Skip to main content

NUREG 0933

Displaying 26 - 50 of 53

TASK II.J.1: VENDOR INSPECTION PROGRAM The objective of this task was to improve vendor-supplied components and services through a modified and more effective vendor inspection program. ITEM II.J.1.1: ESTABLISH A PRIORITY SYSTEM FOR CONDUCTING VENDOR …
The objective of this task was to provide greater assurance that nuclear plants are properly constructed by improving construction inspection programs. ITEM II.J.2.1: REORIENT CONSTRUCTION INSPECTION PROGRAM DESCRIPTION This TMI Action Plan [1] item …
The objective of this task was to improve the qualification of licensees for operating nuclear power plants by requiring greater oversight of design, construction, and modification activities. ITEM II.J.3.1: ORGANIZATION AND STAFFING TO OVERSEE DESIGN AND …
The objective of this task was to clarify deficiency report requirements to obtain uniform reporting and earlier identification and correction of problems. ITEM II.J.4.1: REVISE DEFICIENCY REPORTING REQUIREMENTS DESCRIPTION This TMI Action Plan [1] item …
The objectives of this task were to perform systems reliability analyses and to effect changes in emergency operating procedures and operator training to improve the capability of plants to mitigate the consequences of the small-break LOCAs and …
TASK III.A.1: IMPROVE LICENSEE EMERGENCY PREPAREDNESS - SHORT-TERM The objectives of this task were to improve and upgrade licensee emergency preparedness by requiring improvements in facilities, plans, procedures, offsite support, technical assistance, …
The objective of this task was to upgrade the emergency preparedness of nuclear power plants. Specific criteria to meet this objective were delineated in NUREG-0654. [1] ITEM III.A.2.1: AMEND 10 CFR 50 AND 10 CFR 50, APPENDIX E The four parts of this item …
The objective of this task is to enable NRC, in the event of a nuclear accident at a licensed reactor facility, to: (1) monitor and evaluate the situation and potential hazards, (2) advise the licensee's operating staff as needed, and (3) in an extreme …
The objective of this task is to upgrade the state of emergency preparedness of State and local governments affected by nuclear facilities. The Federal Emergency Management Agency was given the lead on this effort by the President on December 7, 1979. …
The objectives of this task are: (1) to have information available for the news media and the public describing how nuclear plants operate, radiation and its health effects, and protective actions against radiation; and (2) to provide training for members …
TASK III.D.1: RADIATION SOURCE CONTROL The objective of this task is to perform evaluations to establish additional design features that should be included in the rulemaking proceeding of Item II.B.8. The purpose of these evaluations is to identify design …
The objective of this task was to improve public radiation protection in the event of a nuclear power plant accident by improving (1) radioactive effluent monitoring, (2) the dose analysis for accidental releases of radioiodine, tritium, and carbon-14, …
The objective of this task is to improve nuclear power plant worker radiation protection to allow workers to take effective action to control the course and consequences of an accident, as well as to keep exposures as low as reasonably achievable (ALARA) …
The objective of this task is to substantially improve licensee awareness of and attitude toward safety by vigorous enforcement of NRC rules. The two major aspects of this objective are as follows: (1) assess substantial penalties for licensee failure to …
The objective of this task is to develop a more efficient and effective management method for issuing information and requirements to licensees to elimination the duplication of staff effort for NRC and licensees. Provide an NRC-wide system for tracking …
The objective of this task is to assure that the lessons learned from TMI are applied to other NRC programs. ITEM IV.C.1: EXTEND LESSONS LEARNED FROM TMI TO OTHER NRC PROGRAMS DESCRIPTION This TMI Action Plan Item [1] required that lessons learned from …
The objectives of this task are: (1) to improve and expand the NRC training program for the technical staff and resident inspectors, including, where appropriate, hands-on training; and (2) to establish a program to provide technically qualified …
The objective of this task is to develop plans for an integrated program of safety decision-making. These plans include: (1) an expanded program of regulatory research covering methodologies for making safety decisions and safety-cost tradeoffs, with …
The objective of this task is to enhance public safety through the reduction of disincentives to safety resulting from financial pressures on the utility at the construction, operation, and decommissioning stages. ITEM IV.F 1: INCREASED OIE SCRUTINY OF …
The objectives of this task are to improve NRC rulemaking procedures to provide a greater opportunity for public participation, to assure a periodic and systematic reevaluation of NRC rules, and to include appropriate provision for backfitting in all new …
The objective of this task is to respond to the President's request for NRC participation in the Radiation Policy Council. ITEM IV.H.1: NRC PARTICIPATION IN THE RADIATION POLICY COUNCIL DESCRIPTION The Radiation Policy Council, a policy coordinating body …
The objective of this task was the further delineation of substantive safety policy by the NRC. ITEM V.A.1: DEVELOP NRC POLICY STATEMENT ON SAFETY DESCRIPTION This NUREG-0660, [1] Rev. 1 item called for the Commission to develop more explicit articulation …
The objective of this task was the elimination of nonsafety responsibilities from NRC jurisdiction, if appropriate. ITEM V.B.1: STUDY AND RECOMMEND, AS APPROPRIATE, ELIMINATION OF NON-SAFETY RESPONSIBILITIES DESCRIPTION This NUREG-0660, [1] Rev. 1 item …
The objective of this task was to strengthen the role of advisory committees in Commission activities. ITEM V.C.1: STRENGTHEN THE ROLE OF ADVISORY COMMITTEE ON REACTOR SAFEGUARDS DESCRIPTION This NUREG-0660, [1] Rev. 1 item called for the Commission to …
The objective of this task was to enhance public participation in, and make needed reforms to, the nuclear licensing process. ITEM V.D.1: IMPROVE PUBLIC AND INTERVENOR PARTICIPATION IN THE HEARING PROCESS DESCRIPTION This NUREG-0660, [1] Rev. 1 item …