Application Review Schedule for Sweetwater Uranium Mill
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Kennecott Uranium Co. submitted to renew its license for the Sweetwater Uranium Mill Conventional Uranium Mill site.
Key Milestones | Completion Date Actual - A Target - T |
---|---|
Application Tendered (docketed date) | 09/08/14 – A |
Acceptance Review | |
Financial Re-baseline Acceptance Review Complete | 09/16/14 – A |
Docketing Decision Letter Issued/Acceptance Review Complete for Technical Review | 11/25/14 – A |
Financial Review | |
Requests for Additional Information (RAIs) on financial rebaseline portion of application | 12/01/14 – A |
Publish FRN - notice of Opportunity for hearing | 01/30/15 – A |
Financial 5 year Rebaseline Amendment Issued | 02/02/15 – A |
Safety Review * | |
Round 1 of RAIs Issued for Technical/Environmental Review | 07/13/15 – A |
Second Round of RAIs issued to licensee | 02/12/16 – A |
Draft License Conditions Issued | 08/25/16 – A |
RAI responses received with change of design | 10/12/16 – A |
Third round of RAIs issued to the licensee | 06/16/17 – A |
Final Safety Evaluation Report (SER) completed | 02/28/18 – A |
Environmental Review | |
Draft Environmental Assessment (EA) Issued | 03/26/18 – A |
Final EA Issued | 06/04/18 – A |
Record of Decision | |
License Amendment issued | 07/05/18 – A |
* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.
Page Last Reviewed/Updated Wednesday, March 24, 2021
Page Last Reviewed/Updated Wednesday, March 24, 2021