 3 100        
Pilgrim 1 100        
Salem 1 100        
Salem 2 100        
Seabrook 1 100        
Susquehanna 1 100     *  
Susquehanna 2 72   ROD PATTERN ADJUSTMENT *  
Three Mile Island 1 100     *  
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100        
Browns Ferry 2 100        
Browns Ferry 3 62   POWER SUPPRESSION TESTING *  
Brunswick 1 100        
Brunswick 2 63   REACTOR FEED PUMP REPAIRS *  
Catawba 1 98   INCREASING POWER AFTER MAIN TURBINE CONTROL VALVE TESTING *  
Catawba 2 91   COASTDOWN TO REFUELING OUTAGE    
Crystal River 3 0 09/25/2009 DEFUELED    
Farley 1 100        
Farley 2 100        
Harris 1 100   SWITCH YARD MAINTENANCE *  
Hatch 1 100        
Hatch 2 100        
McGuire 1 100        
McGuire 2 100        
North Anna 1 98   COASTDOWN TO REFUELING OUTAGE *  
North Anna 2 100        
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 0 09/09/2010 AUTOMATIC REACTOR TRIP. SEE EN# 46238    
Saint Lucie 1 80   ONE CIRC WATER PUMP OUT OF SERVICE    
Saint Lucie 2 100        
Sequoyah 1 94   COASTDOWN TO REFUELING OUTAGE *  
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100     *  
Vogtle 1 100        
Vogtle 2 100        
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 97   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 98   INCREASING AFTER TURBINE VALVE TESTING *  
D.C. Cook 2 100        
Davis-Besse 100        
Dresden 2 100        
Dresden 3 100        
Duane Arnold 80   INCREASING AFTER ROD SHUFFLE *  
Fermi 2 100        
Kewaunee 100        
La Salle 1 100        
La Salle 2 100        
Monticello 95   REDUCED POWER TO EVALUATE FEEDWATER HEATER TUBE LEAKS.    
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 100        
Quad Cities 1 100        
Quad Cities 2 100        

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 100        
Diablo Canyon 1 100   AT 0500 PDT - MAINTENANCE ON 230KV MORRO BAY TO MIDWAY LINE *  
Diablo Canyon 2 100   AT 0500 PDT - MAINTENANCE ON 230KV MORRO BAY TO MIDWAY LINE *  
Fort Calhoun 100        
Grand Gulf 1 100        
Palo Verde 1 100        
Palo Verde 2 100        
Palo Verde 3 100        
River Bend 1 75   INCREASING POWER *  
San Onofre 2 100        
San Onofre 3 100        
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.