NUREG 0933

Displaying 26 - 50 of 51

DESCRIPTION Historical Background In an AEOD memorandum [1] to NRR, it was concluded that the design of the Point Beach Nuclear Plant, Units 1 and 2, under certain conditions, allowed manual interconnection of redundant electrical load groups, thereby …
DESCRIPTION Historical Background In August 1982, AEOD reviewed a number of LERs related to Class 1E safety related switchgear circuit breakers and found a high incidence of their failure to close on demand. A preliminary report was written and …
DESCRIPTION Historical Background This issue was identified at an NRC Operating Reactor Events meeting on January 7, 1982, [1] and addressed fire protection system (FPS) actuations that resulted in adverse interactions with safety-related equipment at …
DESCRIPTION Historical Background This issue was raised [1] by DSI/NRR in August 1982 [2] following a search of LERs which suggested that additional licensing attention was needed for certain ancillary power plant equipment. The available information …
DESCRIPTION Historical Background On August 12, 1983, one of the three emergency diesel generators (EDG) at the Shoreham Plant failed during overload testing as a result of a fractured crankshaft. The failure occurred in EDG-102 and similar crankshaft …
DESCRIPTION In the prioritization of Issue 22, "Inadvertent Boron Dilution," it was found that inadvertent boron dilution events during cold shutdown operation do not constitute a significant risk to the public. Further work by DSI confirmed this …
DESCRIPTION Historical Background Combustible gases such as H 2 , propane, and acetylene are used during normal operations of nuclear power plants in limited quantities and for relatively short periods of time. H 2 , the most prevalent of these gases in …
DESCRIPTION Historical Background This issue was identified in a DL/NRR memorandum [1] which called for an assessment of the high failure frequency of main transformers and the resultant safety implications. Concern for this issue arose when the North …
DESCRIPTION Historical Background This issue was identified in a DST/NRR memorandum [1] which addressed a condition in which some protective devices intended to trip active engineered safety features (ESF) components, under indication of equipment …
DESCRIPTION Historical Background This issue was identified in a RRAB memorandum [1] in March 1985 and addressed the possibility of relay contact chatter during a seismic event and its resulting effect upon safety and safety-related electrical control …
DESCRIPTION In December 1984, the staff recommended in SECY-83-357B [1] that rulemaking with regard to H 2 control for LWRs with large, dry containments could be safely deferred due to the greater inherent capability of these containments to accommodate …
DESCRIPTION Following the NRR reorganization in November 1985, EIB/DSRO was responsible for resolving three issues that were directly related to onsite electrical systems: Issue 48, "LCO for Class 1E Vital Instrument Buses in Operating Reactors"; Issue …
DESCRIPTION Historical Background This issue was identified by NRR/EIB in February 1986 when it was suggested that Issue 106, "Piping and the Use of Highly Combustible Gases in Vital Areas," be expanded to include new safety concerns associated with the …
DESCRIPTION Historical Background This issue was identified as an alternative approach to the Finding 15 recommendation [1] discussed in Issue 125.I.5, "Safety Systems Tested in All Conditions Required by DBA," which states that "[t]horough integrated …
DESCRIPTION This issue was identified [1] by NRR to address the concerns raised during the licensing of Nine Mile Point Unit 2. On February 7, 1985, Niagara Mohawk submitted to the NRC a report on "Non-Class 1E Devices Connected to Class 1E Power …
DESCRIPTION Historical Background This issue was identified [1] by NRR as a result of a diagnostic evaluation team inspection of the SWS at Zion, a multiplant site. The inspection identified the potential for some additional shared systems to have an …
DESCRIPTION Historical Background Issue 106 was resolved with the issuance of Generic Letter 93-06, "Research Results on Generic Safety Issue 106, Piping and the Use of Highly Combustible Gases in Vital Areas," dated October 25, 1993, [1] which included …
DESCRIPTION As discussed in SECY-93-049, [1] the staff reviewed significant license renewal issues and found that several related to environmental qualification (EQ). A key aspect of these issues was whether the licensing bases, particularly for older …
DESCRIPTION Historical Background This issue was identified [1] by NRR following the issuance of NRC Information Notice (IN) 93-17 [2] which was based in part on a deficiency in the Surry Power Station emergency diesel generator (DG) loading. This …
In resolving GSIs over the years, the staff generally found it necessary to make assumptions and establish limitations on the scope of the issues. As a result of its review of the resolution of some GSIs, the ACRS expressed concerns that the assumptions …
DESCRIPTION On August 24, 1992, Hurricane Andrew hit south Florida and caused extensive onsite and offsite damage at Turkey Point. Following this hurricane which was classified Category 4, an NRC/industry team was organized to: (1) review the damage …
DESCRIPTION Historical Background The issue of potential hazards from combustible gases was raised [1] after two events involving hydrogen combustion occurred within 2 months in late-2001 at two foreign BWRs. Both these events involved sudden rupture of …
DESCRIPTION Historical Background This issue was raised [1] , [2] by an NMSS staff member whose concern arose from the observation that spent fuel pool racks using Boral for neutron absorption had experienced some problems with swelling and degradation of …
DESCRIPTION Historical Background This issue was initiated [1] in response to a recommendation in the screening analysis of Generic Issue (A)             I-195, "Potential Hydrogen Combustion in BWR Piping." GI-195 investigated the potential safety …
DESCRIPTION Historical Background This issue was identified by RES after concern was raised for the number of component failures in the solid state protection systems of nuclear power plants that were caused by the growth of tin whiskers. [1] In 1987, …

Page Last Reviewed/Updated 3/1/2026

Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.