Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Safety Review - Question 7

The correct answer is b.  Verify that the applicant has not omitted long-lived, passive structures and components that are within the scope of license renewal.  The applicant has an option to include more than required if that is more convenient.