Application Review Schedule for Marsland
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Cameco (Crow Butte Resources) submitted to obtain a license amendment for its Marsland In-Situ Recovery Expansion Area.
Key Milestones | Completion Date Actual – A Target – T |
---|---|
Application Tendered | 06/20/12 – A |
Acceptance Review | |
Acceptance Review Start | 08/06/12 – A |
Docketing Decision Issued/Acceptance Review Completed | 10/05/12 – A |
Safety Review | |
Requests for Additional Information (RAIs) issued to Applicant | 07/03/13 – A |
RAI Responses with revised Technical Report (TR) received from Applicant* | 11/12/15 – A |
Open-Issues submitted to Applicant | 04/21/16 – A 06/06/16 – A |
Open-Issues Responses received from Applicant** | 06/30/17 – A |
Safety Evaluation Report (SER) completed | 01/29/18 – A |
Environmental Review | |
Draft EA issued | 12/15/17 – A |
Final EA issued | 04/27/18 – A |
License | |
Licensing Action Completed – License Amendment Issued | 05/23/18 – A |
*Staff identified numerous open issues and additional RAIs associated with new data presented in the November 2015 revised TR. Staff provided open issues to the applicant in public meetings dated 4/6/2016 and 6/14/2016.
**June 2017 submittal covered significant additional characterization.