Construction Inspection Information
NRC Region II is responsible for implementing the inspection program for WBN Unit 2. To request additional information or to contact us, see our Contact a Public Affairs Officer web page.
The following list contains Inspection Reports by the NRC issued to report and document inspection findings. These inspection reports may contain enforcement actions and follow-up inspection items.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
| Date | Description | Inspection Report Number |
|---|---|---|
| 03/09/2016 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2016601 |
| 03/02/2016 | End-Of-Cycle Assessment Letter | 05000391/2016607 |
| 02/10/2016 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2015610 |
| 10/21/2015 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2015609 |
| 10/21/2015 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2015608 |
| 09/29/2015 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2015607 |
| 09/01/2015 | Mid-Cycle Assessment Letter | 05000391/2015606 |
| 08/14/2015 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Operational Readiness Assessment Team Inspection Report | 05000391/2015611 |
| 08/14/2015 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2015605 |
| 06/29/2015 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2015604 |
| 05/22/2015 | Watts Bar Nuclear Plant Unit 2 Construction - NRC Problem Identification and Resolution Inspection Report | 05000391/2015613 |
| 05/01/2015 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2015603 |
| 03/24/2015 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2015602 |
| 02/27/2015 | End-Of-Cycle Assessment Letter | 05000391/2015601 |
| 02/13/2015 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2014615 |
| 12/29/2014 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2014614 |
| 11/14/2014 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2014608 |
| 09/30/2014 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2014607 |
| 09/03/2014 | Mid-Cycle Assessment Letter – Watts Bar Nuclear Plant Unit 2 | 05000391/2014606 |
| 08/13/2014 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2014605 |
| 06/25/2014 | Watts Bar Nuclear Plant Unit 2 Construction- NRC Integrated Inspection Report | 05000391/2014604 |
| 05/15/2014 | Watts Bar Nuclear Plant Unit 2 Construction – NRC Problem Identification And Resolution Inspection Report | 05000391/2014611 |
| 05/09/2014 | Watts Bar Nuclear Plant, Unit 2 Construction- NRC Integrated Inspection | 05000391/2014603 |
| 04/17/2014 | Public Meeting Summary - Watts Bar Nuclear Unit 2 (NRC Inspection Report) | 05000391/2014601 |
| 04/17/2014 | Meeting Summary - Public Meeting Watts Bar Nuclear Unit 2 | |
| 03/27/2014 | Watts Bar Nuclear Plant, Unit 2 Construction - NRC Integrated Inspection Report | 05000391/2014602 |
| 02/28/2014 | End-Of-Cycle Assessment Letter | 05000391/2014601 |
| 02/14/2014 | Watts Bar Nuclear Plant, Unit 2 Construction- NRC Integrated Inspection | 05000391/2013610 |
| 12/18/2013 | Watts Bar Nuclear Plant, Unit 2 Construction- NRC Integrated Inspection | 05000391/2013609 |
| 11/08/2013 | Integrated Construction Inspection Report | 05000391/2013608 |
| 11/07/2013 | Watts Bar Nuclear Plant, Unit 1, Fire Protection Triennial; and Unit 2, Fire Construction Deficiency Reports Inspection | 05000391/2013615 |
| 09/30/2013 | Integrated Construction Inspection Report | 05000391/2013607 |
| 09/03/2013 | Mid-Cycle Assessment Letter- Watts Bar Nuclear Plant Unit 2 | 05000391/2013606 |
| 08/07/2013 | Integrated Construction Inspection Report | 05000391/2013605 |
| 08/07/2013 | Integrated Construction Inspection Report | 05000391/2013605 |
| 06/27/2013 | Integrated Construction Inspection Report | 05000391/2013604 |
| 06/18/2013 | EA-13-019 Watts Bar Unit 2, Notice of Violation and Proposed Imposition of Civil Penalty | 05000391/2013614 |
| 06/07/2013 | Problem Identification and Resolution Inspection Report | 05000391/2013613 |
| 05/13/2013 | Integrated Construction Inspection Report | 05000391/2013603 |
| 04/17/2013 | Public Meeting Summary - Watts Bar Nuclear Plant Unit 2 | 05000391/2013601 |
| 03/28/2013 | Integrated Construction Inspection Report | 05000391/2013612 |
| 03/26/2013 | Focused Problem Identification and Resolution Inspection Report – Commercial Grade Dedication | 05000391/2013611 |
| 03/04/2013 | Annual Assessment Letter for Watts Bar Nuclear Plant Unit 2 | 05000390/2013601 |
| 02/04/2013 | Integrated Construction Inspection Report | 05000391/2012610 |
| 12/20/2012 | Integrated Construction Inspection Report | 05000391/2012609 |
| 11/13/2012 | Integrated Construction Inspection Report | 05000391/2012608 |
| 10/01/2012 | Integrated Construction Inspection Report | 05000391/2012607 |
| 08/07/2012 | Integrated Construction Inspection Report | 05000391/2012605 |
| 06/14/2012 | Integrated Construction Inspection Report | 05000391/2012604 |
| 05/25/2012 | Public Meeting Summary - Watts Bar Nuclear Plant Unit 2 | 05000391/2012612 |
| 05/09/2012 | Problem Identification and Resolution Inspection Report | 05000391/2012612 |
| 05/01/2012 | Integrated Construction Inspection Report | 05000391/2012603 |
| 03/27/2012 | Integrated Construction Inspection Report | 05000391/2012602 |
| 03/05/2012 | End–Of-Cycle Assessment Letter | 05000391/2012601 |
| 02/03/2012 | Integrated Construction Inspection Report | 05000391/2011610 |
| 12/16/2011 | Integrated Construction Inspection Report | 05000391/2011609 |
| 12/14/2011 | Integrated Construction Inspection Report | 05000391/2011612 |
| 11/04/2011 | Integrated Construction Inspection Report | 05000391/2011608 |
| 09/30/2011 | Integrated Construction Inspection Report | 05000391/2011607 |
| 08/05/2011 | Integrated Construction Inspection Report | 05000391/2011605 |
| 06/28/2011 | Integrated Construction Inspection Report | 05000391/2011604 |
| 06/28/2011 | Problem Identification and Resolution Inspection Report | 05000391/2011611 |
| 05/16/2011 | Integrated Construction Inspection Report | 05000391/2011603 |
| 05/13/2011 | Integrated Construction Inspection Report | 05000391/2011606 |
| 03/18/2011 | Integrated Construction Inspection Report | 05000391/2011602 |
| 02/09/2011 | Integrated Construction Inspection Report | 05000391/2010605 |
| 10/29/2010 | Integrated Construction Inspection Report | 05000391/2010604 |
| 10/01/2010 | Problem Identification and Resolution Inspection Report | 05000391/2010607 |
| 08/13/2010 | Integrated Construction Inspection Report | 05000391/2010606 |
| 08/05/2010 | Integrated Construction Inspection Report | 05000391/2010603 |
| 04/30/2010 | Integrated Construction Inspection Report | 05000391/2010602 |
| 01/29/2010 | Integrated Construction Inspection Report | 05000391/2009605 |
| 10/30/2009 | Integrated Construction Inspection Report | 05000391/2009604 |
| 07/31/2009 | Integrated Construction Inspection Report | 05000391/2009603 |
| 04/30/2009 | Integrated Construction Inspection Report | 05000391/2009602 |
| 01/29/2009 | Integrated Construction Inspection Report | 05000391/2008010 |
| 10/30/2008 | Integrated Construction Inspection Report | 05000391/2008009 |
| 07/29/2008 | Integrated Construction Inspection Report | 05000391/2008007 |
| 04/30/2008 | Integrated Construction Inspection Report | 05000391/2008006 |