Interim Staff Guidance Associated with Combined License (COL), Design Certification (DC), and Early Site Permit (ESP) Applications for New Reactors
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Please Contact Us if you have questions or comments regarding the ISG.
Issued ISGs | ||
---|---|---|
Interim Staff Guidance (ISG) Number | Title | Status/Comment |
DC/COL-ISG-01 | Interim Staff Guidance on Seismic Issues Associated with High Frequency Ground Motion in Design Certification and Combined License Applications |
OPEN No decision has been made on how to incorporate this into permanent guidance. |
DC/COL-ISG-02 | Interim Staff Guidance on Financial Qualifications of Applicants For Combined License Applications |
OPEN No decision has been made on how to incorporate this into permanent guidance. |
DC/COL-ISG-03 | Interim Staff Guidance Probabilistic Risk Assessment Information to Support Design Certification and Combined License Applications |
CLOSED Draft Interim Staff Guidance on Probabilistic Risk Assessment (ML080370218) was provided for public comments on February 12, 2008. |
COL/ESP-ISG-04 | Interim Staff Guidance on Definition of Construction and on Limited Work Authorizations |
CLOSED Interim Staff Guidance was issued on February 17, 2009 (74 FR 7488). |
DC/COL-ISG-05 | Interim Staff Guidance on the use of the GALE86 Code for Calculation of Routine Radioactive Releases in Gaseous and Liquid Effluents to Support Design Certification and Combined License Applications |
OPEN The staff plans to update NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition”: Chapter 11. |
DC/COL-ISG-06 | Final Interim Staff Guidance Evaluation and Acceptance Criteria for 10 CFR 20.1406 to Support Design Certification and Combined License Applications |
CLOSED Interim Staff Guidance was issued on October 9, 2009 (74 FR 52267). |
DC/COL-ISG-07 | Interim Staff Guidance on Assessment of Normal and Extreme Winter Precipitation Loads on the Roofs of Seismic Category I Structures |
OPEN The staff plans to update NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition”: Section 2.3.1. |
DC/COL-ISG-08 | Final Interim Staff Guidance Necessary Content of Plant-Specific Technical Specifications When a Combined License Is Issued |
CLOSED Draft Interim Staff Guidance DC/COL-ISG-08 was publish for comment on October 16, 2008 (73 FR 61443). |
DC/COL-ISG-010 | Interim Staff Guidance Review of Evaluation to Address Adverse Flow Effects in Equipment Other than Reactor Internals |
OPEN The staff plans to update Regulatory Guide 1.20, “Comprehensive Vibration Assessment Program for Reactor Internals During Pre-Operational and Initial Startup Testing” and NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition”: Section 3.9.2, “Dynamic Testing and Analysis of Systems, Structures, and Components,” and Section 3.9.5, “Reactor Pressure Vessel Internals.” |
DC/COL-ISG-011 | Interim Staff Guidance Finalizing Licensing-basis Information |
CLOSED Draft Interim Staff Guidance DC/COL-ISG-011 was publish for comment on June 6, 2009 (74 FR 26894). |
DC/COL-ISG-013 | Assessing the Radiological Consequences of Accidental Releases of Radioactive Materials from Liquid Waste Tanks for Combined License Applications |
OPEN The NRC staff intends to incorporate these final ISGs into the next revision of RG 1.206 and NUREG-0800. |
DC/COL-ISG-014 | Assessing the Radiological Consequences of Accidental Releases of Radioactive Materials from Liquid Waste Tanks in Ground and Surface Waters for Combined License Applications |
OPEN The NRC staff intends to incorporate these final ISGs into the next revision of RG 1.206 and NUREG-0800. |
ESP/DC/COL-ISG-015 | Interim Staff Guidance on Post-Combined License Commitments |
CLOSED Draft Interim Staff Guidance ESP/DC/COL-ISG-015 was publish for comment on October 27, 2009 (74 FR 55274). |
DC/COL-ISG-016 | Compliance with 10 CFR 50.54(hh)(2) and 10 CFR 52.80(d) |
CLOSED Interim Staff Guidance was issued on June 9, 2010 (non-public) |
DC/COL-ISG-017 | Interim Staff Guidance on Ensuring Hazard-Consistent Seismic Input for Site Response and Soil Structure Interaction Analyses |
OPEN The staff plans to update Regulatory Guide 1.206, “Combined License Applications for Nuclear Power Plants (LWR Edition)” and NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition”: Section 2.5 and Section 3.7 |
DC/COL-ISG-018 | Interim Staff Guidance on Standard Review Plan, Section 17.4, “Reliability Assurance Program” |
CLOSED Draft Interim Staff Guidance DC/COL-ISG-018 was publish for comment on October 30, 2009 (74 FR 56243). |
DC/COL-ISG-019 | Final Interim Staff Guidance Review of Evaluation to Address Gas Accumulation Issues in Safety Related Systems and Systems Important to Safety |
OPEN The staff plans to update NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition”: Section 5.4.7, “Residual Heat Removal System,” Section 6.3, “Emergency Core Cooling System,” and Section 6.5.2, “Containment Spray System” |
DC/COL-ISG-020 | Interim Staff Guidance on Implementation of a Probabilistic Risk Assessment-Based Seismic Margin Analysis for New Reactors |
OPEN The NRC staff plans to update Regulatory Guide 1.206, “Combined License Applications for Nuclear Power Plants (LWR Edition)” and NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition”: Section 19.0 . Note: This ISG contains guidance for COL holders which has not been superseded by SRP 19.0, Revision 3. |
DC/COL-ISG-021 | Final Interim Staff Guidance Review of Nuclear Power Plant Designs using a Gas Turbine Driven Standby Emergency Alternating Current Power System |
OPEN The staff plans to update Regulatory Guide 1.206, “Combined License Applications for Nuclear Power Plants (LWR Edition)”and NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition”: Section 8.3.1 and Sections 9.5.4 through 9.5.8. |
DC/COL-ISG-022 | Interim Staff Guidance on Impact of Construction (under a Combined License) of New Nuclear Power Plant Units on Operating Units at Multi-Unit Sites |
OPEN The staff plan to update Regulatory Guide 1.206, “Combined License Applications for Nuclear Power Plants (LWR Edition)”and NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition”: Chapter 1.0. |
DC/COL-ISG-024 | Implementation of Regulatory Guide 1.221 on Design-Basis Hurricane and Hurricane Missiles |
OPEN Regulatory Guide 1.206 no longer includes details on what to include in application. Will include recommended updates into SRP 2.3.1 with pointers to SRP chapter 3 as recommended on Page 9 of 11 in ISG. |
DC/COL-ISG-025 | Interim Staff Guidance on Changes During Construction Under 10 CFR Part 52 |
OPEN The staff plans to create a new regulatory guide or update of Regulatory Guide 1.187, “Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments.” |
COL/ESP-ISG-026 | Interim Staff Guidance on Environmental Issues Associated with New Reactors |
OPEN The staff plans on updating NUREG-1555, Environmental Standard Review Plan: “Standard Review Plans for Environmental Reviews for Nuclear Power Plants.” |
COL/ESP-ISG-027 | Specific Environmental Guidance for Light Water Small Modular Reactor Reviews |
OPEN The staff plans to incorporate this guidance into the next revision of the Environmental Standard Review Plan and related guidance documents. |
DC/COL-ISG-028 | Interim Staff Guidance on Assessing the Technical Adequacy of the Advanced Light-Water Reactor Probabilistic Risk Assessment for the Design Certification Application and Combined License Application |
OPEN The staff intends to incorporate this guidance into the next revision of Regulatory Guide (RG) 1.200, Revision 2, “An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities” (ADAMS Accession No. ML090410014), RG 1.206, “Combined License Applications for Nuclear Power Plants” (ADAMS Accession No. ML070720184), and NUREG-0800, “Standard Review Plan (SRP) for the Review of Safety Analysis Reports for Nuclear Power Plants,” SRP Section 19.0 “Probabilistic Risk Assessment and Severe Accident Evaluation for New Reactors” (ADAMS Accession No. ML12132A481). |
COL-ISG-029 | Environmental Considerations Associated with Micro-reactors |
OPEN No decision has been made on how to incorporate this into permanent guidance. |