The objective of this task was to improve the quality assurance program (QA) for design, construction, and operations to provide greater assurance that plant design, construction, and operational activities were conducted in a manner commensurate with …
The objective of this task was to provide instrumentation to monitor plant variables and systems during and following an accident. Indications of plant variables and status of systems important to safety are required by the plant operator (licensee) …
TASK II.J.1: VENDOR INSPECTION PROGRAM The objective of this task was to improve vendor-supplied components and services through a modified and more effective vendor inspection program. ITEM II.J.1.1: ESTABLISH A PRIORITY SYSTEM FOR CONDUCTING VENDOR …
The objective of this task was to improve the qualification of licensees for operating nuclear power plants by requiring greater oversight of design, construction, and modification activities. ITEM II.J.3.1: ORGANIZATION AND STAFFING TO OVERSEE DESIGN AND …
The objective of this task was to clarify deficiency report requirements to obtain uniform reporting and earlier identification and correction of problems. ITEM II.J.4.1: REVISE DEFICIENCY REPORTING REQUIREMENTS DESCRIPTION This TMI Action Plan [1] item …
TASK III.D.1: RADIATION SOURCE CONTROL The objective of this task is to perform evaluations to establish additional design features that should be included in the rulemaking proceeding of Item II.B.8. The purpose of these evaluations is to identify design …
The objective of this task was to improve public radiation protection in the event of a nuclear power plant accident by improving (1) radioactive effluent monitoring, (2) the dose analysis for accidental releases of radioiodine, tritium, and carbon-14, …
DESCRIPTION Historical Background Operation of a LWR results in slow corrosion of the interior metal surfaces of the primary coolant system. The resulting corrosion products circulate through the reactor core and are activated by neutron flux from the …
DESCRIPTION This NUREG-0471 [1] task involves the maintenance and improvement of calculational capabilities for assessing doses to individuals from radiation and radioactive effluents from normal operation and from radioactive releases from postulated …
DESCRIPTION Compilation of occupational radiation exposure reports from operating reactors has shown that exposures to station and contractor personnel have generally been increasing over the past 7 years for both PWRs and BWRs. The overriding problem at …
DESCRIPTION This NUREG-0471 [1] task involves evaluating information from semiannual operating reports, inplant measurements program and topical reports, and revisions to models for calculating releases of radioactive materials in effluents from PWRs and …
DESCRIPTION Practice in health impact assessments at the time of identification of this issue was to convert radiation exposure estimates into estimates of health effects, such as cancer deaths, illness, and life shortening. However, the models that were …
DESCRIPTION Historical Background This issue is identified in Appendix D of NUREG-0572 [1] and is one of the key observations made after the ACRS requested its members and consultants to make comprehensive reviews of all Licensee Event Reports (LERs) …
DESCRIPTION The concern of this issue involves the requirement for verification that the balance-of-plant equipment satisfies the design intent. This issue was identified in NUREG-0705. [1] CONCLUSION Task I.F in NUREG-0660, [2] the TMI Action Plan, is a …
DESCRIPTION Historical Background Cracking has occurred in PWR piping systems as a result of stress corrosion, vibratory and thermal fatigue, and dynamic loading. However, as of February 1981, no cracking had been experienced in the primary system piping …
DESCRIPTION Historical Background Prior to 1981, the number of bolting-related incidents reported by licensees was on the increase. A large number of these were related to primary pressure boundary applications and major component support structures. As a …
DESCRIPTION Historical Background On April 7, 1980, Arkansas Nuclear One (ANO) Units 1 and 2 experienced a significant event resulting from a loss of offsite power. Although both units were safely shut down, the analysis and evaluation of the event …
DESCRIPTION Historical Background Cracks were found in the normal make-up high pressure injection (MU/HPI) nozzles of several B&W plants following an inspection of the 8 B&W plants licensed to operate. These cracks appeared to be directly related to loose …
DESCRIPTION Historical Background PORVs and block valves were originally designed as non-safety components in the reactor pressure control system for use only when plants are in operation. The block valves were installed because of expected leakage from …
DESCRIPTION Historical Background This issue was raised [1] by DSI/NRR in August 1982 [2] following a search of LERs which suggested that additional licensing attention was needed for certain ancillary power plant equipment. The available information …
DESCRIPTION Historical Background On two occasions (February 22 and 25, 1983), Salem Unit 1 failed to scram automatically due to failure of both reactor trip breakers to open on receipt of an actuation signal. In both cases, the unit was successfully …
DESCRIPTION In the prioritization of Issue 22, "Inadvertent Boron Dilution," it was found that inadvertent boron dilution events during cold shutdown operation do not constitute a significant risk to the public. Further work by DSI confirmed this …
DESCRIPTION Historical Background Combustible gases such as H 2 , propane, and acetylene are used during normal operations of nuclear power plants in limited quantities and for relatively short periods of time. H 2 , the most prevalent of these gases in …
DESCRIPTION Historical Background This issue was raised [1] in March 1985 to address the staff's concern that there were no requirements for dynamic qualification testing or dynamic surveillance testing of large bore hydraulic snubbers (> 50 kips load …
DESCRIPTION In December 1984, the staff recommended in SECY-83-357B [1] that rulemaking with regard to H 2 control for LWRs with large, dry containments could be safely deferred due to the greater inherent capability of these containments to accommodate …

Page Last Reviewed/Updated 3/1/2026