NUREG 0933
Applied Filters
Displaying 26 - 50 of 74
DESCRIPTION This NUREG-0471 [1] item was an ACRS generic concern that initially addressed the common mode failure of identical components exposed to identical or nearly-identical conditions or environments. This concern was later expanded to include other …
1
DESCRIPTION Background Flow-induced vibrations caused by vortex shedding resulting from rapid area change, buffeting due to random flow turbulence, fluid structures interaction instability, leakage excitation, steady operation of positive displacement …
1
DESCRIPTION This issue involves a potential deficiency in the ability to control leakage past the main steam isolation valves (MSIV) in BWR plants. Requirements for MSIV leakage control systems outlined in Regulatory Guide 1.96 [1] were developed as a …
1
DESCRIPTION Historical Background In the event of a LOCA in which offsite power remains available, the reactor operator may choose to shut down the emergency diesel generators shortly after the LOCA. If, after the diesels are shut down, offsite power is …
1
DESCRIPTION On November 10, 1979, an event occurred at the Oconee Power Station, Unit 3, that resulted in loss of power to a non-Class 1E 120-volt AC single-phase power panel that supplied power to the integrated control system (ICS) and the nonnuclear …
1
DESCRIPTION Historical Background This concern was raised [1] because of the potential for a high-altitude nuclear weapon detonation causing a large electromagnetic pulse (EMP) which subsequently could induce large currents and voltages in electrical …
1
DESCRIPTION Background This issue addressed the high rate of reactor coolant pump (RCP) seal failures that challenge the makeup capacity of the ECCS in PWRs. At the time this issue was identified [1] in 1980, RCP seal failures in BWRs occurred at a …
1
DESCRIPTION In a San Onofre Unit 1 Preliminary Notification issued in September 1980, it was reported that, during testing, the licensee had identified a problem with the design of the diesel generator sequencing circuitry. This problem occurred when a …
1
DESCRIPTION Historical Background This issue was identified [1] when AEOD expressed concerns about the use inside containment of a particular polymer coating that could flake off and fail when subjected to DBA conditions. In addition to the concern for …
1
DESCRIPTION Historical Background This issue was initiated in response to an immediate action memorandum [1] issued by AEOD in September 1981 regarding desiccant contamination of instrument air lines. NRR responded to the AEOD memorandum by establishing a …
1
DESCRIPTION Historical Background This proposed generic issue has its origin in a January 1981 event at Millstone Unit 2. [1] An operator inadvertently opened a 125V DC main feeder breaker, causing the loss of one of the two redundant emergency systems …
1
DESCRIPTION Historical Background On April 7, 1980, Arkansas Nuclear One (ANO) Units 1 and 2 experienced a significant event resulting from a loss of offsite power. Although both units were safely shut down, the analysis and evaluation of the event …
1
DESCRIPTION An AEOD memorandum [1] to NRR on July 15, 1980, identified the concern that some operating nuclear power plants do not have technical specifications or Administrative controls governing operational restrictions for Class 1E 120 VAC vital …
1
DESCRIPTION Historical Background In an AEOD memorandum [1] to NRR, it was concluded that the design of the Point Beach Nuclear Plant, Units 1 and 2, under certain conditions, allowed manual interconnection of redundant electrical load groups, thereby …
1
DESCRIPTION Historical Background In December 1981, AEOD completed a survey of valve operator-related events that occurred during 1978, 1979, and 1980 and submitted a draft report [1] to NRR for comment. In this study, AEOD established that motor- …
1
DESCRIPTION Historical Background In August 1982, AEOD reviewed a number of LERs related to Class 1E safety related switchgear circuit breakers and found a high incidence of their failure to close on demand. A preliminary report was written and …
1
DESCRIPTION Historical Background This issue was identified at an NRC Operating Reactor Events meeting on January 7, 1982, [1] and addressed fire protection system (FPS) actuations that resulted in adverse interactions with safety-related equipment at …
1
DESCRIPTION Historical Background Increasing attention has recently been focused on the integrity of RCP seals due to loss of cooling to the seals both in connection with PRA studies which are currently under review and from operating experience. [1] , …
1
DESCRIPTION Historical Background PORVs and block valves were originally designed as non-safety components in the reactor pressure control system for use only when plants are in operation. The block valves were installed because of expected leakage from …
1
DESCRIPTION Historical Background The HPCI steam supply line has two containment isolation valves in series: one inside and one outside of the containment. Both are normally open in most plants; however, two plants were found to operate with the HPCI …
1
DESCRIPTION Historical Background On August 12, 1983, one of the three emergency diesel generators (EDG) at the Shoreham Plant failed during overload testing as a result of a fractured crankshaft. The failure occurred in EDG-102 and similar crankshaft …
1
DESCRIPTION Historical Background This issue was recommended [1] for prioritization by DSI after a review of the AEOD engineering evaluation report (AEOD/E325) [2] on vapor binding of the AFW pumps at H.B.Robinson Unit 2. Further AEOD study of the event …
1
DESCRIPTION Historical Background This issue was identified during the staff review of the Indian Point 2 and Zion PRAs [1] ; in both of these studies, the dominant interfacing systems LOCA events were estimated to be through the RHR suction valves. The …
1
DESCRIPTION Historical Background During the review of LaSalle, ASB identified a potential problem which could be generic to all BWRs. [1] [2] The problem relates to ability of the CRD accumulators to retain pressure for a sufficient period of time after …
1
DESCRIPTION Historical Background On April 17, 1984, a DSI memorandum [1] on the subject of RHR interlocks for W plants described staff concerns that the design basis for RHR interlocks had been misunderstood and that these concerns had not been …
1
Page Last Reviewed/Updated 3/1/2026
Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.