DESCRIPTION Historical Background Prior to 1981, the number of bolting-related incidents reported by licensees was on the increase. A large number of these were related to primary pressure boundary applications and major component support structures. As a …
1
DESCRIPTION Historical Background On two occasions (February 22 and 25, 1983), Salem Unit 1 failed to scram automatically due to failure of both reactor trip breakers to open on receipt of an actuation signal. In both cases, the unit was successfully …
1
DESCRIPTION Historical Background The HPCI steam supply line has two containment isolation valves in series: one inside and one outside of the containment. Both are normally open in most plants; however, two plants were found to operate with the HPCI …