NUREG 0933
Applied Filters
Displaying 1 - 24 of 24
DESCRIPTION Historical Background In the event of a LOCA in which offsite power remains available, the reactor operator may choose to shut down the emergency diesel generators shortly after the LOCA. If, after the diesels are shut down, offsite power is …
1
DESCRIPTION On November 10, 1979, an event occurred at the Oconee Power Station, Unit 3, that resulted in loss of power to a non-Class 1E 120-volt AC single-phase power panel that supplied power to the integrated control system (ICS) and the nonnuclear …
1
DESCRIPTION Historical Background This concern was raised [1] because of the potential for a high-altitude nuclear weapon detonation causing a large electromagnetic pulse (EMP) which subsequently could induce large currents and voltages in electrical …
1
DESCRIPTION In a San Onofre Unit 1 Preliminary Notification issued in September 1980, it was reported that, during testing, the licensee had identified a problem with the design of the diesel generator sequencing circuitry. This problem occurred when a …
1
DESCRIPTION Historical Background This issue was initiated in response to an immediate action memorandum [1] issued by AEOD in September 1981 regarding desiccant contamination of instrument air lines. NRR responded to the AEOD memorandum by establishing a …
1
DESCRIPTION Historical Background This proposed generic issue has its origin in a January 1981 event at Millstone Unit 2. [1] An operator inadvertently opened a 125V DC main feeder breaker, causing the loss of one of the two redundant emergency systems …
1
DESCRIPTION Historical Background On April 7, 1980, Arkansas Nuclear One (ANO) Units 1 and 2 experienced a significant event resulting from a loss of offsite power. Although both units were safely shut down, the analysis and evaluation of the event …
1
DESCRIPTION An AEOD memorandum [1] to NRR on July 15, 1980, identified the concern that some operating nuclear power plants do not have technical specifications or Administrative controls governing operational restrictions for Class 1E 120 VAC vital …
1
DESCRIPTION Historical Background In an AEOD memorandum [1] to NRR, it was concluded that the design of the Point Beach Nuclear Plant, Units 1 and 2, under certain conditions, allowed manual interconnection of redundant electrical load groups, thereby …
1
DESCRIPTION Historical Background In August 1982, AEOD reviewed a number of LERs related to Class 1E safety related switchgear circuit breakers and found a high incidence of their failure to close on demand. A preliminary report was written and …
1
DESCRIPTION Historical Background This issue was identified at an NRC Operating Reactor Events meeting on January 7, 1982, [1] and addressed fire protection system (FPS) actuations that resulted in adverse interactions with safety-related equipment at …
1
DESCRIPTION Historical Background On August 12, 1983, one of the three emergency diesel generators (EDG) at the Shoreham Plant failed during overload testing as a result of a fractured crankshaft. The failure occurred in EDG-102 and similar crankshaft …
1
DESCRIPTION Historical Background This issue was identified in a DL/NRR memorandum [1] which called for an assessment of the high failure frequency of main transformers and the resultant safety implications. Concern for this issue arose when the North …
1
DESCRIPTION Historical Background This issue was identified in a DST/NRR memorandum [1] which addressed a condition in which some protective devices intended to trip active engineered safety features (ESF) components, under indication of equipment …
1
DESCRIPTION Historical Background This issue was identified in a RRAB memorandum [1] in March 1985 and addressed the possibility of relay contact chatter during a seismic event and its resulting effect upon safety and safety-related electrical control …
1
DESCRIPTION Following the NRR reorganization in November 1985, EIB/DSRO was responsible for resolving three issues that were directly related to onsite electrical systems: Issue 48, "LCO for Class 1E Vital Instrument Buses in Operating Reactors"; Issue …
1
DESCRIPTION Historical Background This issue was identified as an alternative approach to the Finding 15 recommendation [1] discussed in Issue 125.I.5, "Safety Systems Tested in All Conditions Required by DBA," which states that "[t]horough integrated …
1
DESCRIPTION This issue was identified [1] by NRR to address the concerns raised during the licensing of Nine Mile Point Unit 2. On February 7, 1985, Niagara Mohawk submitted to the NRC a report on "Non-Class 1E Devices Connected to Class 1E Power …
1
DESCRIPTION Historical Background This issue was identified [1] by NRR as a result of a diagnostic evaluation team inspection of the SWS at Zion, a multiplant site. The inspection identified the potential for some additional shared systems to have an …
1
DESCRIPTION As discussed in SECY-93-049, [1] the staff reviewed significant license renewal issues and found that several related to environmental qualification (EQ). A key aspect of these issues was whether the licensing bases, particularly for older …
1
DESCRIPTION Historical Background This issue was identified [1] by NRR following the issuance of NRC Information Notice (IN) 93-17 [2] which was based in part on a deficiency in the Surry Power Station emergency diesel generator (DG) loading. This …
1
In resolving GSIs over the years, the staff generally found it necessary to make assumptions and establish limitations on the scope of the issues. As a result of its review of the resolution of some GSIs, the ACRS expressed concerns that the assumptions …
1
DESCRIPTION On August 24, 1992, Hurricane Andrew hit south Florida and caused extensive onsite and offsite damage at Turkey Point. Following this hurricane which was classified Category 4, an NRC/industry team was organized to: (1) review the damage …
1
DESCRIPTION Historical Background This issue was identified [1] by NRR following an allegation that was submitted to the NRC in March 2006 that described a scenario in which a SBLOCA event in a PWR has progressed to the sump recirculation mode of core …
1
Page Last Reviewed/Updated 3/1/2026
Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.