NUREG 0933
Applied Filters
Displaying 26 - 50 of 86
DESCRIPTION This issue involves a potential deficiency in the ability to control leakage past the main steam isolation valves (MSIV) in BWR plants. Requirements for MSIV leakage control systems outlined in Regulatory Guide 1.96 [1] were developed as a …
1
DESCRIPTION Historical Background In the event of a LOCA in which offsite power remains available, the reactor operator may choose to shut down the emergency diesel generators shortly after the LOCA. If, after the diesels are shut down, offsite power is …
1
DESCRIPTION Historical Background This issue effects all PWR-type reactors (Westinghouse, CE, B&W). The issue as described, [1] , [2] , [3] concerns postulated accidents resulting from a steam line break which consequentially results in a steam generator …
1
DESCRIPTION Background This issue addressed the high rate of reactor coolant pump (RCP) seal failures that challenge the makeup capacity of the ECCS in PWRs. At the time this issue was identified [1] in 1980, RCP seal failures in BWRs occurred at a …
1
DESCRIPTION In a San Onofre Unit 1 Preliminary Notification issued in September 1980, it was reported that, during testing, the licensee had identified a problem with the design of the diesel generator sequencing circuitry. This problem occurred when a …
1
DESCRIPTION This issue was identified during plant design and emergency procedure reviews which raised questions as to whether certain safety actions have to be accomplished automatically or whether manual operator action is acceptable. CONCLUSION This …
1
DESCRIPTION Historical Background This issue corresponds to AEOD recommendation 4 highlighted in an AEOD memorandum [1] to NRR in December 1980. The AEOD recommendation resulted from a natural circulation cooldown event from full power at St. Lucie Unit …
1
DESCRIPTION In AEOD/CO05, [1] AEOD identified potential safety problems concerning steam generator overfill due to control system failures and combined primary and secondary blowdown. As a result of discussions with the Commissioners and the EDO, NRR …
1
DESCRIPTION Historical Background This issue was identified [1] when AEOD expressed concerns about the use inside containment of a particular polymer coating that could flake off and fail when subjected to DBA conditions. In addition to the concern for …
1
DESCRIPTION AEOD issued a memorandum [1] in which a potential safety issue involving combined primary and secondary system LOCAs was raised. The issue was discussed at Commission meetings on October 16, 1980 and on November 10, 1980. NRR informed AEOD of …
1
DESCRIPTION Historical Background This issue was initiated in response to an immediate action memorandum [1] issued by AEOD in September 1981 regarding desiccant contamination of instrument air lines. NRR responded to the AEOD memorandum by establishing a …
1
DESCRIPTION Historical Background This proposed generic issue has its origin in a January 1981 event at Millstone Unit 2. [1] An operator inadvertently opened a 125V DC main feeder breaker, causing the loss of one of the two redundant emergency systems …
1
DESCRIPTION Historical Background On April 7, 1980, Arkansas Nuclear One (ANO) Units 1 and 2 experienced a significant event resulting from a loss of offsite power. Although both units were safely shut down, the analysis and evaluation of the event …
1
DESCRIPTION Historical Background In January 1982, AEOD published a report (AEOD/C201 [1] ) on safety concerns associated with reactor vessel level instrumentation in BWRs. The report was forwared to NRR for further action. Safety Significance BWRs use …
1
DESCRIPTION Historical Background In December 1981, AEOD completed a survey of valve operator-related events that occurred during 1978, 1979, and 1980 and submitted a draft report [1] to NRR for comment. In this study, AEOD established that motor- …
1
DESCRIPTION On April 8, 1981, while operating at 100% power, the Arkansas Nuclear One, Unit 1 experienced a moderate feedwater-overfill transient in one of its once-through steam generators. AEOD performed a case study of this event, concluded that the …
1
DESCRIPTION Historical Background This issue was identified at an NRC Operating Reactor Events meeting on January 7, 1982, [1] and addressed fire protection system (FPS) actuations that resulted in adverse interactions with safety-related equipment at …
1
DESCRIPTION Historical Background Increasing attention has recently been focused on the integrity of RCP seals due to loss of cooling to the seals both in connection with PRA studies which are currently under review and from operating experience. [1] , …
1
DESCRIPTION Historical Background PORVs and block valves were originally designed as non-safety components in the reactor pressure control system for use only when plants are in operation. The block valves were installed because of expected leakage from …
1
DESCRIPTION Historical Background On two occasions (February 22 and 25, 1983), Salem Unit 1 failed to scram automatically due to failure of both reactor trip breakers to open on receipt of an actuation signal. In both cases, the unit was successfully …
1
DESCRIPTION Historical Background This issue was identified [1] when a number of concerns regarding DC power systems were raised during the review of the proposed resolution of Issue A-30, "Adequacy of Safety-Related DC Power Supplies." The main concerns …
1
DESCRIPTION Historical Background In October 1982, the Executive Director for Operations appointed the Committee to Review Safety Requirements at Power Reactors (CRSRPR) to review U.S. Nuclear Regulatory Commission (NRC) security requirements at nuclear …
1
DESCRIPTION Historical Background In BWRs, SRVs are mounted on the main steam line inside the drywell. Each SRV discharge is piped through its own discharge line (tailpipe) to a point below the minimum water level in the primary containment suppression …
1
DESCRIPTION Historical Background The HPCI steam supply line has two containment isolation valves in series: one inside and one outside of the containment. Both are normally open in most plants; however, two plants were found to operate with the HPCI …
1
DESCRIPTION Historical Background This issue was recommended [1] for prioritization by DSI after a review of the AEOD engineering evaluation report (AEOD/E325) [2] on vapor binding of the AFW pumps at H.B.Robinson Unit 2. Further AEOD study of the event …
1
Page Last Reviewed/Updated 3/1/2026
Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.