The objective of this task was to enhance public safety and reduce individual and societal risk by developing and implementing a phased program to include, in safety reviews, consideration of core degradation and melting beyond the design basis. ITEM …
The objective of this task was to provide instrumentation to monitor plant variables and systems during and following an accident. Indications of plant variables and status of systems important to safety are required by the plant operator (licensee) …
The objective of this task was to increase the reliability and diversification of the electrical power supplies for certain safety-related equipment. ITEM II.G.1: POWER SUPPLIES FOR PRESSURIZER RELIEF VALVES, BLOCK VALVES, AND LEVEL INDICATORS DESCRIPTION …
TASK III.D.1: RADIATION SOURCE CONTROL The objective of this task is to perform evaluations to establish additional design features that should be included in the rulemaking proceeding of Item II.B.8. The purpose of these evaluations is to identify design …
The objective of this task was to improve public radiation protection in the event of a nuclear power plant accident by improving (1) radioactive effluent monitoring, (2) the dose analysis for accidental releases of radioiodine, tritium, and carbon-14, …
The objective of this task is to improve nuclear power plant worker radiation protection to allow workers to take effective action to control the course and consequences of an accident, as well as to keep exposures as low as reasonably achievable (ALARA) …
The objective of this task is to respond to the President's request for NRC participation in the Radiation Policy Council. ITEM IV.H.1: NRC PARTICIPATION IN THE RADIATION POLICY COUNCIL DESCRIPTION The Radiation Policy Council, a policy coordinating body …
DESCRIPTION Historical Background Operation of a LWR results in slow corrosion of the interior metal surfaces of the primary coolant system. The resulting corrosion products circulate through the reactor core and are activated by neutron flux from the …
DESCRIPTION At the time this issue was identified in NUREG-0371, [1] trends in the design of nuclear power plants showed an increase in the use of digital computer technology in safety-related instrumentation and control systems. The first application of …
DESCRIPTION At the time this issue was identified in NUREG-0371, [1] compliance with NEPA required that alternatives to a proposed Federal action be considered, and that required alternatives be balanced against the base case in terms of their associated …
DESCRIPTION CP applicants for which SERs were issued after July 1, 1974, were required by the NRC to qualify all safety- related equipment to IEEE 323. [1] From the time this standard was originated, the industry developed methods that were used to …
DESCRIPTION Historical Background This issue is documented in NUREG-0371 [1] and addresses the adequacy of safety-related DC power supplies which was questioned by a nuclear consultant in a letter to the ACRS in April 1977 (NUREG-0305, [2] Attachment B). …
DESCRIPTION This NUREG-0371 [1] item was initiated in order to develop criteria and guidelines to be used by applicants, licensees, and staff reviewers to support implementation of Regulatory Guide 1.97, [2] Revision 1. Such criteria and guidelines were …
DESCRIPTION Nuclear power plant instrumentation and control systems are composed of safety-related protection systems and non-safety-related control systems. The safety-related protection systems are designed to satisfy the General Design Criteria …
DESCRIPTION This NUREG-0471 [1] task will develop more reliable models and associated computer capability than currently available to the staff for assessing the radiological consequences of accidents that could result in the releases of radioactivity …
DESCRIPTION This NUREG-0471 [1] task involved the preparation of a paper detailing the bases for design basis flood events utilized by the staff in case reviews, including probable maximum floods, hurricanes, tsunamis, seiches, seismically-induced dam …
DESCRIPTION Historical Background This issue, as originally stated in 1978, [1] addressed the unavailability (at that time) of a suitable model to predict the erosion rates and, therefore, the flood hydrographs at nuclear power plant sites resulting from …
DESCRIPTION This NUREG-0471 [1] task involves the maintenance and improvement of calculational capabilities for assessing doses to individuals from radiation and radioactive effluents from normal operation and from radioactive releases from postulated …
DESCRIPTION Practice in health impact assessments at the time of identification of this issue was to convert radiation exposure estimates into estimates of health effects, such as cancer deaths, illness, and life shortening. However, the models that were …
DESCRIPTION Historical Background The ACRS raised a concern that there is a need to develop criteria for vibration monitoring systems which could provide early warning of excessive vibration inside the reactor vessel. This item is documented in …
DESCRIPTION Historical Background This NUREG-0471 [1] item was developed because of concerns regarding the long-term capability of hermetically- sealed instruments and equipment which must function in postaccident environments. Certain classes of …
DESCRIPTION This NUREG-0471 [1] item was an ACRS generic concern that initially addressed the common mode failure of identical components exposed to identical or nearly-identical conditions or environments. This concern was later expanded to include other …
DESCRIPTION Background This issue was identified [1] after a review of LERs involving the failure or degraded performance of essential equipment that resulted from the failure of protective devices such as fuses and circuit breakers. The affected systems …
DESCRIPTION Historical Background This issue is identified in Appendix D of NUREG-0572 [1] and is one of the key observations made after the ACRS requested its members and consultants to make comprehensive reviews of all LERs issued during the years 1976, …
DESCRIPTION Historical Background In the event of a LOCA in which offsite power remains available, the reactor operator may choose to shut down the emergency diesel generators shortly after the LOCA. If, after the diesels are shut down, offsite power is …