DESCRIPTION Historical Background Cracks were found in the normal make-up high pressure injection (MU/HPI) nozzles of several B&W plants following an inspection of the 8 B&W plants licensed to operate. These cracks appeared to be directly related to loose …
DESCRIPTION Historical Background PORVs and block valves were originally designed as non-safety components in the reactor pressure control system for use only when plants are in operation. The block valves were installed because of expected leakage from …
DESCRIPTION Background This issue was raised in Board Notification No. 82-81 [1] and addressed the failure of control rod drive (CRD) guide tube support pins in W reactors. The first pin failure at a U.S. plant occurred at North Anna 1 in 1982 where a …
DESCRIPTION Historical Background During the period 1978 to 1980, there were reports of fatigue failure of thermal sleeve assemblies in the piping systems of both PWRs and BWRs. The BWR problem was addressed by GE in NEDO-21821 and was resolved with a …
DESCRIPTION Historical Background This issue was identified [1] when a number of concerns regarding DC power systems were raised during the review of the proposed resolution of Issue A-30, "Adequacy of Safety-Related DC Power Supplies." The main concerns …
DESCRIPTION Historical Background On November 11, 1981, the DAILY REPORT-REGION I carried a "prompt report" from Calvert Cliffs Units 1 and 2 indicating the licensee had been notified that the water tight integrity of the service water pump rooms in both …
DESCRIPTION Historical Background STS for newer OLs require licensees to keep account of the number of transient occurrences to ensure that transient limits, based on design assumptions, are not exceeded. However, a number of older plants for which …
DESCRIPTION Historical Background On March 18, 1983, B&W expressed [1] concern for unanalyzed reactor vessel thermal stress that could occur during natural convection cooldown of PWRs. The concern emerged from a preliminary B&W evaluation of a voiding …
DESCRIPTION Historical Background This issue was identified by the ACRS in 1978 during the operating license reviews of some BWRs. The ACRS posed questions concerning the likelihood and effects of a LOCA which could cause interactions with the CRD …
DESCRIPTION This issue was raised by the ACRS in a memorandum [1] to the Commission in October 1983. Following the TMI-2 accident, the purpose and use of PORVs had been the subject of considerable analyses and discussion. The original purpose for which …
DESCRIPTION Historical Background In BWRs, SRVs are mounted on the main steam line inside the drywell. Each SRV discharge is piped through its own discharge line (tailpipe) to a point below the minimum water level in the primary containment suppression …
DESCRIPTION Historical Background In March 1982, leaks were detected in the heat-affected zones of the safe-end-to-pipe welds in two of the 28 in. diameter recirculation loop safe ends at Nine Mile Point Unit 1. Subsequent UT revealed extensive cracking …
DESCRIPTION Historical Background The HPCI steam supply line has two containment isolation valves in series: one inside and one outside of the containment. Both are normally open in most plants; however, two plants were found to operate with the HPCI …
DESCRIPTION Historical Background Experiments conducted at several test facilities prior to 1984 showed that irradiated fuel can fragment (crumble) into small pieces during a LOCA. Some evaluation of this effect was made for NRC by EG&G. [1] Although it …
DESCRIPTION Historical Background Low temperature overpressurization originally identified in NUREG 0371 [1] as item A-26. This issue later became USI A-26 and was resolved in September 1978 with a revision to SRP [2] Section 5.2. The resolution of USI …
DESCRIPTION Historical Background This concern was raised by an NRC resident inspector who questioned the practice of leaving the refueling canal drain valve in the closed position during operations at H. B. Robinson Unit 2. [1] A subsequent investigation …
DESCRIPTION Historical Background This issue was identified during the staff review of the Indian Point 2 and Zion PRAs [1] ; in both of these studies, the dominant interfacing systems LOCA events were estimated to be through the RHR suction valves. The …
DESCRIPTION In the prioritization of Issue 22, "Inadvertent Boron Dilution," it was found that inadvertent boron dilution events during cold shutdown operation do not constitute a significant risk to the public. Further work by DSI confirmed this …
DESCRIPTION Historical Background Issue B-63, which was resolved and implemented as MPA B-45, required leak-testing of the check valves that isolate those low pressure systems that are connected to the RCS outside the containment. However, except for …
DESCRIPTION Historical Background Combustible gases such as H 2 , propane, and acetylene are used during normal operations of nuclear power plants in limited quantities and for relatively short periods of time. H 2 , the most prevalent of these gases in …
DESCRIPTION Historical Background Potential stress corrosion cracking (SCC) of reactor vessel (RV) closure studs was raised as a GSI in December 1984. [1] Concerns were expressed that two contributors to SCC had not been subject to careful research and …
DESCRIPTION Historical Background This issue was identified in a DST/NRR memorandum [1] which addressed a condition in which some protective devices intended to trip active engineered safety features (ESF) components, under indication of equipment …
DESCRIPTION In an August 1983 memorandum, [1] the EDO requested a comprehensive review of NRC requirements in the area of nuclear power plant piping. In response to this request, the NRC Piping Review Committee (PRC) was formed to review and evaluate …
DESCRIPTION The loss of all feedwater event at Davis-Besse on June 9, 1985, resulted in the formation of an NRC project team to investigate the event. The team's findings were published in NUREG-1154 [1] and were subsequently reviewed by DL/NRR. As a …
DESCRIPTION Historical Background Potential seismic interaction involving the movable in-core flux mapping systems was identified as a generic issue in August 1985. [1] This potential interaction exists because portions of the in-core flux mapping system, …