NUREG 0933
Displaying 1 - 25 of 31
The objective of this task was to improve the quality assurance program (QA) for design, construction, and operations to provide greater assurance that plant design, construction, and operational activities were conducted in a manner commensurate with …
1
TASK II.E.1: AUXILIARY FEEDWATER SYSTEM The objective of this task was to improve the reliability of the auxiliary feedwater (AFW) system. ITEM II.E.1.1: AUXILIARY FEEDWATER SYSTEM EVALUATION This item was clarified in NUREG-0737, [1] requirements were …
1
TASK II.J.1: VENDOR INSPECTION PROGRAM The objective of this task was to improve vendor-supplied components and services through a modified and more effective vendor inspection program. ITEM II.J.1.1: ESTABLISH A PRIORITY SYSTEM FOR CONDUCTING VENDOR …
1
The objective of this task was to improve the qualification of licensees for operating nuclear power plants by requiring greater oversight of design, construction, and modification activities. ITEM II.J.3.1: ORGANIZATION AND STAFFING TO OVERSEE DESIGN AND …
1
The objective of this task was to clarify deficiency report requirements to obtain uniform reporting and earlier identification and correction of problems. ITEM II.J.4.1: REVISE DEFICIENCY REPORTING REQUIREMENTS DESCRIPTION This TMI Action Plan [1] item …
1
The objectives of this task were to perform systems reliability analyses and to effect changes in emergency operating procedures and operator training to improve the capability of plants to mitigate the consequences of the small-break LOCAs and …
1
DESCRIPTION The concern of this issue involves the requirement for verification that the balance-of-plant equipment satisfies the design intent. This issue was identified in NUREG-0705. [1] CONCLUSION Task I.F in NUREG-0660, [2] the TMI Action Plan, is a …
1
DESCRIPTION Historical Background Cracking has occurred in PWR piping systems as a result of stress corrosion, vibratory and thermal fatigue, and dynamic loading. However, as of February 1981, no cracking had been experienced in the primary system piping …
1
DESCRIPTION Historical Background Prior to 1981, the number of bolting-related incidents reported by licensees was on the increase. A large number of these were related to primary pressure boundary applications and major component support structures. As a …
1
DESCRIPTION Historical Background On April 7, 1980, Arkansas Nuclear One (ANO) Units 1 and 2 experienced a significant event resulting from a loss of offsite power. Although both units were safely shut down, the analysis and evaluation of the event …
1
DESCRIPTION Historical Background This issue was identified at an NRC Operating Reactor Events meeting on January 7, 1982, [1] and addressed fire protection system (FPS) actuations that resulted in adverse interactions with safety-related equipment at …
1
DESCRIPTION Historical Background In an evaluation of INPO/NSAC Significant Operating Experience Report 81-17, [1] the operators at Fort Calhoun determined that the configuration of their plant made it susceptible to the possibility that all AFW supply …
1
DESCRIPTION Historical Background Cracks were found in the normal make-up high pressure injection (MU/HPI) nozzles of several B&W plants following an inspection of the 8 B&W plants licensed to operate. These cracks appeared to be directly related to loose …
1
DESCRIPTION Historical Background PORVs and block valves were originally designed as non-safety components in the reactor pressure control system for use only when plants are in operation. The block valves were installed because of expected leakage from …
1
DESCRIPTION Historical Background On two occasions (February 22 and 25, 1983), Salem Unit 1 failed to scram automatically due to failure of both reactor trip breakers to open on receipt of an actuation signal. In both cases, the unit was successfully …
1
DESCRIPTION Historical Background This issue was recommended [1] for prioritization by DSI after a review of the AEOD engineering evaluation report (AEOD/E325) [2] on vapor binding of the AFW pumps at H.B.Robinson Unit 2. Further AEOD study of the event …
1
DESCRIPTION Historical Background This issue was raised [1] in March 1985 to address the staff's concern that there were no requirements for dynamic qualification testing or dynamic surveillance testing of large bore hydraulic snubbers (> 50 kips load …
1
DESCRIPTION In December 1984, the staff recommended in SECY-83-357B [1] that rulemaking with regard to H 2 control for LWRs with large, dry containments could be safely deferred due to the greater inherent capability of these containments to accommodate …
1
DESCRIPTION The loss of all feedwater event at Davis-Besse on June 9, 1985, resulted in the formation of an NRC project team to investigate the event. The team's findings were published in NUREG-1154 [1] and were subsequently reviewed by DL/NRR. As a …
1
DESCRIPTION In 1985, operating experience as well as staff and industry studies indicated that AFW systems continued to fail at a high rate. These studies also indicated that plants with similar AFW system reliabilities (as calculated in accordance with …
1
DESCRIPTION Historical Background This issue was identified in the U.S. Nuclear Regulatory Commission (NRC) incident investigation team (IIT) report on the loss of integrated control system (ICS) power event at Rancho Seco Nuclear Generating Station …
1
DESCRIPTION Historical Background This issue was identified by NRR/EIB in February 1986 when it was suggested that Issue 106, "Piping and the Use of Highly Combustible Gases in Vital Areas," be expanded to include new safety concerns associated with the …
1
DESCRIPTION Historical Background This issue was identified as an alternative approach to the Finding 15 recommendation [1] discussed in Issue 125.I.5, "Safety Systems Tested in All Conditions Required by DBA," which states that "[t]horough integrated …
1
DESCRIPTION Historical Background This issue was raised in SECY-89-170 [1] and addressed the potential for control system vulnerabilities as a result of fire-induced alternate shutdown/control room panel interactions. Concern for these interactions arose …
1
DESCRIPTION Historical Background This issue was raised in SECY-89-170 [1] and addressed the effectiveness of manual fire-fighting in the presence of smoke. This concern arose as a result of an NRC-sponsored Fire Risk Scoping Study [2] which focused on …
1
Page Last Reviewed/Updated 3/1/2026
Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.