Safety Evaluation Report Related to the License Renewal of Davis-Besse Nuclear Power Station Docket Number 50-346 FirstEnergy Nuclear Operating Company (NUREG-2193, Supplement 1)

On this page:

Download complete document

Publication Information

Manuscript Completed: August 2015
Date Published: April 2016

Office of Nuclear Reactor Regulation
U.S. Nuclear Regulatory Commission
Washington, DC 20555-0001

Availability Notice

Abstract

This document is a supplemental safety evaluation report (SSER) for the license renewal application (LRA) for Davis-Besse Nuclear Power Station (Davis-Besse) as submitted by FirstEnergy Nuclear Operating Company (FENOC or the applicant). By letter dated August 27, 2010, FENOC submitted its LRA to the U.S. Nuclear Regulatory Commission (NRC) for renewal of the Davis-Besse operating licenses for an additional 20 years. The NRC staff (the staff) issued a safety evaluation report (SER) related to the license renewal of Davis-Besse Nuclear Power Station, dated September 3, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13248A267), which summarizes the results of its review of the LRA for compliance with the requirements of Title 10, Part 54, of the Code of Federal Regulations (10 CFR Part 54), "Requirements for Renewal of Operating Licenses for Nuclear Power Plants."

This SSER documents the staff’s review of supplemental information provided by the applicant since the issuance of the SER. This information includes annual updates required by 10 CFR 54.21(b) and updated information and commitments in response to the recent industry operating experience. This SSER supplements portions of SER Sections 1, 2, 3, 4, and Appendices.

Page Last Reviewed/Updated Wednesday, March 24, 2021