Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Power Reactor Status Report for May 13, 2024

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 0 2024-04-13 Refueling Outage *
Beaver Valley 2 100 *
Calvert Cliffs 1 100 *
Calvert Cliffs 2 100 *
FitzPatrick 100
Ginna 100
Hope Creek 1 7 Increasing Power *
Limerick 1 100 *
Limerick 2 100 *
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 100
Peach Bottom 2 100
Peach Bottom 3 100
Salem 1 100
Salem 2 100
Seabrook 1 100 *
Susquehanna 1 100 *
Susquehanna 2 100 *

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 100
Browns Ferry 3 100
Brunswick 1 100
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Farley 1 90 Increasing Power *
Farley 2 100
Harris 1 28 Increasing Power *
Hatch 1 100
Hatch 2 100
McGuire 1 100
McGuire 2 100
North Anna 1 100 *
North Anna 2 100 *
Oconee 1 100
Oconee 2 100
Oconee 3 0 2024-05-04 Refueling Outage
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 100
Summer 100
Surry 1 0 2024-04-07 Refueling Outage *
Surry 2 100 *
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Vogtle 3 100
Vogtle 4 99 Reduced Power For Secondary Flow Meter Maintenance
Watts Bar 1 100
Watts Bar 2 100

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100 *
Braidwood 2 100 *
Byron 1 100 *
Byron 2 100 *
Clinton 100
D.C. Cook 1 100 *
D.C. Cook 2 100 *
Davis-Besse 100 *
Dresden 2 100
Dresden 3 100
Fermi 2 55 Increasing Power Geomagnetic Disturbance Warning *
LaSalle 1 100 *
LaSalle 2 100 *
Monticello 100
Perry 1 0 2024-05-11 Maintenance Outage *
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 100 *
Prairie Island 2 42 Reduced Power For Maintenance *
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 0 2024-04-27 *
Arkansas Nuclear 2 100 *
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 0 2024-05-11 Maintenance Outage *
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 0 2024-04-07 Refueling Outage
Grand Gulf 1 41 Increasing Power *
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 12 Increasing Power *
River Bend Station 1 100
South Texas 1 100
South Texas 2 0 2024-05-13 Forced Outage; EN57124 * 1
Waterford 3 0 2024-03-21 Forced Outage *
Wolf Creek 1 93 Holding power for fuel conditioning *

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.