Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Power Reactor Status Report for March 29, 2025

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 99 Steam Generator Limitations
Calvert Cliffs 1 100
Calvert Cliffs 2 60 Holding Power for Auto Voltage Regulator Testing *
FitzPatrick 100
Ginna 100
Hope Creek 1 100
Limerick 1 100
Limerick 2 93 Coastdown to Refueling Outage *
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 0 2025-03-17 Refueling Outage
Nine Mile Point 2 92 Reduced Power for Maintenance
Peach Bottom 2 100
Peach Bottom 3 100
Salem 1 94 Coastdown to Refueling Outage *
Salem 2 100
Seabrook 1 100
Susquehanna 1 100 *
Susquehanna 2 0 2025-03-24 Refueling Outage

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 0 2025-03-05 Refueling Outage
Browns Ferry 3 100
Brunswick 1 100
Brunswick 2 8 Performing Startup *
Catawba 1 100
Catawba 2 100
Farley 1 100
Farley 2 0 2025-03-16 Refueling Outage
Harris 1 100
Hatch 1 100
Hatch 2 0 2025-03-27 Maintenance Outage
McGuire 1 87 Coastdown to Refueling Outage
McGuire 2 100
North Anna 1 100
North Anna 2 0 2025-03-02 Refueling Outage *
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 0 2024-07-31 Extended Outage
Summer 100
Surry 1 100
Surry 2 100
Turkey Point 3 100
Turkey Point 4 0 2025-03-01 Refueling Outage *
Vogtle 1 100
Vogtle 2 0 2025-03-06 Refueling Outage *
Vogtle 3 100
Vogtle 4 0 2025-03-24 Maintenance Outage
Watts Bar 1 0 2025-01-17 Forced Outage
Watts Bar 2 100

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 100
Byron 1 100
Byron 2 94 Coastdown to Refueling Outage *
Clinton 99 100% Electrical Capability
D.C. Cook 1 0 2025-03-22 Refueling Outage
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 100
Dresden 3 100
Fermi 2 100
LaSalle 1 100
LaSalle 2 100
Monticello 95 Coastdown to Refueling Outage; Power Increased Following Rod Power Adjustment *
Perry 1 0 2025-03-17 Refueling Outage
Point Beach 1 0 2025-03-22 Refueling Outage
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 100
Quad Cities 1 0 2025-03-10 Refueling Outage *
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 70 Reduced Power for Isolation of Waterbox
Callaway 0 2025-03-29 Refueling Outage *
Columbia Generating Station 87 Coastdown to Refueling Outage
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 100
Grand Gulf 1 76 Reduced Power for Rod Pattern Adjustment *
Palo Verde 1 0 2025-03-28 Refueling Outage *
Palo Verde 2 100
Palo Verde 3 100
River Bend Station 1 0 2025-02-11 Refueling Outage
South Texas 1 100
South Texas 2 100
Waterford 3 94 Transformer Limitation
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.