Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Power Reactor Status Report for October 23, 2022

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 0 2022-10-09 Refueling Outage
Beaver Valley 2 100
Calvert Cliffs 1 100 *
Calvert Cliffs 2 100
FitzPatrick 100
Ginna 100
Hope Creek 1 0 2022-09-28 Refueling Outage
Limerick 1 100
Limerick 2 100
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 100
Peach Bottom 2 0 2022-10-17 Refueling Outage
Peach Bottom 3 100
Salem 1 100
Salem 2 100
Seabrook 1 100 One down power contingency due to ISO New England work
Susquehanna 1 92 Increasing Power *
Susquehanna 2 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 0 2022-10-01 Refueling Outage
Browns Ferry 2 100
Browns Ferry 3 100
Brunswick 1 100
Brunswick 2 100
Catawba 1 100
Catawba 2 0 2022-09-14 Refueling Outage
Farley 1 0 2022-09-18 Refueling Outage
Farley 2 100
Harris 1 0 2022-10-08 Refueling Outage *
Hatch 1 100
Hatch 2 100
McGuire 1 100
McGuire 2 100 C Heater Drain Tank Pump Maintenance *
North Anna 1 0 2022-09-21 Refueling Outage *
North Anna 2 100
Oconee 1 97 Coastdown To Refueling Outage *
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 0 2022-10-22 Refueling Outage *
Sequoyah 2 100
Summer 100
Surry 1 87 Coastdown To Refueling Outage
Surry 2 100
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Vogtle 3 0
Watts Bar 1 92 Reduced Power For Maintenance
Watts Bar 2 100

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 48 Increasing Power *
Braidwood 2 100
Byron 1 100
Byron 2 100
Clinton 100
D.C. Cook 1 100
D.C. Cook 2 0 2022-10-01 Refueling Outage
Davis-Besse 100
Dresden 2 100
Dresden 3 85 Coastdown To Refueling Outage *
Fermi 2 100
LaSalle 1 100
LaSalle 2 100
Monticello 100
Perry 1 100
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 0 2022-10-15 Refueling Outage
Prairie Island 2 100
Quad Cities 1 100
Quad Cities 2 65 Reduced Power For Sequence Exchange, Scram Timing Adjustment, and other Maintenance *

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 0 2022-10-08 Refueling Outage
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100
Comanche Peak 2 100 *
Cooper 0 2022-10-01 Refueling Outage
Diablo Canyon 1 100
Diablo Canyon 2 0 2022-10-15 Refueling Outage
Grand Gulf 1 95 Limited by Plant Service Water *
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 0 2022-10-08 Refueling Outage
River Bend Station 1 90 Reduced power following a transient per procedure *
South Texas 1 100
South Texas 2 0 2022-10-08 Refueling Outage
Waterford 3 100
Wolf Creek 1 0 2022-10-06 Refueling Outage

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.