Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Beaver Valley 1 | 100 | ||||
Beaver Valley 2 | 100 | ||||
Calvert Cliffs 1 | 40 | INCREASING POWER | * | ||
Calvert Cliffs 2 | 100 | ||||
FitzPatrick | 100 | * | |||
Ginna | 100 | ||||
Hope Creek 1 | 98 | TURBINE VALVE TESTING | * | ||
Indian Point 2 | 100 | ||||
Indian Point 3 | 100 | ||||
Limerick 1 | 100 | ||||
Limerick 2 | 100 | ||||
Millstone 2 | 100 | ||||
Millstone 3 | 100 | ||||
Nine Mile Point 1 | 100 | ||||
Nine Mile Point 2 | 100 | ||||
Oyster Creek | 100 | ||||
Peach Bottom 2 | 100 | * | |||
Peach Bottom 3 | 100 | * | |||
Pilgrim 1 | 100 | ||||
Salem 1 | 100 | ||||
Salem 2 | 100 | ||||
Seabrook 1 | 100 | ||||
Susquehanna 1 | 100 | GENERATOR VOLTAGE REGULATOR IN MANUAL | |||
Susquehanna 2 | 98 | CONTROL ROD ADJUSTMENT | * | ||
Three Mile Island 1 | 99 | * | |||
Vermont Yankee | 100 |
Region 2
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Browns Ferry 1 | 0 | 03/03/1985 | REFUELING OUTAGE | * | |
Browns Ferry 2 | 100 | 1 OF 7 500 KV LINES OOS FOR PLANNED MAINTENANCE 1 OF 2 161 KV LINES OOS FOR PLANNED MAINTENANCE | |||
Browns Ferry 3 | 100 | 1 OF 7 500 KV LINES OOS FOR PLANNED MAINTENANCE 1 OF 2 161 KV LINES OOS FOR PLANNED MAINTENANCE | |||
Brunswick 1 | 100 | ||||
Brunswick 2 | 100 | ||||
Catawba 1 | 0 | 11/10/2006 | DEFUELED | ||
Catawba 2 | 100 | CURRENTLY SUPPLYING AUX STEAM TO UNIT 1 | |||
Crystal River 3 | 100 | ||||
Farley 1 | 100 | ||||
Farley 2 | 100 | ||||
Harris 1 | 100 | ||||
Hatch 1 | 100 | ||||
Hatch 2 | 100 | ||||
McGuire 1 | 100 | ||||
McGuire 2 | 100 | ||||
North Anna 1 | 100 | K-7 SOLAR ACTIVITY WARNING UNTIL 2200 HOURS ISSUED BY SYSTEM OPERATOR | |||
North Anna 2 | 100 | K-7 SOLAR ACTIVITY WARNING UNTIL 2200 HOURS ISSUED BY SYSTEM OPERATOR | |||
Oconee 1 | 19 | HOLDING POWER - TURBINE GENERATOR TESTING | * | ||
Oconee 2 | 100 | ||||
Oconee 3 | 100 | ||||
Robinson 2 | 100 | ||||
Saint Lucie 1 | 100 | ||||
Saint Lucie 2 | 100 | ||||
Sequoyah 1 | 100 | ||||
Sequoyah 2 | 0 | 11/26/2006 | REFUELING OUTAGE | * | |
Summer | 100 | ||||
Surry 1 | 100 | ||||
Surry 2 | 100 | ||||
Turkey Point 3 | 100 | ||||
Turkey Point 4 | 100 | ||||
Vogtle 1 | 98 | * | |||
Vogtle 2 | 100 | ||||
Watts Bar 1 | 100 |
Region 3
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Braidwood 1 | 100 | ||||
Braidwood 2 | 100 | ||||
Byron 1 | 100 | ||||
Byron 2 | 100 | ||||
Clinton | 96 | 100% ELECTRICAL CAPABILITY | |||
D.C. Cook 1 | 100 | ||||
D.C. Cook 2 | 100 | ||||
Davis-Besse | 100 | ||||
Dresden 2 | 97 | 100% ELECTRICAL CAPABILITY | * | ||
Dresden 3 | 98 | 100% ELECTRICAL CAPABILITY | * | ||
Duane Arnold | 98 | 100% ELECTRICAL CAPABILITY | |||
Fermi 2 | 100 | ||||
Kewaunee | 99 | ||||
La Salle 1 | 100 | ||||
La Salle 2 | 100 | ||||
Monticello | 100 | ||||
Palisades | 100 | ||||
Perry 1 | 0 | 12/13/2006 | FORCED OUTAGE - INSTRUMENT AIR REPAIRS COMPLETED | * | |
Point Beach 1 | 100 | * | |||
Point Beach 2 | 100 | * | |||
Prairie Island 1 | 100 | ||||
Prairie Island 2 | 55 | INCREASING POWER AT 3%/HOUR | * | ||
Quad Cities 1 | 97 | 100% ELECTRICAL CAPABILITY | |||
Quad Cities 2 | 96 | 100% ELECTRICAL CAPABILITY |
Region 4
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
---|---|---|---|---|---|
Arkansas Nuclear 1 | 100 | ||||
Arkansas Nuclear 2 | 100 | ||||
Callaway | 100 | ||||
Columbia Generating Station | 100 | ||||
Comanche Peak 1 | 100 | ||||
Comanche Peak 2 | 100 | ||||
Cooper | 100 | ||||
Diablo Canyon 1 | 100 | 1 X 500 KV LINE (BREAKER 632) WILL BE TAKEN OOS FOR PLANNED MAINTENANCE | * | ||
Diablo Canyon 2 | 54 | UNIT WILL RETURN TO FULL POWER ONCE CIRC WATER PUMP REPAIRS ARE COMPLETED NEXT WEEK | * | ||
Fort Calhoun | 98 | REDUCED POWER IN PREPARATION FOR MTC TESTING ON 12/17 | * | ||
Grand Gulf 1 | 100 | ||||
Palo Verde 1 | 100 | ||||
Palo Verde 2 | 100 | ||||
Palo Verde 3 | 100 | ||||
River Bend 1 | 100 | ||||
San Onofre 2 | 99 | STEAM GENERATOR TUBE PLUGGING LIMITATION | |||
San Onofre 3 | 20 | PREPARING TO INCREASE POWER | * | ||
South Texas 1 | 100 | ||||
South Texas 2 | 100 | ||||
Waterford 3 | 0 | 11/25/2006 | REFUELING OUTAGE | * | |
Wolf Creek 1 | 100 |