Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Thermal-Hydraulic Phenomena Subcommittee Meeting - July 8, 2003

ADVISORY COMMITTEE ON REACTOR SAFEGUARDS
MEETING OF THE SUBCOMMITTEE ON
THERMAL-HYDRAULIC PHENOMENA
ROOM T-2B3, 11545 ROCKVILLE PIKE, ROCKVILLE, MARYLAND
July 8, 2003

ACRS Contact: Ralph Caruso (301) 415-8065      
  E-mail: rxc@nrc.gov      

- PROPOSED SCHEDULE -
 
Tuesday, July 8, 2003
TOPIC PRESENTER TIME
     
1. Introduction Graham Wallis, ACRS  8:30-8:35 am
  • Review goals and objectives
    for this meeting
   
2. ESBWR Design Overview A. Rao, GE 8:35-9:30 am
3. ESBWR Testing and Analysis Program (TAPD) B. Shiralkar, GE 9:30-10:15 am
  ***BREAK***   10:15-10:30 am
4. ESBWR Testing and Scaling R. Gamble, GE 10:30-11:40 am
5. ESBWR TRACG Qualification B. Shiralkar, GE 11:40-12:00 pm
  ***LUNCH***   12:00 - 1:00 pm
6. ESBWR TRACG Qualification (Continued) B. Shiralkar, GE 1:00-1:30 pm
7. ESBWR TRACG Application Y. Cheung, GE 1:30-2:15 pm
8. TRACG Review R. Landry, NRR 2:15-3:15 pm
  ***BREAK***   3:15 - 3:30 pm
9. TAPD, Testing and Scaling Review M. Razzaque, NRR 3:30 - 4:15 pm
10. Confirmatory Research Plan J. Staudemeier, RES 4:15-4:45 am
11. General Discussion and Adjournment Graham Wallis, ACRS 4:45-5:00 pm

Note:

  • Presentation time should not exceed 50% of the total time allocated for a specific item.
  • Number of copies of presentation materials to be provided to the ACRS - 35.