NUREG 0933

Displaying 1 - 6 of 6

DESCRIPTION Historical Background A memorandum [1] from AEOD to NRR dated May 23, 1980 drew attention to the generic issue of BWR jet pump integrity. The concern that motivated the AEOD memo was a February 1980 jet pump failure at Dresden Unit 3, together …
DESCRIPTION Historical Background In January 1982, AEOD published a report (AEOD/C201 [1] ) on safety concerns associated with reactor vessel level instrumentation in BWRs. The report was forwared to NRR for further action. Safety Significance BWRs use …
DESCRIPTION Historical Background On March 18, 1983, B&W expressed [1] concern for unanalyzed reactor vessel thermal stress that could occur during natural convection cooldown of PWRs. The concern emerged from a preliminary B&W evaluation of a voiding …
DESCRIPTION Historical Background This concern was raised by an NRC resident inspector who questioned the practice of leaving the refueling canal drain valve in the closed position during operations at H. B. Robinson Unit 2. [1] A subsequent investigation …
DESCRIPTION Historical Background Issue B-63, which was resolved and implemented as MPA B-45, required leak-testing of the check valves that isolate those low pressure systems that are connected to the RCS outside the containment. However, except for …
DESCRIPTION Historical Background Combustible gases such as H 2 , propane, and acetylene are used during normal operations of nuclear power plants in limited quantities and for relatively short periods of time. H 2 , the most prevalent of these gases in …