Skip to main content

NUREG 0933

Displaying 1 - 25 of 30

TASK II.E.1: AUXILIARY FEEDWATER SYSTEM The objective of this task was to improve the reliability of the auxiliary feedwater (AFW) system. ITEM II.E.1.1: AUXILIARY FEEDWATER SYSTEM EVALUATION This item was clarified in NUREG-0737, [1] requirements were …
The objectives of this task were to perform systems reliability analyses and to effect changes in emergency operating procedures and operator training to improve the capability of plants to mitigate the consequences of the small-break LOCAs and …
DESCRIPTION Prior to 1978, operating experience with PWR steam generators was characterized by extensive corrosion and mechanically-induced degradation of the steam generator tubes, frequent plant shutdowns to repair primary-to- secondary leaks, and two …
DESCRIPTION This item was originally identified in NUREG-0371 [1] and was later declared a USI in NUREG-0510. [2] (See Item A-3 for further details.) CONCLUSION This item was RESOLVED and requirements were established. (See Item A-3 for further details.) …
DESCRIPTION During the course of the licensing action for North Anna Units 1 and 2, a number of questions were raised as to the potential for lamellar tearing and low fracture toughness of the steam generator and RCP support materials for these …
DESCRIPTION Historical Background This issue effects all PWR-type reactors (Westinghouse, CE, B&W). The issue as described, [1] , [2] , [3] concerns postulated accidents resulting from a steam line break which consequentially results in a steam generator …
DESCRIPTION Historical Background This issue was identified [1] after AEOD completed a study on internal appurtenances in LWRs. This study, AEOD/E101, [2] was initiated because of the relatively high number of LERs that described events in which internal …
DESCRIPTION In AEOD/CO05, [1] AEOD identified potential safety problems concerning steam generator overfill due to control system failures and combined primary and secondary blowdown. As a result of discussions with the Commissioners and the EDO, NRR …
DESCRIPTION AEOD issued a memorandum [1] in which a potential safety issue involving combined primary and secondary system LOCAs was raised. The issue was discussed at Commission meetings on October 16, 1980 and on November 10, 1980. NRR informed AEOD of …
DESCRIPTION Historical Background On April 7, 1980, Arkansas Nuclear One (ANO) Units 1 and 2 experienced a significant event resulting from a loss of offsite power. Although both units were safely shut down, the analysis and evaluation of the event …
DESCRIPTION Historical Background This issue was identified at an NRC Operating Reactor Events meeting on January 7, 1982, [1] and addressed fire protection system (FPS) actuations that resulted in adverse interactions with safety-related equipment at …
DESCRIPTION Historical Background Following the steam generator tube rupture (SGTR) event at Ginna in January 1982, [1] the staff proceeded to develop generic steam generator requirements which would help mitigate or reduce steam generator tube …
DESCRIPTION Following the SGTR event at Ginna on January 25, 1982, increased staff effort was placed on developing means to mitigate and reduce steam generator tube degradations and ruptures. To meet these objectives, two steps were taken. The first step …
DESCRIPTION Historical Background In an evaluation of INPO/NSAC Significant Operating Experience Report 81-17, [1] the operators at Fort Calhoun determined that the configuration of their plant made it susceptible to the possibility that all AFW supply …
DESCRIPTION Historical Background PORVs and block valves were originally designed as non-safety components in the reactor pressure control system for use only when plants are in operation. The block valves were installed because of expected leakage from …
DESCRIPTION Historical Background This issue was recommended [1] for prioritization by DSI after a review of the AEOD engineering evaluation report (AEOD/E325) [2] on vapor binding of the AFW pumps at H.B.Robinson Unit 2. Further AEOD study of the event …
DESCRIPTION Historical Background Once-through steam generators (OTSGs) are a feature unique to B&W reactor designs. Main feedwater is injected from a header, located at approximately mid-elevation of the OTSG, into an annular downcomer region. As the …
DESCRIPTION In December 1984, the staff recommended in SECY-83-357B [1] that rulemaking with regard to H 2 control for LWRs with large, dry containments could be safely deferred due to the greater inherent capability of these containments to accommodate …
DESCRIPTION The loss of all feedwater event at Davis-Besse on June 9, 1985, resulted in the formation of an NRC project team to investigate the event. The team's findings were published in NUREG-1154 [1] and were subsequently reviewed by DL/NRR. As a …
DESCRIPTION In 1985, operating experience as well as staff and industry studies indicated that AFW systems continued to fail at a high rate. These studies also indicated that plants with similar AFW system reliabilities (as calculated in accordance with …
DESCRIPTION Steam generator overfill and its consequences have received staff and industry attention because of the frequency and severity of overfill events. Over the years, a number of issues have been raised concerning steam generator overfill …
DESCRIPTION Historical Background This issue was identified by NRR/EIB in February 1986 when it was suggested that Issue 106, "Piping and the Use of Highly Combustible Gases in Vital Areas," be expanded to include new safety concerns associated with the …
DESCRIPTION Historical Background This issue was identified as an alternative approach to the Finding 15 recommendation [1] discussed in Issue 125.I.5, "Safety Systems Tested in All Conditions Required by DBA," which states that "[t]horough integrated …
DESCRIPTION Historical Background This issue was raised in SECY-89-170 [1] and addressed the potential for control system vulnerabilities as a result of fire-induced alternate shutdown/control room panel interactions. Concern for these interactions arose …
DESCRIPTION Historical Background This issue was raised in SECY-89-170 [1] and addressed the effectiveness of manual fire-fighting in the presence of smoke. This concern arose as a result of an NRC-sponsored Fire Risk Scoping Study [2] which focused on …

Page Last Reviewed/Updated 3/1/2026

Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.