Application Review Schedule for SHINE Medical Technologies, LLC Operating License

SHINE Medical Technologies, LLC submitted an operating license application for a medical radioisotope facility. The following table summarizes the U.S. Nuclear Regulatory Commission's key milestones for reviewing this application.
 
Key Milestones Completion Date
Actual—A
Target—T
Application Tendered
Receipt of Operating License Application
08/2019—A
Acceptance Review
Acceptance of Application for Docketing
10/2019—A
Federal Register Notice
Issuance of Notice of Opportunity to Request Hearing
01/2020—A
Closing of Opportunity to Request Hearing
03/2020—A
Environmental Review Schedule
Environmental Scoping Meeting
12/2019—A
NUREG Publication of Supplemental Draft Environmental Impact Statement
06/2022—A
NUREG Publication of Supplement Final Environmental Impact Statement
02/2023—A
Safety Review Schedule
Draft Safety Evaluation Report
11/2022—A
Final Safety Evaluation Report
02/2023—A
Advisory Committee on Reactor Safeguards (ACRS)
ACRS Subcommittee Meeting
03/2022—A
ACRS Subcommittee Meeting
05/2022—A
ACRS Subcommittee Meeting
07/2022—A
ACRS Subcommittee Meeting
09/2022—A
ACRS Full Committee Meeting
11/2022—A
Construction Inspection
Notification of Substantial Completion of Construction
TBD
Hearing
Contested Hearing on Issuance of Operating License
No Petitions for Hearing Received by Deadline
License
Determination on Whether to Issue Operating License
TBD
First Production
2024

Page Last Reviewed/Updated Friday, March 31, 2023