Displaying 1 - 4 of 4

DESCRIPTION Historical Background Prior to 1981, the number of bolting-related incidents reported by licensees was on the increase. A large number of these were related to primary pressure boundary applications and major component support structures. As a …
DESCRIPTION Historical Background During the period 1978 to 1980, there were reports of fatigue failure of thermal sleeve assemblies in the piping systems of both PWRs and BWRs. The BWR problem was addressed by GE in NEDO-21821 and was resolved with a …
DESCRIPTION Historical Background In March 1982, leaks were detected in the heat-affected zones of the safe-end-to-pipe welds in two of the 28 in. diameter recirculation loop safe ends at Nine Mile Point Unit 1. Subsequent UT revealed extensive cracking …
DESCRIPTION Historical Background Low temperature overpressurization originally identified in NUREG 0371 [1] as item A-26. This issue later became USI A-26 and was resolved in September 1978 with a revision to SRP [2] Section 5.2. The resolution of USI …

Page Last Reviewed/Updated 3/1/2026

Disclaimer: Some of the formatting in NUREG-0933 may not be correct. We are currently working on fixing the formatting.