The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for October 21, 2024

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 0 10/13/2024 Refueling Outage;
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100
Ginna 100
Hope Creek 1 100
Limerick 1 100
Limerick 2 100
Millstone 2 0 10/4/2024 Refueling Outage
*
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 100
Peach Bottom 2 0 10/21/2024 Refueling Outage
*
Peach Bottom 3 100
Salem 1 100
Salem 2 0 10/6/2024 Refueling Outage
Seabrook 1 0 10/5/2024 Refueling Outage
Susquehanna 1 100 Minimum 50 MVAR Generation
Susquehanna 2 100 Minimum 100 MVAR Generation

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 100
Browns Ferry 3 100
Brunswick 1 0 10/17/2024 Maintenance Outage
Brunswick 2 100
Catawba 1 0 10/1/2024 Refueling Outage
Catawba 2 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 100
Hatch 2 100
McGuire 1 100
McGuire 2 100
North Anna 1 98
Increasing Power
*
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 38 Holding Power; Issues with in-core detectors
Sequoyah 1 14 Synchronized to the grid;
Increasing Power
*
Sequoyah 2 0 7/31/2024 Refueling Outage
Summer 0 9/21/2024 Refueling Outage
Surry 1 100
Surry 2 92 Coastdown To Refueling Outage
*
Turkey Point 3 0 10/13/2024 Refueling Outage
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Vogtle 3 0 10/13/2024 Refueling Outage
Vogtle 4 100
Watts Bar 1 100
Watts Bar 2 100

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100
Braidwood 2 0 10/7/2024 Refueling Outage
Byron 1 100
Byron 2 100
Clinton 100
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 100
Dresden 3 94 Coastdown To Refueling Outage
Fermi 2 100
LaSalle 1 100
LaSalle 2 100
Monticello 100
Perry 1 100
Point Beach 1 100
Point Beach 2 0 10/12/2024 Refueling Outage
Prairie Island 1 0 9/21/2024 Refueling Outage
Prairie Island 2 100
Quad Cities 1 100
*
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 0 9/28/2024 Refueling Outage
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100


Comanche Peak 2 0 10/21/2024 Refueling Outage *
Cooper 0 9/29/2024 Refueling Outage
Diablo Canyon 1 100

Diablo Canyon 2 100
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 0 10/5/2024 Refueling Outage
Palo Verde 3 100
River Bend Station 1 100
South Texas 1 0 10/5/2024 Refueling Outage
South Texas 2 100
Waterford 3 94 Transformer Limitation.
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.
  • Additional plant status information is made available on the web page after 28 days.

Page Last Reviewed/Updated Monday, November 18, 2024