NUREG 0933
Applied Filters
Displaying 1 - 21 of 21
The objectives of this task were to: (1) increase the capability of shift crews to operate facilities in a safe and competent manner by assuring that training for plant changes and off-normal events was conducted; and (2) review the comprehensiveness of …
1
The objective of this task was to provide greater assurance that nuclear plants are properly constructed by improving construction inspection programs. ITEM II.J.2.1: REORIENT CONSTRUCTION INSPECTION PROGRAM DESCRIPTION This TMI Action Plan [1] item …
1
The objective of this task was to improve the qualification of licensees for operating nuclear power plants by requiring greater oversight of design, construction, and modification activities. ITEM II.J.3.1: ORGANIZATION AND STAFFING TO OVERSEE DESIGN AND …
1
The objective of this task was to clarify deficiency report requirements to obtain uniform reporting and earlier identification and correction of problems. ITEM II.J.4.1: REVISE DEFICIENCY REPORTING REQUIREMENTS DESCRIPTION This TMI Action Plan [1] item …
1
The objective of this task is to enhance public safety through the reduction of disincentives to safety resulting from financial pressures on the utility at the construction, operation, and decommissioning stages. ITEM IV.F 1: INCREASED OIE SCRUTINY OF …
1
DESCRIPTION This issue was documented in NUREG-0471 [1] and stemmed from an ACRS recommendation that the staff explore diverse means of obtaining ECCS capability for future plants. The ACRS also recommended the staff explore the issue in the context of …
1
DESCRIPTION Historical Background Prior to 1981, the number of bolting-related incidents reported by licensees was on the increase. A large number of these were related to primary pressure boundary applications and major component support structures. As a …
1
DESCRIPTION Historical Background This issue was identified [1] following a staff evaluation of allegations that improper consideration of "stiff" pipe clamps in Class 1 piping systems could result in unsafe plant operation. IE Information Notice No. …
1
DESCRIPTION Historical Background Low temperature overpressurization originally identified in NUREG 0371 [1] as item A-26. This issue later became USI A-26 and was resolved in September 1978 with a revision to SRP [2] Section 5.2. The resolution of USI …
1
DESCRIPTION Historical Background On April 17, 1984, a DSI memorandum [1] on the subject of RHR interlocks for W plants described staff concerns that the design basis for RHR interlocks had been misunderstood and that these concerns had not been …
1
DESCRIPTION Historical Background The issue of using the most recent NOAA procedures for determining probable maximum precipitation (PMP) was raised [1] after an OL applicant disputed the NRC use of NOAA Hydrometeorological Report (HMR) Nos. 51 [2] and …
1
DESCRIPTION Historical Background Issue B-63, which was resolved and implemented as MPA B-45, required leak-testing of the check valves that isolate those low pressure systems that are connected to the RCS outside the containment. However, except for …
1
DESCRIPTION Historical Background This issue was raised [1] in March 1985 to address the staff's concern that there were no requirements for dynamic qualification testing or dynamic surveillance testing of large bore hydraulic snubbers (> 50 kips load …
1
DESCRIPTION Historical Background On January 27, 1985, a dented and leaking tendon grease cap was found during inspections at Farley Unit 2 prior to the integrated leak rate test of the prestressed concrete containment structure. Subsequent detailed …
1
DESCRIPTION Background The reliability of PWR main steam safety valves (MSSVs) was identified as a generic issue in a DSRO memorandum on March 1986 [1] in which it was noted that individual PWR plant FSARs assume credit for MSSV functional capability to …
1
DESCRIPTION The issue, as originally proposed, [1] addressed the concern for fission product removal by the containment sprays and suppression pools in PWRs and BWRs, respectively; however, it was expanded to include PWR plants that use ice condenser …
1
DESCRIPTION Historical Background This issue was identified [1] by NRR when concerns were expressed that the seismic loading on equipment and pipe-mounted components may have been underestimated. These concerns could be divided into two sub- issues: …
1
DESCRIPTION Historical Background This issue was raised in SECY-89-170 [1] and addressed the effectiveness of manual fire-fighting in the presence of smoke. This concern arose as a result of an NRC-sponsored Fire Risk Scoping Study [2] which focused on …
1
DESCRIPTION The TMI-2 Safety Advisory Board was established to provide the licensee, General Public Utilities Nuclear Corporation, with a qualified, independent appraisal of the cleanup of TMI-2, with particular emphasis on the assurance of public and …
1
Note: Due to the sensitive nature of some information in this analysis, redactions are necessary in this public version. The Nuclear Regulatory Commission (NRC) has coordinated with other Federal agencies (Department of Homeland Security, Federal Energy …
1
Note: Due to the sensitive nature of some information in this analysis, redactions are necessary in this public version. The Nuclear Regulatory Commission (NRC) has coordinated with other Federal agencies (Department of Homeland Security, Federal Energy …
1
Page Last Reviewed/Updated 3/1/2026
Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.