DESCRIPTION Historical Background Indications of possible stress corrosion cracking (SCC) in the Indian Point Unit 3 (IP-3) steam generator prompted MTEB to review foreign and domestic operating experiences related to possible indications of SCC in …
1
DESCRIPTION Historical Background In February 1983, the Westinghouse Owners Group submitted WCAP-10271, "Evaluation of Surveillance Frequencies and Out of Service Times for the Reactor Protection Instrumentation System," to the NRC for review and …
1
DESCRIPTION Historical Background This issue was raised [1] in March 1985 to address the staff's concern that there were no requirements for dynamic qualification testing or dynamic surveillance testing of large bore hydraulic snubbers (> 50 kips load …
1
DESCRIPTION Historical Background This issue was identified in a RRAB memorandum [1] in March 1985 and addressed the possibility of relay contact chatter during a seismic event and its resulting effect upon safety and safety-related electrical control …
1
DESCRIPTION Historical Background The ATWS rule [1] , [2] for W plants requires the implementation of a diverse ATWS mitigation system, Auxiliary [or ATWS] Mitigating Systems Actuation Circuitry (AMSAC). The functions prescribed for AMSAC are turbine trip …
1
DESCRIPTION Historical Background This issue was identified in a NRR/DST memorandum [1] and addressed the potential risk reduction that might result from training operators and having procedures developed to assist the operators in managing accidents …
1
DESCRIPTION Historical Background This issue was identified in 1985 when a concern was raised that, due to non-obvious interactions between diverse equipment, TS may permit a plant to be in a dangerous configuration by the simultaneous outage of equipment …
1
DESCRIPTION Historical Background On January 27, 1985, a dented and leaking tendon grease cap was found during inspections at Farley Unit 2 prior to the integrated leak rate test of the prestressed concrete containment structure. Subsequent detailed …
1
DESCRIPTION In an August 1983 memorandum, [1] the EDO requested a comprehensive review of NRC requirements in the area of nuclear power plant piping. In response to this request, the NRC Piping Review Committee (PRC) was formed to review and evaluate …
1
DESCRIPTION Historical Background This issue was raised [1] by the staff in 1985 during the review of several plant TS when it was found that the protection system designs of some older plants did not provide as complete a degree of on-line protection …
1
DESCRIPTION In December 1984, the staff recommended in SECY-83-357B [1] that rulemaking with regard to H 2 control for LWRs with large, dry containments could be safely deferred due to the greater inherent capability of these containments to accommodate …
1
DESCRIPTION The loss of all feedwater event at Davis-Besse on June 9, 1985, resulted in the formation of an NRC project team to investigate the event. The team's findings were published in NUREG-1154 [1] and were subsequently reviewed by DL/NRR. As a …
1
DESCRIPTION Following the Davis-Besse event in June 1985, potential inadequacies of nuclear power plant design criteria and safety analyses were raised in a DST/NRR memorandum. [1] These concerns were: (1) root causes of DBAs are not analyzed and may …
1
DESCRIPTION In 1985, operating experience as well as staff and industry studies indicated that AFW systems continued to fail at a high rate. These studies also indicated that plants with similar AFW system reliabilities (as calculated in accordance with …
1
On June 9, 1985, Davis-Besse had a partial loss of feedwater while operating at 90% power. Following a reactor trip, the loss of all feedwater occurred. The two OTSGs became dry and were ineffective as a heat sink. Consequently, the RCS pressure increased …
1
DESCRIPTION Background The reliability of PWR main steam safety valves (MSSVs) was identified as a generic issue in a DSRO memorandum on March 1986 [1] in which it was noted that individual PWR plant FSARs assume credit for MSSV functional capability to …
1
DESCRIPTION Historical Background This issue was identified in the U.S. Nuclear Regulatory Commission (NRC) incident investigation team (IIT) report on the loss of integrated control system (ICS) power event at Rancho Seco Nuclear Generating Station …
1
DESCRIPTION Following the NRR reorganization in November 1985, EIB/DSRO was responsible for resolving three issues that were directly related to onsite electrical systems: Issue 48, "LCO for Class 1E Vital Instrument Buses in Operating Reactors"; Issue …
1
DESCRIPTION Historical Background This issue was identified in a May 1986 DSI memorandum [1] in which 21 instances of BWR vessel draining through various paths in the RHR system piping were described. Later, in August 1986, AEOD/E609 [2] was issued …
1
DESCRIPTION Historical Background This issue was identified [1] when the staff found the Byron Unit 1 vulnerable to core-melt sequences in the absence of the availability of Byron Unit 2 which was not yet operational. Because of the licensing status of …
1
DESCRIPTION Historical Background Potential seismic interaction involving the movable in-core flux mapping systems was identified as a generic issue in August 1985. [1] This potential interaction exists because portions of the in-core flux mapping system, …
1
DESCRIPTION Historical Background This issue was identified [1] by NRR as a result of concern for the potential loss of the RHR system under a harsh containment environment. The RHR system is normally located outside the containment and is not required to …
1
DESCRIPTION Historical Background In IE Circular No. 80-02, [1] the concern of overtime work for licensee staff who perform safety-related functions was discussed and limits on maximum working hours were recommended. In July 1980, a letter [2] was issued …
1
DESCRIPTION Since the TMI-2 accident in March 1979, to which human error was a major contributor, the issue of academic requirements for reactor operators has been a major concern of the NRC. In October 1985, the NRC issued a Policy Statement on …
1
DESCRIPTION Steam generator overfill and its consequences have received staff and industry attention because of the frequency and severity of overfill events. Over the years, a number of issues have been raised concerning steam generator overfill …
1