NUREG 0933
Applied Filters
Displaying 51 - 75 of 205
DESCRIPTION Historical Background In January 1982, AEOD published a report (AEOD/C201 [1] ) on safety concerns associated with reactor vessel level instrumentation in BWRs. The report was forwared to NRR for further action. Safety Significance BWRs use …
1
DESCRIPTION Historical Background This issue was raised in a DL memorandum [1] to DST in March 1982 and addressed the subject of service water system (SWS) fouling at operating plants primarily by aquatic bivalves. Prior to and following this memorandum, …
1
DESCRIPTION This issue was raised in an AEOD memorandum [1] to NRR in May 1982 and addressed the problem of flow blockage by blue mussels (Mytilus Edilus) in the reactor building closed cooling water system at Pilgrim. CONCLUSION This issue has been …
1
DESCRIPTION Historical Background In response to a 1967 ACRS concern relative to the potential of melting and subsequent disintegration of a portion of a fuel assembly due to inlet orifice flow blockage, GE submitted NEDO-10174 [1] in May 1970. As a …
1
DESCRIPTION Historical Background In December 1981, AEOD completed a survey of valve operator-related events that occurred during 1978, 1979, and 1980 and submitted a draft report [1] to NRR for comment. In this study, AEOD established that motor- …
1
DESCRIPTION Historical Background In August 1982, AEOD reviewed a number of LERs related to Class 1E safety related switchgear circuit breakers and found a high incidence of their failure to close on demand. A preliminary report was written and …
1
DESCRIPTION On April 8, 1981, while operating at 100% power, the Arkansas Nuclear One, Unit 1 experienced a moderate feedwater-overfill transient in one of its once-through steam generators. AEOD performed a case study of this event, concluded that the …
1
DESCRIPTION Historical Background This issue was identified at an NRC Operating Reactor Events meeting on January 7, 1982, [1] and addressed fire protection system (FPS) actuations that resulted in adverse interactions with safety-related equipment at …
1
DESCRIPTION Historical Background The containment flooding issue stems from a flooding event that occurred at the Indian Point 2 reactor in October 1980. [1] A large quantity of water leaked from fan coolers onto the containment building floor and …
1
DESCRIPTION Historical Background As a result of the loss of high head injection capability at McGuire Unit 1 on February 12, 1982, this issue was raised by Region II because plant TS require (somewhat rapid) plant shutdown if certain safety equipment is …
1
DESCRIPTION The issue of lamellar tearing was originally addressed in NUREG-0410 [1] in connection with Technical Activity No. A-12, "Fracture Toughness of Steam Generator and Reactor Coolant Pump Supports." The significance of this issue as a potential …
1
DESCRIPTION Historical Background The SRVs of a BWR plant provide protection against overpressurization of the reactor primary system. During normal operation, the SRVs which are mounted in the main steam lines open on high pressure permitting steam to …
1
DESCRIPTION This issue was raised in November 1981 by the Materials Engineering Branch (MTEB), DE/NRR, and was based on the concern that NRC provides no control regulations or guides for bolting other than for the reactor vessel head. CONCLUSION In …
1
DESCRIPTION Historical Background BWRs are required to be operated within set thermal limits to maintain the integrity of the fuel cladding during postulated events. One of the established thermal limits is the minimum critical power ratio (MCPR). The …
1
DESCRIPTION Historical Background Protection systems in nuclear power plants are required to meet the design criteria of IEEE-279, "Criteria for Protection Systems for Nuclear Power Generating Stations." [1] One of the criteria of IEEE-279 requires that …
1
DESCRIPTION Historical Background Increasing attention has recently been focused on the integrity of RCP seals due to loss of cooling to the seals both in connection with PRA studies which are currently under review and from operating experience. [1] , …
1
DESCRIPTION Historical Background Following the steam generator tube rupture (SGTR) event at Ginna in January 1982, [1] the staff proceeded to develop generic steam generator requirements which would help mitigate or reduce steam generator tube …
1
DESCRIPTION Following the SGTR event at Ginna on January 25, 1982, increased staff effort was placed on developing means to mitigate and reduce steam generator tube degradations and ruptures. To meet these objectives, two steps were taken. The first step …
1
DESCRIPTION Historical Background In an evaluation of INPO/NSAC Significant Operating Experience Report 81-17, [1] the operators at Fort Calhoun determined that the configuration of their plant made it susceptible to the possibility that all AFW supply …
1
DESCRIPTION Historical Background Cracks were found in the normal make-up high pressure injection (MU/HPI) nozzles of several B&W plants following an inspection of the 8 B&W plants licensed to operate. These cracks appeared to be directly related to loose …
1
DESCRIPTION Historical Background PORVs and block valves were originally designed as non-safety components in the reactor pressure control system for use only when plants are in operation. The block valves were installed because of expected leakage from …
1
DESCRIPTION Historical Background This issue was raised [1] by DSI/NRR in August 1982 [2] following a search of LERs which suggested that additional licensing attention was needed for certain ancillary power plant equipment. The available information …
1
DESCRIPTION Background This issue was raised in Board Notification No. 82-81 [1] and addressed the failure of control rod drive (CRD) guide tube support pins in W reactors. The first pin failure at a U.S. plant occurred at North Anna 1 in 1982 where a …
1
DESCRIPTION Historical Background During the period 1978 to 1980, there were reports of fatigue failure of thermal sleeve assemblies in the piping systems of both PWRs and BWRs. The BWR problem was addressed by GE in NEDO-21821 and was resolved with a …
1
DESCRIPTION Historical Background This issue was raised [1] by DSI in June 1983 and addresses the concern that several operating PWRs and BWRs either lack iodine coolant activity LCOs or have inadequate LCOs such that accidents involving the release of …
1
Page Last Reviewed/Updated 3/1/2026
Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.