Skip to main content

NUREG 0933

Displaying 26 - 50 of 76

DESCRIPTION This issue involves a potential deficiency in the ability to control leakage past the main steam isolation valves (MSIV) in BWR plants. Requirements for MSIV leakage control systems outlined in Regulatory Guide 1.96 [1] were developed as a …
DESCRIPTION Background This issue addressed the high rate of reactor coolant pump (RCP) seal failures that challenge the makeup capacity of the ECCS in PWRs. At the time this issue was identified [1] in 1980, RCP seal failures in BWRs occurred at a …
DESCRIPTION Pressurized water reactors are susceptible to certain types of hypothetical accidents that, under circumstances such as operation of the reactor beyond a critical time in its life, could result in failure of the pressure vessel as a result of …
DESCRIPTION Historical Background Prior to 1981, the number of bolting-related incidents reported by licensees was on the increase. A large number of these were related to primary pressure boundary applications and major component support structures. As a …
DESCRIPTION Historical Background This issue was raised by AEOD [1] , [2] and involved isolation of the reactor coolant system charging and letdown system following a spurious safety injection transient at H. B. Robinson on January 29, 1981. Following the …
DESCRIPTION In AEOD/CO05, [1] AEOD identified potential safety problems concerning steam generator overfill due to control system failures and combined primary and secondary blowdown. As a result of discussions with the Commissioners and the EDO, NRR …
DESCRIPTION Historical Background This issue was identified [1] when AEOD expressed concerns about the use inside containment of a particular polymer coating that could flake off and fail when subjected to DBA conditions. In addition to the concern for …
DESCRIPTION Historical Background This issue was initiated in response to an immediate action memorandum [1] issued by AEOD in September 1981 regarding desiccant contamination of instrument air lines. NRR responded to the AEOD memorandum by establishing a …
DESCRIPTION Historical Background In response to a 1967 ACRS concern relative to the potential of melting and subsequent disintegration of a portion of a fuel assembly due to inlet orifice flow blockage, GE submitted NEDO-10174 [1] in May 1970. As a …
DESCRIPTION Historical Background In December 1981, AEOD completed a survey of valve operator-related events that occurred during 1978, 1979, and 1980 and submitted a draft report [1] to NRR for comment. In this study, AEOD established that motor- …
DESCRIPTION Historical Background This issue was identified at an NRC Operating Reactor Events meeting on January 7, 1982, [1] and addressed fire protection system (FPS) actuations that resulted in adverse interactions with safety-related equipment at …
DESCRIPTION This issue was raised in November 1981 by the Materials Engineering Branch (MTEB), DE/NRR, and was based on the concern that NRC provides no control regulations or guides for bolting other than for the reactor vessel head. CONCLUSION In …
DESCRIPTION Historical Background Increasing attention has recently been focused on the integrity of RCP seals due to loss of cooling to the seals both in connection with PRA studies which are currently under review and from operating experience. [1] , …
DESCRIPTION Historical Background Cracks were found in the normal make-up high pressure injection (MU/HPI) nozzles of several B&W plants following an inspection of the 8 B&W plants licensed to operate. These cracks appeared to be directly related to loose …
DESCRIPTION Historical Background PORVs and block valves were originally designed as non-safety components in the reactor pressure control system for use only when plants are in operation. The block valves were installed because of expected leakage from …
DESCRIPTION Background This issue was raised in Board Notification No. 82-81 [1] and addressed the failure of control rod drive (CRD) guide tube support pins in W reactors. The first pin failure at a U.S. plant occurred at North Anna 1 in 1982 where a …
DESCRIPTION Historical Background During the period 1978 to 1980, there were reports of fatigue failure of thermal sleeve assemblies in the piping systems of both PWRs and BWRs. The BWR problem was addressed by GE in NEDO-21821 and was resolved with a …
DESCRIPTION Historical Background STS for newer OLs require licensees to keep account of the number of transient occurrences to ensure that transient limits, based on design assumptions, are not exceeded. However, a number of older plants for which …
DESCRIPTION Historical Background On March 18, 1983, B&W expressed [1] concern for unanalyzed reactor vessel thermal stress that could occur during natural convection cooldown of PWRs. The concern emerged from a preliminary B&W evaluation of a voiding …
DESCRIPTION Historical Background This issue was identified by the ACRS in 1978 during the operating license reviews of some BWRs. The ACRS posed questions concerning the likelihood and effects of a LOCA which could cause interactions with the CRD …
DESCRIPTION This issue was raised by the ACRS in a memorandum [1] to the Commission in October 1983. Following the TMI-2 accident, the purpose and use of PORVs had been the subject of considerable analyses and discussion. The original purpose for which …
DESCRIPTION Historical Background In March 1982, leaks were detected in the heat-affected zones of the safe-end-to-pipe welds in two of the 28 in. diameter recirculation loop safe ends at Nine Mile Point Unit 1. Subsequent UT revealed extensive cracking …
DESCRIPTION Historical Background The HPCI steam supply line has two containment isolation valves in series: one inside and one outside of the containment. Both are normally open in most plants; however, two plants were found to operate with the HPCI …
DESCRIPTION Historical Background This issue was recommended [1] for prioritization by DSI after a review of the AEOD engineering evaluation report (AEOD/E325) [2] on vapor binding of the AFW pumps at H.B.Robinson Unit 2. Further AEOD study of the event …
DESCRIPTION Historical Background Low temperature overpressurization originally identified in NUREG 0371 [1] as item A-26. This issue later became USI A-26 and was resolved in September 1978 with a revision to SRP [2] Section 5.2. The resolution of USI …

Page Last Reviewed/Updated 3/1/2026

Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.