Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Power Reactor Status Report for February 01, 2024

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 100
Calvert Cliffs 1 88 Coastdown To Refueling Outage *
Calvert Cliffs 2 100
FitzPatrick 100
Ginna 100
Hope Creek 1 100
Limerick 1 99 Moisture Carryover Concerns *
Limerick 2 100
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 98 Moisture Separator Reheater Issue
Peach Bottom 2 62 Increasing Power *
Peach Bottom 3 100
Salem 1 100
Salem 2 100
Seabrook 1 100 Two Contingency Down Powers at 1100MWe and 900MWe
Susquehanna 1 100
Susquehanna 2 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 22 Increasing Power *
Browns Ferry 2 100
Browns Ferry 3 93 Coastdown To Refueling Outage *
Brunswick 1 100
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 86 Coastdown To Refueling Outage
Hatch 2 100
McGuire 1 100
McGuire 2 100
North Anna 1 100
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 100
Summer 100
Surry 1 100
Surry 2 100
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Vogtle 3 0 2024-01-28 Maintenance Outage *
Vogtle 4 0 Startup testing *
Watts Bar 1 100
Watts Bar 2 100 *

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 100
Byron 1 100
Byron 2 100
Clinton 99 100% Electrical Capability *
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 100
Dresden 3 100
Fermi 2 100
LaSalle 1 91 Coastdown To Refueling Outage *
LaSalle 2 100
Monticello 100
Perry 1 100
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 0 2023-10-07 Refueling Outage
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 100
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 100
River Bend Station 1 100
South Texas 1 100 *
South Texas 2 100
Waterford 3 0 2023-10-14 *
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.