Information Notice No. 82-02:Westinghouse NBFD Relay Failures in Reactor Protection Systems at Certain Nuclear Power Plants
SSINS: 6835 Accession No.: 8107230046 IN 82-02 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C. 20555 January 27, 1982 Information Notice No. 82-02: WESTINGHOUSE NBFD RELAY FAILURES IN REACTOR PROTECTION SYSTEMS AT CERTAIN NUCLEAR POWER PLANTS Discussion: Westinghouse has notified the NRC of a higher-than-expected failure rate of Westinghouse type NBFD relay coils in reactor protection systems at certain power reactor plants. Investigation into the cause for failure revealed that, at high ambient temperature conditions, relay coils could fail due to the inductive voltage spike generated by the deenergization of the relay coil. It was also determined that the relay coil failures have been confined to normally energized relays used in the reactor protection systems where high ambient temperature conditions exist due to heat generated by the normally energized relays. To date, no failures of NBFD relay coils have been reported in safeguard cabinets where these relays are normally in a deenergized state and temperature conditions are normal. After reviewing the NBFD relay problem, Westinghouse issued technical bulletin NSD-TB-81-14 on December 7, 1981 to Westinghouse-designed power plants using BFD or NBFD relays in the reactor protection and safeguard systems. An extract of this bulletin is attached for your information and appropriate use. The bulletin provides interim test methods for verifying the operability of normally deenergized and energized NBFD relay applications and recommends replacement of NBFD relays manufactured prior to January 1, 1981. The bulletin also provides relay coil numbers as well as data codes to facilitate affected licensees' replacement efforts if required. This information notice is provided as an early notification of a potentially significant matter. It is expected that recipients will review the information for applicability to their facilities. No specific action or response is required at this time. If you have any questions regarding this matter, please contact the Regional Administrator of the appropriate NRC Regional Office. Attachments: 1. Extract of Westinghouse technical bulletin NSD-TB-81-14, dated 12/7/81 2. Recently issued IE Information Notices
Page Last Reviewed/Updated Tuesday, March 09, 2021
Page Last Reviewed/Updated Tuesday, March 09, 2021