The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for March 13, 2003

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BEAVER VALLEY 1 0 03/07/2003 Cold Shutdown
REFUELING OUTAGE
   
BEAVER VALLEY 2 100        
CALVERT CLIFFS 1 100        
CALVERT CLIFFS 2 0 02/14/2003 Refueling
REFUELING OUTAGE - DEFUELED
   
FITZPATRICK 1 100        
GINNA 1 100        
HOPE CREEK 1 0 03/07/2003 Startup
PULLING TO CRITICALITY
*  
INDIAN POINT 2 100        
INDIAN POINT 3 100        
LIMERICK 1 100        
LIMERICK 2 0 03/03/2003 Refueling
REFUELING OUTAGE
   
MILLSTONE 2 0 03/07/2003 Cold Shutdown
CONTAINMENT PURGE IN PROGRESS
   
MILLSTONE 3 100        
NINE MILE POINT 1 100        
NINE MILE POINT 2 100        
OYSTER CREEK 1 100        
PEACH BOTTOM 2 100        
PEACH BOTTOM 3 100        
PILGRIM 1 100        
SALEM 1 100        
SALEM 2 100        
SEABROOK 1 100        
SUSQUEHANNA 1 100        
SUSQUEHANNA 2 0 03/07/2003 Refueling
REFUELING OUTAGE
   
THREE MILE ISLAND 1 100        
VERMONT YANKEE 1 100        

Region 2

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BROWNS FERRY 1 0 03/03/1985 Refueling
DEFUELED
   
BROWNS FERRY 2 0 02/24/2003 Cold Shutdown
REFUELING OUTAGE
*  
BROWNS FERRY 3 100        
BRUNSWICK 1 94   Power Operation
100% ELECTRICAL POWER
   
BRUNSWICK 2 0 03/07/2003 Refueling
REFUELING OUTAGE
   
CATAWBA 1 100        
CATAWBA 2 0 02/28/2003 Refueling
REFUELING OUTAGE - DEFUELED
   
CRYSTAL RIVER 3 100        
FARLEY 1 100        
FARLEY 2 100        
HARRIS 1 100        
HATCH 1 100        
HATCH 2 0 02/28/2003 Refueling
REFUELING OUTAGE
   
MCGUIRE 1 100        
MCGUIRE 2 100        
NORTH ANNA 1 0 02/22/2003 Refueling
REFUELING OUTAGE - DEFUELED
   
NORTH ANNA 2 100        
OCONEE 1 100        
OCONEE 2 100        
OCONEE 3 100        
ROBINSON 2 100        
SAINT LUCIE 1 100        
SAINT LUCIE 2 100     *  
SEQUOYAH 1 100        
SEQUOYAH 2 0 03/10/2003 Hot Standby
MANUAL REACTOR TRIP FOLLOWING LOSS OF SECONDARY PLANT EQUIPMENT - SEE EVENT#39653
   
SUMMER 1 100        
SURRY 1 100        
SURRY 2 100        
TURKEY POINT 3 0 02/28/2003 Refueling
REFUELING OUTAGE - DEFUELED
   
TURKEY POINT 4 100        
VOGTLE 1 100        
VOGTLE 2 100        
WATTS BAR 1 0 03/09/2003 Hot Standby
AUTOMATIC REACTOR TRIP ON TURBINE TRIP DUE TO MAIN TRANSFORMER RELAY ACTUATION - SEE EVENT #39651
   

Region 3

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BRAIDWOOD 1 100        
BRAIDWOOD 2 100        
BYRON 1 100        
BYRON 2 100     *  
CLINTON 1 91   Power Operation
100% ELECTRICAL CAPABILITY
   
COOK 1 100        
COOK 2 100        
DAVIS BESSE 1 0 02/15/2002 Cold Shutdown
REFUELING OUTAGE
*  
DRESDEN 2 96   Power Operation
100% ELECTRICAL CAPABILITY
   
DRESDEN 3 97   Power Operation
100% ELECTRICAL CAPABILITY
   
DUANE ARNOLD 1 94   Power Operation
100% ELECTRICAL CAPABILITY
   
FERMI 2 100        
KEWAUNEE 1 100        
LASALLE 1 99     *  
LASALLE 2 100        
MONTICELLO 1 100        
PALISADES 1 100     *  
PERRY 1 85   Power Operation
COASTDOWN TO REFUELING OUTAGE
   
POINT BEACH 1 100        
POINT BEACH 2 100        
PRAIRIE ISLAND 1 100        
PRAIRIE ISLAND 2 100        
QUAD CITIES 1 96   Power Operation
100% ELECTRICAL CAPABILITY
   
QUAD CITIES 2 97   Power Operation
100% ELECTRICAL CAPABILITY
   

Region 4

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
ARKANSAS NUCLEAR 1 100        
ARKANSAS NUCLEAR 2 100        
CALLAWAY 1 100        
COLUMBIA GENERATING 0 02/28/2003 Startup
STARTUP IN PROGRESS
*  
COMANCHE PEAK 1 100        
COMANCHE PEAK 2 100        
COOPER 1 0 02/23/2003 Refueling
REFUELING OUTAGE
   
DIABLO CANYON 1 100        
DIABLO CANYON 2 0 02/03/2003 Hot Shutdown
REFUELING OUTAGE
*  
FT CALHOUN 1 100        
GRAND GULF 1 100        
PALO VERDE 1 97   Power Operation
RCS T hot Temperature Limited
   
PALO VERDE 2 98   Power Operation
RCS T hot Temperature Limited
   
PALO VERDE 3 99   Power Operation
RCS T hot Temperature Limited
   
RIVER BEND 1 85   Power Operation
COASTDOWN TO REFUELING OUTAGE
*  
SAN ONOFRE 2 100        
SAN ONOFRE 3 100     *  
SOUTH TEXAS 1 97   Power Operation
COASTDOWN TO REFUELING OUTAGE
*  
SOUTH TEXAS 2 14   Power Operation
TESTING MAIN TURBINE
*  
WATERFORD 3 100        
WOLF CREEK 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours