DESCRIPTION
Concerns for inoperability of instrumentation due to extreme cold weather were raised[1]by AEOD after an event at Arkansas Nuclear One, Unit 2 (ANO-2) in which all four RWST instrumentation channels were lost when the level transmitters froze. The system heat-tracing circuit was de-energized because the main line fuse was removed. This situation would have prevented the automatic change-over of the ECC from injection to recirculation mode under LOCA conditions, i.e., loss of safety function. Prior to the ANO-2 event, IE Bulletin No. 79-24[2]was issued after LERs revealed many events involving frozen instrument, sampling, and processing lines. All licensees and CP holders were requested to review their plants to determine that adequate protective measures had been taken to assure that safety-related process, instrument, and sampling lines do not freeze during extremely cold weather. AEOD requested that OIE issue a supplement to Bulletin 79-24[3]and that NRR address the adequacy of protective measures for freezing of safety-related instrument lines in the review of OLs.
In an August 14, 1981 memorandum to AEOD,[4]NRR advised that a BTP on freeze protection of safety- related instrument lines was being developed and would be included in the appropriate SRP[5]Section following its review and approval. NRR further advised that OIE proposed to amend the Inspection and Enforcement Manual[6]to include a module which would set forth procedures for inspection of systems and measures for protection against cold weather. This inspection module would require that regional inspectors perform plant site visits prior to the beginning of the cold season to verify the condition of heat-tracing systems and measures taken to protect plant equipment from cold weather conditions.
An amendment to the Inspection and Enforcement Manual (Procedure No. 71714)[7]was issued by OIE on January 1, 1982, thus completing the OIE portion of the resolution of this issue. Acceptance criteria for the design of protective measures against freezing in instrument lines of safety-related systems were included in Draft[8]Regulatory Guide 1.151, "Instrument Sensing Lines," and further work on a BTP was terminated. The Draft Regulatory Guide was issued for comment in March, 1982. Comments were collected and dispositioned and the Regulatory Guide[9]was published in July, 1983. Notice of the issuance of Regulatory Guide 1.151[10]
was published in the Federal Register[11]on August 8, 1983. Implementation of the Guide was limited to all CPs issued after September 1, 1983. However, other licensees or applicants could adopt the use of the Guide on a voluntary basis. As stated in the value/impact statement for the Guide, no backfitting of requirements for freeze protection and alarms was to be accomplished other than those changes effected by IE Bulletin 79-24[12](and the inspection requirements added to the OIE Inspection Manual).
CONCLUSION
In February 1984, the following SRP[13]Sections were revised[14],[15]to incorporate the changes associated with the resolution of this issue: (1) Section 7.1, Rev. 3; (2) Section 7.1, Appendix A, Rev. 1; (3) Section 7.5, Rev. 3; and (4) Section 7.7, Rev. 3. Thus, this issue was RESOLVED and requirements were issued.
[1] Memorandum for H. Denton and V. Stello from C. Michelson, "Inoperability of Instrumentation Due to Extreme Cold Weather," June 15, 1981. [8107010161]
[2] IE Bulletin 79-24, "Frozen Lines," U.S. Nuclear Regulatory Commission, September 27, 1979. [ML031220178]
[3] IE Bulletin 79-24, "Frozen Lines," U.S. Nuclear Regulatory Commission, September 27, 1979. [ML031220178]
[4] Memorandum for C. Michelson from H. Denton, "AEOD Memorandum on the Inoperability of Instrumentation Due to Extreme Cold Weather," August 14, 1981. [8109110138]
[5]NUREG-0800, "Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants," U.S. Nuclear Regulatory Commission, (1st Ed.) November 1975, (2nd Ed.) March 1980, (3rd Ed.) July 1981.
[6] NUREG/CR-5669, "Evaluation of Exposure Limits to Toxic Gases for Nuclear Reactor Control Room Operators," U.S. Nuclear Regulatory Commission, July 1991.
[7] NUREG/CR-5669, "Evaluation of Exposure Limits to Toxic Gases for Nuclear Reactor Control Room Operators," U.S. Nuclear Regulatory Commission, July 1991.
[8] Draft Regulatory Guide and Value/Impact Statement, Task IC 126-5, "Instrument Sensing Lines," U.S. Nuclear Regulatory Commission, March 1982. [8204190028]
[9] Regulatory Guide 1.151, "Instrument Sensing Lines," U.S. Nuclear Regulatory Commission, July 1983. [8808230051]
[10] Regulatory Guide 1.151, "Instrument Sensing Lines," U.S. Nuclear Regulatory Commission, July 1983. [8808230051]
[11] Federal Register Notice 48 FR 36029, "Regulatory Guide; Issuance, Availability," August 8, 1983.
[12] IE Bulletin 79-24, "Frozen Lines," U.S. Nuclear Regulatory Commission, September 27, 1979. [ML031220178]
[13]NUREG-0800, "Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants," U.S. Nuclear Regulatory Commission, (1st Ed.) November 1975, (2nd Ed.) March 1980, (3rd Ed.) July 1981.
[14] Memorandum for V. Stello from H. Denton, "Issuance of Revised Section 7.1, Appendix A to this Section, Section 7.5 and Section 7.7 of the Standard Review Plan, NUREG-0800," March 9, 1984. [8404160228]
[15] Memorandum for H. Denton from V. Stello, "SRP Changes Concerning Resolution of Generic Issue 45, Inoperability of Instrumentation due to Extreme Cold Weather," April 3, 1984. [8404180510]