United States Nuclear Regulatory Commission - Protecting People and the Environment
Home > NRC Library > Document Collections > NUREG-Series Publications > Staff Reports > NUREG 0933 > Section 3. New Generic Issues- Issue 40: Safety Concerns Associated with Pipe Breaks in the BWR Scram System (Rev. 1)

Resolution of Generic Safety Issues: Issue 40: Safety Concerns Associated with Pipe Breaks in the BWR Scram System (Rev. 1) ( NUREG-0933, Main Report with Supplements 1–35 )

DESCRIPTION

Historical Background

On April 3, 1981, AEOD published draft NUREG-0785, "Safety Concerns Associated with Pipe Breaks in the BWR Scram System."324 As a result of the development of these safety concerns and the findings presented in the report, the NRC staff met with representatives of the BWR Regulatory Response Group and GE on April 9, 1981. A letter325 was issued on April 10, 1981 to all BWR licensees requiring a generic evaluation of the safety concerns within 45 days of receipt and a plant-specific evaluation within 120 days of receipt.

A meeting was held with GE on April 28, 1981 to discuss the status of its generic evaluation. Subsequently, NEDO-24342326 was submitted to the NRC by letter dated April 30, 1981.327

A multidisciplinary group from NRR was assembled to review the generic evaluation. A three-phase approach was developed to identify generic review objectives and describe review termination points. It was agreed that this approach would be based on establishing either: (1) a low probability for the event, (2) acceptable consequences for the event, or (3) alternate cooling systems and mitigation equipment for the event.

As the review progressed, it became evident that a sufficient data base did not exist to conservatively terminate the generic review on the basis of a quantitative risk assessment. It was equally difficult to show acceptable consequences for all scram initiators, considering the potential for an unisolable leak from the reactor coolant system into the reactor building. Thus, it was necessary to generically evaluate the mitigation capability for this scenario.

As the evaluation proceeeded, several suggestions for improving and verifying piping integrity, mitigation capability, and environmental qualifications of essential equipment were made. These suggestions are discussed in NUREG-0803328 which begins with a review of the licensing design basis for the SDV piping system. An evaluation of the SDV piping system integrity and an assessment of the mitigation capability follow. Finally, each suggestion for improvement is evaluated in NUREG-0803328 and the final guidance for resolution of this problem is presented. NUREG-0803328 was transmitted to the BWR licensees, CP applicants, CP holders, and OL applicants by letters.329,332 These letters also requested appropriate responses to the safety concerns and guidelines presented in NUREG-0803.328 In these letters, it has been noted that an acceptable plantspecific response for this issue will conform to the final approved guidance provided in NUREG-0803.328

However, an additional submittal402 was forwarded to the NRC staff by GE and the BWR Owners' Group in August, 1982 in which an analysis was presented to demonstrate the probability of a pipe break in the scram discharge volume system was negligibly small and that, therefore, this issue should not be regarded as a significant safety issue. On the basis of its review of the August 1982 submittal, the NRC staff concluded that the results of the submittal were unacceptable. However, before the submittal was formally rejected by the staff, GE and the BWR Owners' Group provided additional material which amplified the August 1982 submittal with supporting information403 which was presented at a meeting with the staff on February 8, 1983.

A study337 was completed which describes the predicted response of Unit 1 at the Browns Ferry Nuclear Plant to a postulated small-break LOCA outside of the primary containment. This study is contained in the first volume of a two-volume study in which a detailed analysis of the accident sequence is presented. An estimate of the magnitude and timing of the concomitant release of the noble gas, cesium, and iodine-based fission products to the environment will be provided in Volume 2 of the study.

Safety Significance

If a break or leak exists or develops in the SDV piping during a reactor scram, this would result in the release of water and steam at 212F into the reactor building at a maximum flow rate of 550 gpm and is postulated to result in 100% relative humidity in the reactor building. The principal means of isolating this break would be to close the scram exhaust valves which are located on the hydraulic control units; however, this is dependent upon the ability to reset scram, which cannot be absolutely ensured immediately following the scram. Therefore, a rupture of the SDV could result in an unisolable break outside of primary containment, which is postulated to threaten emergency core cooling equipment by flooding areas in which this equipment is located and by causing ambient temperature and relative humidity conditions for which this equipment is not qualified.

Solution

NUREG-0803328 provides guidance to ensure pipe integrity, detection capability, mitigation capability and qualification of the emergency equipment to the expected environment.

CONCLUSION

This issue was RESOLVED, requirements were established, and MPA B-65 was established by DL for implementation purposes.602

REFERENCES

0322.AEOD/C201, "Report on The Safety Concern Associated with Reactor Vessel Level Instrumentation in Boiling Water Reactors," Office for Analysis and Evaluation of Operational Data, U.S. Nuclear Regulatory Commission, January 1982. [8202180432]
0324.NUREG-0785, "Safety Concerns Associated with Pipe Breaks in the BWR Scram System," U.S. Nuclear Regulatory Commission, April 1981.
0325. Letter to All BWR Licensees from U.S. Nuclear Regulatory Commission, "Safety Concerns Associated with Pipe Breaks in the BWR Scram System (Generic Letter 81-20)," April 10, 1981. [ML031210330]
0326.NEDO-24342, "GE Evaluation in Response to NRC Request Regarding BWR Scram System Pipe Breaks," General Electric Company, April 1981. [8105070251]
0327.Letter to D. Eisenhut (U.S Nuclear Regulatory Commission) from G. Sherwood (GE), "NRC Report, `Safety Concerns Associated with Pipe Breaks in the BWR Scram System,'" April 30, 1981. [8105070249]
0328.NUREG-0803, "Generic Safety Evaluation Report Regarding Integrity of BWR Scram System Piping," U.S. Nuclear Regulatory Commission, August 1981.
0329. Letter to All GE BWR Licensees (Except Humboldt Bay) from U.S. Nuclear Regulatory Commission, "Safety Concerns Associated with Pipe Breaks in the BWR Scram System (Generic Letter 81-34)," August 31, 1981. [ML031110042]
0337.NUREG/CR-2672, "SBLOCA Outside Containment at Browns Ferry Unit One—Accident Sequence Analysis," U.S. Nuclear Regulatory Commission, November 1982.
0402.Letter to D. Eisenhut (U.S. Nuclear Regulatory Commission) from T. Dente (BWR Owners' Group), "Analysis of Scram Discharge Volume System Piping Integrity, NEDO-22209 (Prepublication Form)," August 23, 1982. [8208310340]
0403.Letter to K. Eccleston (U.S. Nuclear Regulatory Commission) from T. Dente (BWR Owners' Group), "Transmittal of Supporting Information on Application of Scram Time Fraction to Scram Discharge Volume (SDV) Pipe Break Probability as Used in NEDO-22209," January 28, 1983. [8302010525]
0602.Memorandum for T. Speis from R. Mattson, "Status of Generic Issues 40 and 65 Assigned to DSI," December 27, 1983. [8401170445]